1) That the proposals as set out at Appendix 2 (exempt) not be incorporated in the consultation draft Station to Stadium Enterprise Corridor Masterplan. 2) That approval be given to the Station to Stadium Enterprise Corridor Masterplan as contained in Appendix 1 of the report. 3) That authority be delegated to the Service Director for Skills and Regeneration to undertake a wider public consultation exercise to further inform the masterplan process. 4) That once consultation has been completed, the Strategic Director for Growth and Regeneration, in consultation with the Cabinet Member for Regeneration, be authorised to make all necessary changes to the masterplan and formally agree the plan. 5) That once finalised, the plan be published on the Council’s website to form the basis for informing investment decisions in the masterplan area. 6) That authority be given to officers to continue to develop the masterplan, its principles and the propositions as set out in the report with a particular emphasis on the next steps set out in section 5 of the considered report. 7) That approval be given for officers to begin work to put in place the appropriate planning framework for the area.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
This report seeks Cabinet endorsement of the Station to Stadium Enterprise Corridor Masterplan and to move to the next stage of development including wider consultation. It sets out why this is important, how it aligns with other economic development activity across Kirklees and what steps are required in order to help progress towards achieving the vision set out in the plan.
Key Decision - Is it likely to result in spending or Yes saving £250k or more, or to have a significant effect on two or more electoral wards?
Key Decision - Is it in the Council’s Forward Plan Key Decision - Yes (key decisions and private reports)?
Private Report/Private Appendix - Yes
The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director & name David Shepherd
Is it also signed off by the Service Director for Eamonn Croston Finance?
Is it also signed off by the Service Director for Julie Muscroft Legal Governance and Commissioning?
Cabinet member portfolio Councillor Graham Turner – Portfolio Holder for Regeneration
Electoral wards affected: Dalton and Newsome
Ward councillors consulted: None at this Stage
Public or private: Public (Appendix 2 and 3 Private).
Appendices to the Cabinet Report are set out below:
Appendix 1 - Station to Stadium Enterprise Corridor Masterplan (public) Appendix 2 - Gasworks Street – Alternative proposal (private) Appendix 3 - Gasworks Street – Strategic Outline Business Case (private)
The private Appendices are recommended for consideration in private in accordance with Schedule 12A of the Local Government Act 1972 namely they contain information relating to the financial and business affairs of the council and a third party. It is considered that disclosure of the information would adversely affect the commercial interests of a third party and therefore the public interest in maintaining the exemption, which would protect the rights of an individual or the council, outweighs the public interest in disclosing the information and providing greater openness in the council’s decision making
Has GDPR been considered? Yes. 1. Summary
This report seeks Cabinet endorsement of the Station to Stadium Enterprise Corridor Masterplan. It sets out the rationale, long term vision and principles of the plan as well as the next steps required to move towards delivery, including public consultation in early 2023.
2. Information required to take a decision
Background
2.1The Station to Stadium Enterprise Corridor represents one of the most exciting economic development opportunities in the Yorkshire region and beyond.
2.2Huge investment by Network Rail in the Transpennine Rail Upgrade is making Huddersfield (and the other towns on the route) one of the best-connected places in the North of England. The University of Huddersfield’s investment in the Health Innovation Campus at Southgate will put the town on the map globally in terms of translational health and wellbeing research and applied applications.
2.3Concurrently, the Council and its partners connected with the John Smiths Stadium have brought forward plans to secure the stadium’s long-term future.
2.4All of these core assets (TRU, the Health Innovation Campus and the Stadium) are connected by some of the town’s most striking architecture and heritage buildings but also interspersed with underutilised land and premises. This forms the basis of the strategic case and economic opportunity.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.