2009/10 Capital Programme (*)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 11 February 2009. Below is the council's own wording, with the papers it was decided on.

Item132

Resolved

RESOLVED – ( i ) That the Council, at its meeting due to be held on 4 th March 2009 be recommended to:- (a) approve t he ‘ passporting ’ of Government block allocations to the relevant service areas as discussed in section 4.3 of the report now submitted ; (b) approve the proposed new start schemes totalling £10.073m as detailed in paragraph 5.2 of the report now submitted; (c) approve the Capital Strategy set out in Appendix A to the report now submitted; and (ii) that the Cabinet Member with Portfolio for Finance and Information Technology be authorised to finalise the Cabinet’s proposal for a 2009/10 Capital Programme (on the basis of recommendation ( i ) (a) to (c) above) after undertaking further consultations as appropriate with Cabinet Member colleagues and having taken into consideration the various requests for additional capital investment set out in section 6 of the report and the potential funding sources set out in section 4 of the report and submit it to the Council meeting on 4th March 2009.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

The purpose of this report is to advise the Cabinet of the level of capital resources available for 2009/10 and future years and to propose a Capital Programme.

Recommendations

2.1Members of the Cabinet are recommended to make proposals to the Council meeting on 4 March 2009 in relation to the 2009/10 Capital Programme based upon the information set out in this report and the accompanying reports on the agenda.

2.2In making proposals in line with recommendation 2.1 above, Members of the Cabinet are recommended to:-

(a) endorse the policy of passporting Government block allocations to the relevant service areas as discussed in section 4 of this report;

(b) note the potential availability of capital receipts in 2009/10 of £4.000m (as discussed at paragraph 4.7 of this report);

(c) endorse the proposed new start schemes totalling £10.073m as detailed in paragraph 5.2 of this report; and,

(d) propose Council approval of the Capital Strategy set out in Appendix A to this report. 3. BACKGROUND

3.1There are a range of capital resources available to fund the Council’s 2009/10 capital programme. This report identifies those resources and provides details of proposed capital schemes for the 2009/10 programme. In addition, proposals for additional schemes arising from the Portfolio budget preparation process are identified for consideration for funding from available capital resources.

3.2The proposed capital programme has been prepared in line with the Council’s Capital Strategy, which is designed to ensure that the Council’s strategic priorities can be delivered. It outlines the process for the approval of capital projects and demonstrates a robust and transparent approach. It includes the use of a capital investment outline which sets out the details, impact and alignment to priorities of any given capital scheme. The Capital Strategy has been refreshed and is attached for approval at Appendix A.

4. 2009/10 CAPITAL RESOURCES

4.1The total capital resources available to the Council in 2009/10 equate to £42.076m which includes the rephasing discussed in the 2008/09 Budget Monitoring report elsewhere on this agenda.. It should be noted that the majority of these resources are already committed against schemes in the existing capital programme. The total resources are summarised in the table below and further details can be found at Appendix B:-

Para. Source of Funding £m Ref. 4.2 Existing 2009/10 Capital Programme Resources 23.896 4.3 Revenue Supported Borrowing 2.253 4.4 Capital Grant Allocations 11.471 4.5 Other Resources (including Revenue and Reserves) 0.085 Sub-total of Resources Allocated to Portfolios 37.705 4.6 2008/09 Unallocated Capital Receipts (forecast) 0.371 4.7 2009/10 Unallocated Capital Receipts (forecast) 4.000 Total Resources 42.076

4.2Existing 2009/10 Capital Programme Resources

This figure reflects previously approved rephasing of resources into 2009/10. All of these resources are already allocated to fund existing schemes. Details across Portfolios are shown in Appendix B. 4.3 Capital Block Allocations 2009/10

4.3.1 The Government provides capital funding to local authorities in two main ways:-

• Revenue Supported Borrowing (£2.253m in 2009/10) – this is approval to borrow a specified amount of money for which the Government will fund the repayment costs; and,

• Capital Grant Allocations (£11.471m in 2009/10) – this is provided to the Council as a lump sum and therefore removes the need to borrow (see section 4.4.1 below).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
2009/10 Capital Programme (*)Report 201 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. 2009/10 Capital Programme (*)This decision
  2. Capital Programme: 2026/27 Monitoring (*)Approved
  3. Capital Programme: 2025/26 Final Outturn (*)Agreed
  4. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Approved
  5. Capital Programme - 2025/26 and Future YearsApproved
  6. Capital Programme - 2025/26 and Future Years (*)Approved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies