Noted Executive 1 paper

Cabinet noted this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

Item17:

Resolved

1) That the Quarter 3 forecast £1.1m revenue monitoring overspend be noted. 2) That the expectation that Strategic Directors work to identify opportunities for spending plans to be collectively brought back in line with the Council’s overall budget by year end be noted. 3) That the additional in-year funding allocations for High Needs and Levy rebate announced as part of the 2019-2020 Finance Settlement and the Brexit funding allocation be noted. 4) That the forecast planned use of general fund earmarked reserves in-year, and the forecast year end position at £91.7m be noted. 5) That the anticipated overall forecast year end surplus of £5.8m on the Collection Fund be noted. 6) That the Quarter 3 forecast HRA surplus at £1.3m and forecast reserves position at year end of £54.1m be noted. 7) That the Quarter 3 forecast capital monitoring position, net of budgeted slippage, on line with budget, be noted. 8) That approval be given to the virement of £800k uncommitted capital budget from Risks and Pressures to support the Pioneer House Scheme. 9) That approval be given to the £500k commitment from the existing Town Centre Action Plan budget to contribute to the Pioneer House project. 10) That the proposed drawdown from the Strategic Investment Support reserve, for the proposed waste management revenue developments, be noted. 11) That approval be given to the garden waste containers and vehicles scheme (£1m) from the 2019-2020 Council approved capital plan, to enable early rollout from April 2019. 12) That the request for works to facilitate the relocation of Almondbury Library be approved.
Word for word from the decision Kirklees published for this meeting. Source: democracy.kirklees.gov.uk

Follow this further

Built from Kirklees's papers

What the report saysPro

Report to Cabinet

Purpose of the report

To receive information on financial monitoring for General Fund Revenue, Housing Revenue Account (HRA) and Capital Plan, as at Quarter 3 (month 10), 2018-19.

Key decision – is it likely to result in Yes spending or saving £250k or more, or to have a significant effect on two or more electoral wards? Key decision - is it in the Council’s Key decision - Yes Forward Plan (key decisions and private reports?

The Decision - Is it eligible for “call in” Yes by Scrutiny? Date signed off by Strategic Director & Rachel Spencer Henshall – 6 March 2019 name

Is it also signed off by the Service Eamonn Croston – 7 March 2019 Director for Finance?

Is it also signed off by the Service Julie Muscroft – 7 March 2019 Director – Legal, Governance & Commissioning? Cabinet member portfolio - Corporate Give name of Portfolio Holders Cllr Graham Turner

Electoral wards affected: None Ward Councillors consulted: None

Public or private: Public Have you considered GDPR? Yes, N/A

1. Summary General Fund

1.1The Council’s General Fund controllable (net) revenue budget for 2018-19 is £291.1m. The budget includes planned (net) revenue savings of £16.2m in 2018-19. 1.2 There is a forecast overspend of £1.1m against the £291.1m revised budget at Quarter 3; equivalent to 0.4% variance against revised budget. In summary, the council is making good progress with a forecast headline delivery of £12.4m against £16.2m planned savings; equivalent to 77% forecast delivery. The balance of forecast undelivered savings of £3.8m includes continued pressures on schools transport at £1.9m and volume pressures on external residential placements plus other volume led placements within Children’s at £1.2m. There are £2.7m net underspends elsewhere; details of which are included in the paragraphs further below in this report.

1.3The forecast revenue outturn as at Quarter 3 is summarised by Strategic Director Portfolios in Table 1 below.

Table 1 - Overview of 2018-19 general fund forecast revenue outturn position at Quarter 3

Annual forecast Strategic Revised Change from Director Budget Forecast Variance Quarter 2 Portfolios £000 £000 £000 £000 Children & Families 76,956 82,600 5,644 (2,862)

Adults & Health 107,386 106,908 (478) (464) Economy & Infrastructure 39,277 40,899 1,622 (455) Corporate Services 32,227 31,866 (361) (121)

Central Budgets 35,250 29,902 (5,348) 49

Grand Total 291,096 292,175 1,079 (3,673)

1.4It is expected that Strategic Directors continue to ensure as far as possible that management actions are taken between now and year end to manage down the remaining forecast overspend, to deliver an overall break-even positon for the Council for 2018-19.

Learning – High Needs

1.5There is currently a net £6.9m pressure identified within the High Needs funding block of the Dedicated Schools Grant, shown within Children and Families in Table 1 above. This includes a projected overspend figure of £3.6m in respect of placements of Kirklees children in independent and other local authority specialist provisions; compared to a £2.7m overspend in 2017-18. The average annual number of active placements in independent specialist provision has significantly increased over the last few years moving from an average of 88 active placements in 2016-17 to a forecast 2018-19 average of 121, an increase of 38%. An increase is also evident over the same period in the annual average number of children placed in other local authority specialist provision, moving from an average of 20 children in 2016-17 to a forecast average of 35 children.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Financial Monitoring Report Quarter 3 2018-19Report 495 KB DownloadRead as text

At this meeting

Whole meeting

More from Kirklees Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 8RESOLVED – 1) That the outcome of the Regulator of Social Housing inspection be noted. 2) That the Regulatory Improve... Noted Open
3 Nov 2026 10RESOLVED – 1) That the rent and service charge policy be approved. 2) That authority be granted to the Executive Dire... Approved Open
3 Nov 2026 12RESOLVED – 1) That approval be given to the Kirklees Employment Skills Framework 2026-2030 as the district-wide strat... Approved Open
6 Oct 2026 8RESOLVED – That the report be referred to the Meeting of Council on 21 October 2026 with the recommendations that Cou... Noted Open
6 Oct 2026 9RESOLVED 1) That approval be given to the disposal of the land and property within the Capital Receipts Schedule Octo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies