RESOLVED – That approval be given to the Strategic Director (Growth and Regeneration) in consultation with the Chief Executive, Service Director (Finance), Service Director (Legal, Governance and Commissioning), Cabinet Members for Regeneration and the Cabinet Member for Corporate Services to:- 1) Conduct negotiations with the current principal occupier- Huddersfield Town Association Football Club (HTAFC), with a view to HTAFC taking full operational control of the facility. 2) Conduct negotiations with other current leaseholders, etc as necessary 3) Agree terms that involve an element of debt write off (as detailed in the exempt appendix to the report) to facilitate such an agreement. 4) Enter into such any agreements on the Council’s behalf necessary to give effect to such an agreement if they are satisfied with such outcomes.
Word for word from the decision Kirklees published for this meeting.Source: democracy.kirklees.gov.uk
Name of meeting: Cabinet Date: 21st December 2022 Title of report: Kirklees Stadium Development Limited – Revisions to the previously agreed approach.
Purpose of report To review current arrangements for the standalone Stadium management and development business (Kirklees Stadium Development Limited or KSDL) that manages the Stadium for the benefit of the two professional sports clubs and the community.
Key Decision - Is it likely to result in Yes spending or saving £250k or more, or to Proposed spending in excess of £250k have a significant effect on two or more . electoral wards? Key Decision - Is it in the Council’s Yes Forward Plan (key decisions and private reports?) The Decision - Is it eligible for call in by Yes Scrutiny?
Date signed off by Strategic Director and David Shepherd – 08. 12 22 name
Is it also signed off by the Service Eamonn Croston 01.12.22 Director - Finance?
Is it also signed off by the Service Julie Muscroft – 01.12.22 Director -Legal Governance and Commissioning? Cabinet member portfolio Cllr Paul Davies Corporate Cllr Graham Turner Regeneration
Electoral wards affected: N/A
Ward Councillors consulted: N/A
Public or private: Public (Appendix A in private)
Appendix A of this report is in private in accordance with Schedule 12A of the Local Government Act 1972 namely it contains information relating to the financial and business affairs of a third party. It is considered that disclosure of the information would adversely affect KSDL and therefore the public interest in maintaining the exemption, which would protect the rights of an individual or the Council, outweighs the public interest in disclosing the information and providing greater openness in the Council’s decision making.
Has GDPR been considered? Yes 1. Summary
1.1Kirklees Stadium Development Limited (KSDL) was established originally in 1993. The current structure created a standalone Stadium management and development business to manage the Stadium for the benefit of both professional clubs, Huddersfield Town AFC (HTAFC) and Huddersfield Giants (HRLFC) as well as for the benefit of the community. This solution separated the assets from individual control of either of the clubs, procured the building of the new Stadium and has supported a decent quality facility over a 25- year period, with KSDL shareholders being Kirklees Council (40% shareholding), HTAFC (40% shareholding) and Huddersfield Sporting Pride – known as Huddersfield Giants or HRLFC (20% shareholding). 1.2 Whilst the arrangement enabled operation of the Stadium for more than 25 years, during 2020 and 2021 it was identified that for various reasons, relating to the need for additional investment- in refurbishment, it was appropriate to amend arrangements for the management to seek to ensure:
i) the Stadium did not become a source of reputational damage to the Council or financial burden to local taxpayers. ii) the long-term tenure of professional sport- HTAFC and HRLFC at the stadium. iii) financial sustainability over the longer term and delivery of longer-term Stadium operational investment requirements iv) complementary regeneration opportunities for an enterprise corridor between the Stadium and the town centre
1.3In March 2021, the Cabinet endorsed the development of a Community Trust operating model that was considered most suitable to delivering the above objectives, Cabinet also approved a complimentary regeneration opportunity for the strategic acquisition of a land asset. 1.4 Negotiations to create the Community Trust took place during Spring and Summer 2021 and made reasonable progress. However, two issues arose, which impeded that approach and now necessitate a revised approach. These relate to a change in the ownership of HTAFC (it reverting to the control of the previous owner), and matters related to historical liability. It has taken a further year to identify a solution with which all parties to KSDL are in broad agreement. This is set out in this report.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.