RESOLVED – 1) That approval be given for work to commence on the implementation and delivery of the programme in Kirklees. 2) That approval be given to accept external funding of £2.3 million from the West Yorkshire Combined Authority to support delivery of the Programme in Kirklees, and for the Council to act as Accountable Body for the grant. 3) That authority be delegated to the Strategic Director Growth and Regeneration and the Service Director Legal, Governance and Commissioning to finalise and execute all necessary legal agreements with the West Yorkshire Combined Authority and the Council’s project delivery partners. 4) That authority be delegated to the Strategic Director Growth and Regeneration to implement the programme in Kirklees, including the commencement and award of any related procurement exercises. 5) That authority be delegated to the Strategic Director Growth and Regeneration and the Service Director Finance, to submit grant claims and to undertake related project monitoring and reporting.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
The report presents an update on Employment West Yorkshire, the West Yorkshire Combined Authority led programme proposed to replace and build on the current Employment Hub model to support people into work, apprenticeships and other learning and training opportunities . It details proposals to utilise the Employment West Yorkshire gainshare funding that has been allocated in principle to the Council , to extend the council led Works Better employability programme when the current ESF funding streams ends in December 2023 .
The report seeks Cabinet approval to enter into a funding agreement with West Yorkshire Combined Authority to receive funding to the value of £ 2.3 million to deliver Employment West Yorkshire in Kirklees between April 2023 and March 2025 and put in place the necessary officer delegations.
Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards?
Key Decision - Is it in the Council’s Forward Plan Key Decision - Yes (key decisions and private reports)?
Private Report/Private Appendix - No
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name David Shepherd – Yes 8th h December 2022
Is it also signed off by the Service Director for Eamonn Croston – Yes 8th December 2022 Finance?
Is it also signed off by the Service Director for Julie Muscroft – Yes - 9th December 2022 Legal Governance and Commissioning?
Cabinet member portfolio Councillor Graham Turner – Portfolio Holder for Growth and Regeneration
Electoral wards affected: All wards
Ward councillors consulted: Ward councillors have not been consulted because of the need to establish the scheme as soon as possible.
Public or private: Public.
Has GDPR been considered? Yes. Page 2 of the report
Summary
1.1The report presents an update on Employment West Yorkshire which is the title for the West Yorkshire Combined Authority led programme proposed to replace and build on the current WYCA Employment Hub model . In Kirklees Employment Hub funding has been used to part fund the Works Better Programme which is the council led employment programme funded by ESIF , Gainshare and Council funds.
1.2The aims of Works Better is to support people into work, apprenticeships and other learning and training opportunities . If offers an all age all employment information , advice and guidance service for resident aged 15 plus who live in Kirklees. Priority is given to those furthest from the labour market who are either not in work or in insecure low paid work.
1.3The report details proposals to utilise the Employment West Yorkshire Gainshare funding that has been allocated in principle to the Council , to extend the Works Better programme when the current ESIF funding streams come to an end in December 2023.
1.4The report also offers a high-level overview of current ESF funded provision as we prepare for the final year of delivery and to provide context to the proposals for Employment West Yorkshire.
2. Information required to take a decision
Background
Context
2.1Locally, the number of Kirklees residents in receipt of Universal Credit or other unemployment benefits has stabilised following unprecedented increases in April and May 2020 and the claimant rate currently stands at 4.1 % ( Nomis , UK)
2.2The Employment rate is also remains steady however the percentage of jobs in Kirklees paying below the Real Living Wage remains at 22% versus a national average of 17 % . ( WYCA , State of Region report , October 2022 )
2.3However there remains challenges around employment in Kirklees . Many Universal Credit claimants yet to be fully engaged by Jobcentre Plus and significant increase in demand for employment support is anticipated as the effects of the Cost of Living crisis are predicted to increase redundancies and in work poverty .
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.