Resolved
RESOLVED – That the content of the consultation draft of the revised circular on cost awards in appeals and other planning proceedings, and their implications for Knowsley, be noted.
Planning Committee noted this item on Thursday 12 February 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED – That the content of the consultation draft of the revised circular on cost awards in appeals and other planning proceedings, and their implications for Knowsley, be noted.
1.1The purpose of this report is to inform Planning Committee members regarding the consultation draft of the revised circular on cost awards in appeals and other planning proceedings and its implications for Knowsley.
2.1It is recommended that members of Planning Committee note the consultation draft of the revised circular on cost awards in appeals and other planning proceedings and its implications for Knowsley. 3. BACKGROUND
3.1Current policy on the award of costs is contained within DOE Circular 8/93 and is well established. It has remained largely unchanged since its introduction.
3.2In 2007 the government consulted on a number of measures to improve the handling of appeals. The consultation proposed changes to the appeals process and also proposed an update to the costs circular in light of legislative and procedural changes that were likely to be brought forward. These changes are being introduced through various amendments to the Planning Acts and amendments to secondary legislation that will be introduced in April 2009.
3.3The current consultation seeks views on the revised costs circular. The Planning White Paper ‘Planning for a Sustainable Future’ published in May 2007 set out proposals which aimed to improve the speed, responsiveness and efficiency of the planning system.
4. SUMMARY OF MAIN CHANGES
4.1The proposed circular, amongst other things, emphasises the need to reflect updated legislation, clarifies the extent of full awards of costs and re-affirms examples of what can be regarded as unreasonable behaviour in the appeal process. 4.2 The draft circular does not change the fundamental principles on which the costs system is based. This is founded on the basis that an award of costs is likely if there is unreasonable behaviour by parties involved in an appeal. The areas of changes from DOE Circular 8/93 are principally:
• To enable costs to be awarded in appeals dealt with by written representations • Allow costs to be awarded in cases where the Planning Inspectorate determines the appeal method • To explain how costs can be sought even where appeals have been withdrawn before a date for a hearing or inquiry has been set, thereby encouraging parties to behave more responsibly in submitting appeals • To provide clearer examples of what might be considered unreasonable behaviour and also outline best practice to avoid costs awards.
5. IMPLICATIONS FOR KNOWSLEY
5.1The need to avoid unreasonable behaviour in the determination of planning applications and progressing appeals is well established. The revised circular provides clear examples of situations where a planning authority and other parties are at risk of an award of costs against. The award of costs regime now effectively covers all appeal methods as it will now include those appeals dealt with by written representations.
5.2Members and officers need to ensure that unreasonable behaviour is avoided. The examples provided are in the draft circular are in two categories “substantive” and “procedural” as follows:
Substantive
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Costs Awards in Planning Appeals and Other Proceedings Consultation on Revised CircularReport | 25 KB | DownloadRead as text |
Follow Planning Committee at Knowsley and we tell you when its next papers are published, before the meeting rather than after it.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.