RESOLVED - (i) That the rephasings and adjustments exceeding £1m requested by Portfolio Holders and totalling £8.725m as set out in paragraphs 4.1.3 and 4.1.4 of the report now submitted, be approved; (ii) that the revised phasing of the Capital Programme for 2010/11 of £79.681m as discussed in paragraph 4.1.5 of the report now submitted, be approved; (iii) that the capital expenditure to date of £37.602m and the expected impact on the delivery of the approved 2010/11 Capital Programme as set out in paragraph 4.1.6 of the report now submitted, be noted; (iv) that the revised three-year Capital Programme of £119.656m, of which £79.681m is programmed for 2010/11 as noted in section 5.2 and detailed in Appendix A of the report, be approved; (v) that the position on capital receipts in 2010/11 as discussed at section 5.4 of the report now submitted, be noted; (vi) that the proposal from the Cabinet Member with Portfolio for Children and Family Services for new schemes over £1m and totalling £2.676m be added to the Council’s 2011/12 Capital Programme as set out in paragraph 6.1.3 of the report now submitted; (vii) that the proposed approach to the capitalisation of early retirement and voluntary severance costs as set out in section 7.1 of the report now submitted, be endorsed; and (viii) that the revised approach to financing the Stockbridge Village Regeneration scheme as set out in section 7.2 of the report, be endorsed.
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
1.1This report presents an update on the Council’s Capital Programme and the current level of expenditure against the planned delivery profile for 2010/11.
1.2The report also advises the Cabinet of the level of capital resources available and proposes a revised Capital Programme for the Council for 2011/12 and future years.
Recommendations
Members of the Cabinet are recommended to:-
(i) Approve the rephasings and adjustments exceeding £1m requested by Portfolio Holders and totalling £8.725m as set out in paragraphs 4.1.3 and 4.1.4 of this report;
(ii) Approve the revised phasing of the Capital Programme for 2010/11 of £79.681m as discussed in paragraph 4.1.5 of this report;
(iii) Note the capital expenditure to date of £37.602m and the expected impact on the delivery of the approved 2010/11 Capital Programme as set out in paragraph 4.1.6 of this report; (iv) Approve the revised three-year Capital Programme of £119.656m, of which £79.681m is programmed for 2010/11 as noted in section 5.2 and detailed in Appendix A of this report.
(v) Note the position on capital receipts in 2010/11 as discussed at section 5.4 of this report;
(vi) Agree that the proposal from the Cabinet Member with Portfolio for Children and Family Services for new schemes over £1m and totalling £2.676m should be added to the Council’s 2011/12 Capital Programme as set out in paragraph 6.1.3 of this report;
(vii) Endorse the proposed approach to the capitalisation of early retirement and voluntary severance costs as set out in section 7.1 of this report; and,
(viii) Endorse the revised approach to financing the Stockbridge Village Regeneration scheme as set out in section 7.2 of this report.
Background
3.1There are a range of capital resources available to fund the Council’s Capital Programme. This report identifies those resources and provides details of proposed capital schemes. In addition, proposals for additional schemes arising from the Portfolio capital monitoring process are identified for consideration for funding from available capital resources.
3.2The proposed Capital Programme has been prepared in line with the Council’s Capital Strategy, which is designed to ensure that the Council’s strategic priorities can be delivered. It outlines the process for the approval of capital projects and demonstrates a robust and transparent approach. It includes the use of a capital investment outline which sets out the details, impact and alignment to priorities of any given capital scheme.
3.3As well as being an integral part of the planning process aimed to deliver high quality services and value for money, the Capital Strategy is also intrinsically linked with the Council’s Property and Asset Management Plans, and is designed to support the priorities emerging from this wider view of facilities and assets across the Borough.
3.4The Council’s Capital Strategy can be accessed on the Council’s intranet site and copies are available on request from the Borough Treasurer. 4. 2010/11 CAPITAL PROGRAMME
4.1Rephasings and Adjustments to the 2010/11 Capital Programme
4.1.1 The approved Capital Programme reflects adjustments arising from the 2010/11 monitoring position as last reported to the Cabinet on 20 October 2010. Any adjustments to the Programme since that time are explained within the body of this report and also summarised in Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.