CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Knowsley Metropolitan Borough Council
Planning Committee, Thursday 12 February 2009 at 6.00pm

Publication and Information of Planning Applications

Noted Planning 1 paper

Planning Committee noted this item on Thursday 12 February 2009. Below is the council's own wording, with the papers it was decided on.

Item87

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Planning Committee

Purpose of report

The purpose of this report is to inform Members of the statistical analysis forwarded to the Department of Communities & Local Government covering the quarterly periods between 1 April 2008 and 31 December 2008.

Recommendation

That the report be noted.

Background

The Government’s targets for the national Best Value Performance Indicators are:-

• 60% of major applications to be determined within 13 weeks. • 65% of minor applications to be determined within 8 weeks. • 80% of all other applications to be determined within 8 weeks.

4. INFORMATION

a) i. Period 1 April 2008 to 30 June 2008

The Authority determined 157 valid applications within the three month period of which:-

2 (33%) of major applications were dealt with within 13 weeks. 27 (73%) of minor applications were dealt with within 8 weeks. 100 (87.7%) of all other applications were dealt with within 8 weeks.

a) ii. 91% of householder developments were dealt with within 8 weeks.

The overall average equates to 80.9%. b) i. Period 1 July 2008 to 30 September 2008

The Authority determined 159 valid applications within the three month period of which:-

3 (30%) of major applications were dealt with within 13 weeks. 25 (65.8%) of minor applications were dealt with within 8 weeks. 93 (83.8%) of all other applications were dealt with within 8 weeks.

b) ii. 85.4% of householder developments were dealt with within 8 weeks.

The overall average equates to 74.2%.

c) i. Period 1 October 2008 to 31 December 2008

The Authority succeeded in determining 188 valid applications within the three month period of which:-

6 (75%) of major applications were dealt with within 13 weeks. 35 (64.8%) of minor applications were dealt with within 8 weeks. 106 (84.1%) of all other applications were dealt with within 8 weeks.

c) ii. 90.3% of householder developments were dealt with within 8 weeks.

The overall average equates to 75.5%.

5. COMPARISON WITH OTHER MERSEYSIDE AUTHORITIES

Statistics have recently been published for the period 1 April 2008 to 30 September 2008. The percentage of all applications dealt with within 13 and 8 weeks for each Merseyside Authority is as follows:-

Major within Minor within All other Decisions 13 weeks 8 weeks. within 8 weeks.

Knowsley 49% 76% 88% Liverpool 49% 68% 74% St Helens 70% 85% 94% Sefton 77% 87% 93% Wirral 59% 76% 85%

6. RESOURCE IMPLICATIONS

Over the last 12 months there has been significant decrease in the number of planning applications. This trend has also been reflected in Knowsley. Over the same period there has been a significant resource input into the Kirkby application and appeal processes. This is currently ongoing. There have also been senior posts vacated during the period. These posts have still not been filled permanently pending the Directorate Restructure. By using temporary resources, to augment the established team, priorities have been re-ordered and the build up of caseloads during the summer of 2008 has been reduced and performance remains strong.

7. RISK ASSESSMENT

The report is for noting and there are no associated risks at this time.

8. IMPACT ON POPULATION GROUPS

None

9. COMMUNICATION ISSUES

There are no communication issues.

10. CONCLUSION

Performance remains above national targets for “minor” and “other” category applications and performance on major applications is improving. The build up of applications from 2008 will continue to be worked through in the next quarter and the impact of this on performance will be closely monitored. The development control team has dealt with some significant resource challenges during 2008. These challenges are continuing. The performance of the team against targets should hopefully be assisted by the finalisation of the ongoing Directorate Restructure.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Publication and Information of Planning ApplicationsReport 75 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Publication and Information of Planning ApplicationsThis decision
  2. Publication and information of planning applicationsNoted

More from Knowsley Planning Committee

All decisions
MeetingDecisionOutcome
9 Jul 2026 25/00458/FUL and 25/00459/LBC - Huyton Cricket Club, Huyton Lane, Huyton, Knowsley, L36 7XHRESOLVED – That:- (i) In respect of planning application 25/00458/FUL that delegated authority be granted to the Head... Agreed Open
9 Jul 2026 26/00054/ful - change of existing use from a dwelling (use class c3) to a family assessment centre (use class c2) for a maximum of two families together with the conversion of existing detached garage to form an office ancillary to the famiRESOLVED – That delegated authority be granted to the Head of Planning & Building Control to grant planning permissio... Decided Open
9 Jul 2026 25/00681/FUL - The Installation oF 3No Antennas, 1No GPS Node and Associated Ancillary Development Thereto - Chads Parade, Kirkby Town Centre, Knowsley, L32 8RDRESOLVED – That delegated authority be granted to the Head of Planning & Building Control to grant planning permissio... Noted Open
9 Jul 2026 Delegated Planning DecisionsRESOLVED – That the report be noted. Noted Open
4 Jun 2026 25/00638/COU - Change of Use of Residential Dwelling (Use Class C3) to Childrens Care Home (Use Class C2), for a Maximum of 2 No. Children - 24 Brookdale Grove, Huyton, Knowsley, L14 8AGRESOLVED – That the application be granted subject to t he conditions set out in the attached schedule, or such addit... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies