1) That approval be given to the business case, as attached at Appendix A to the considered report, which outlines the rationale for the schools’ condition programme, the availability of funding, the selection process and the main categories of work, thereby enabling the projects concerned to be designed, procured and implemented. 2) That approval be given to the detailed list of proposed works in schools, as attached at Appendix B of the considered report. 3) That the delegated authority, as set out at paragraphs 2.16 and 2.17 of the considered report be approved. 4) That the revised amendments and allocations to the 2018/2019 Schools Capital Maintenance programme applied under delegated authority, as detailed in Appendix C to the considered report, be noted.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
This report will identify potential projects, for Member approval, to be funded from the 2019/20 Learning and Early Support Capital Maintenance section of the Capital Plan and present an update on the delivery of the 2018/19 Capital Maintenance programme approved by Cabinet on 17 April 2018.
Key Decision - Is it likely to result in Yes, this report involves significant spending or saving £250k or more, or to expenditure in excess of £250K. have a significant effect on two or more electoral wards? Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private report?
The Decision - Is it eligible for “call in” by Yes Scrutiny?
Date signed off by Strategic Director & Karl Battersby - 8.03.2019 name
Date signed off by the Service Director - Eamonn Croston - 8.03.2019 for Finance?
Date signed off by the Service Director - Julie Muscroft - 7.03.2019 for Legal, Governance and Commissioning?
Cabinet member portfolio Corporate - Cllr Graham Turner Learning & Aspiration - Cllr Masood Ahmed Children - Cllr Viv Kendrick Electoral wards affected: All Ward councillors consulted: No Public or private: Public Report
Have you considered GDPR? There are no GDPR implications relating to this report. 1 1. Summary
1.1This report will identify potential projects to be funded from the Learning & Early Support Capital Maintenance baseline section of the Capital Plan which was approved by Council on 13 February 2019.
1.2Members will be asked to consider and approve the Capital Maintenance programme along with named projects so that they can be delivered in 2019/20 and to authorise delegated powers for officers to manage the programme.
1.3This report will also update Members regarding the delivery of the 2018/19 Learning & Early Support Capital Maintenance programme. It will report retrospectively on amendments authorised by officers using delegated powers approved by Cabinet on 17 April 2018.
2. Information required to take a decision
(a) Background
2.1In May 2018 the Department of Education (DfE) announced a fixed Schools Condition grant allocation for 2018/19 of £3.797M for Kirklees. This level of grant was also deemed to be indicative of the allocation for 2019/20. Members should note that this indicative allocation is reviewed annually by the DfE and will be subject to a DfE announcement early in the 2019/20 financial year.
2.2The methodology for calculating the allocations was changed in 2016 to take account of the following three components:
Core condition funding for all responsible bodies based on their pupil numbers; High condition needs funding for those with disproportionately high needs; and Floor protections to provide some stability in the transition to the new system.
The allocation methodology is to remain the same for the financial year 2019/20. This is to provide stability for responsible bodies while the DfE review the methodology for 2020–21 onwards.
2.3As noted above, grant allocations are revised annually to reflect new or closing schools and where a school moves to a new responsible body (e.g. Academy), in which case the pupil-led core condition funding will move with the schools. It is known that around five schools converted to Academy status during 2018/19 and that a reduction in Core Condition Funding for 2019/20 can therefore be expected to reflect the reduction in pupil numbers.
The five year Capital Plan 2019/20 to 2023/24 was approved by Council on 13 February 2019 and took into account an estimate of the expected reduction in grant in 2019/20 and hence, is set at £3.6M.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
2018/19 and 2019/20 Council Capital Plan: proposed allocation of 2019/20 Capital funding from the Directorate for Children's Learning & Early Support baseline section of the Capital Plan along with details of proposed amendments to the 2018/19 approved programme of worksReport
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.