08/00474/FUL

Deferred Planning 3 papers

Planning Committee deferred this item on Thursday 12 February 2009. Below is the council's own wording, with the papers it was decided on.

Item83c

Resolved

RESOLVED – That consideration of the application be deferred to a future meeting of the Committee to enable further information on the application to be submitted. (Note: In accordance with the provisions of Section 81 of the Local Government Act 2000, Councillor T Cunningham declared a personal interest in application no. , but remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Planning Committee

APPLICATION N0: 08/00474/FUL APPLICANT: [name removed] AFFECTED: Prescot West

DEVELOPMENT:

ERECTION OF WASTE GASIFICATION PLANT INCORPORATING A 50M HIGH CHIMNEY STACK AND 2 NO. SILO ENCLOSURES, TURBINE ROOM AND AIR COOLED CONDENSERS WITH ASSOCIATED SCREENING, CHP ROOM, SWITCH AND TRANSFORMER COMPOUNDS, TOGETHER WITH CONSTRUTION OF CAR PARKING AND NEW ACCESS AND ASSOCIATED WORKS

LOCATION OF SITE:

Land Opposite Contract Chemicals, Bounded By, Penrhyn Road/Villiers Road, Knowsley Business Park, Knowsley

PROPOSAL

The proposed Energy from Waste (EfW) facility would comprise a main building, 50m high chimney stack, turbine generator building, gasification plant, sub station and transformer compound, air cooled condenser, boiler house /CHP room and offices and associated parking. The external site areas would also include two weighbridges, site entrance and circulation road, 16 car parking spaces and cycle shelter. A new site entrance would be located off Villiers Road.

The facility would be designed to handle 80,000 tonnes of industrial and commercial waste, rising to a maximum of 96,000 tonnes if the feedstock is 100% residual municipal waste. It would not accept hazardous or clinical waste and it is anticipated that the vast majority of this material would comprise waste from Merseyside. The waste would be processed in two-stages. The first stage gasifies the waste to produce a synthetic gas. This gas is then transferred to a second stage where it burns more efficiently as fuel. The plant will have a capacity to produce a gross 9MW of electricity. The heat recovery steam generator then recovers energy from the flue gas allowing production of low pressure steam. The steam would then be used to produce the 9MW of electricity. The electricity would be supplied to adjacent businesses.

The proposed site was selected because of its proximity to energy intensive industrial consumers. It is intended that the proposal would be able to offer low cost secure energy to one or both of the adjacent chemical plants.

All waste material would be unloaded inside the main building which would be 19m above ground level at its highest point.

It is proposed that the facility would only accept the delivery of waste and the despatch of recyclates (e.g. paper, metals) and residues (untreatable waste e.g. ash and residues from flue gas cleaning process) off site during the hours of 07:30 to 18:00 hours on Monday to Friday and 08:00 to 13:00 on Saturdays. The internal processing of materials would operate on a 24 hour basis. A total of 18 staff would be employed on the site (12 full time and 6 part time). The application is accompanied by various reports including an Environmental Impact Assessment.

SITE AND SURROUNDINGS

The site lies within the Knowsley Business Park bounded by Penrhyn Road and Villiers Road. There is an existing area of hardstanding within the site adjacent to an existing access off Penrhyn Road. The remainder of the site comprises vacant land covered by scrub type vegetation with many trees lining the boundary along Villiers Road and part of the Penrhyn Road boundary.

The surrounding uses comprise a large chemical plant to the north of Penrhyn Road, a furniture manufacturing company to the east of the site, and a mix of modern industrial units and established industrial premises to the south of Villiers Road. The nearest individual dwelling to the site is Quarry Cottage on Ainsworth Lane within Knowsley Business Park which is 300m from the application site. On School Lane there is an individual dwelling 400m from the site and on Knowsley Lane there is an individual dwelling located 520m from the site.

HISTORY

K/7822 – Provision of loop road to service land for industrial development and provision of contractors compound for duration of works. – Granted January 1984.

REPRESENTATIONS

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08-00474-Location PlanPlan 81 KB Download
PDF
08-00474-ful-Site PlanPlan 410 KB Download
PDF
08/00474/FULReport 200 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. 08/00474/FULThis decision
  2. 25/00458/FUL and 25/00459/LBC - Huyton Cricket Club, Huyton Lane, Huyton, Knowsley, L36 7XHAgreed
  3. 26/00054/ful - change of existing use from a dwelling (use class c3) to a family assessment centre (use class c2) for a maximum of two families together with the conversion of existing detached garage to form an office ancillary to the famiDecided
  4. 25/00681/FUL - The Installation oF 3No Antennas, 1No GPS Node and Associated Ancillary Development Thereto - Chads Parade, Kirkby Town Centre, Knowsley, L32 8RDNoted
  5. 23/02710/FUL - Erection of 29N0. Dwellings (Consisting of 23No. Houses and 6No. Apartments) Together with Associated Infrastructure and Access from Greensbridge Lane - Land At Former Merseyside Dogs Home, Greensbridge Lane, Halewood, Knowsley, L35 1QH.Agreed
  6. 25/00568/FUL - Erection of 3 No. Dwellings - Land at Thursby Walk, Southdene, KirkbyDecided

More from Knowsley Planning Committee

All decisions
MeetingDecisionOutcome
9 Jul 2026 25/00458/FUL and 25/00459/LBC - Huyton Cricket Club, Huyton Lane, Huyton, Knowsley, L36 7XHRESOLVED – That:- (i) In respect of planning application 25/00458/FUL that delegated authority be granted to the Head... Agreed Open
9 Jul 2026 26/00054/ful - change of existing use from a dwelling (use class c3) to a family assessment centre (use class c2) for a maximum of two families together with the conversion of existing detached garage to form an office ancillary to the famiRESOLVED – That delegated authority be granted to the Head of Planning & Building Control to grant planning permissio... Decided Open
9 Jul 2026 25/00681/FUL - The Installation oF 3No Antennas, 1No GPS Node and Associated Ancillary Development Thereto - Chads Parade, Kirkby Town Centre, Knowsley, L32 8RDRESOLVED – That delegated authority be granted to the Head of Planning & Building Control to grant planning permissio... Noted Open
9 Jul 2026 Delegated Planning DecisionsRESOLVED – That the report be noted. Noted Open
4 Jun 2026 25/00638/COU - Change of Use of Residential Dwelling (Use Class C3) to Childrens Care Home (Use Class C2), for a Maximum of 2 No. Children - 24 Brookdale Grove, Huyton, Knowsley, L14 8AGRESOLVED – That the application be granted subject to t he conditions set out in the attached schedule, or such addit... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies