Cabinet, Wednesday 13 February 2013 at 2.00pm

Capital Programme - 2012/13 Monitoring Update and Future Years (*)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 13 February 2013. Below is the council's own wording, with the papers it was decided on.

Item75

Resolved

RESOLVED – That:- (i) the revised Capital Programme for 2012/13 of £20.429m as discussed in section 4.1 of the report be approved ; (ii) t he capital expenditure in 2012/13 to date of £10.073m and the expected impact on the delivery of the approved capital programme as set out in paragraph 4.1.4 of the report be noted; (iii) the position on capital receipts as discussed at section 5.4 of the report be noted; (iv) the allocation of available capital receipts as discussed in section 5.4 of the report be noted; (v) the proposals from Portfolio Holders for new start schemes under £1m in 2013/14 and future years totalling £5.336m as discussed in paragraph 6.1.1 of the report be endorsed ; (vi) th e proposals for new start schemes over £1m totalling £1.648m in 2013/14 and £2.654m in 2014/15 to be added to the Council’s Capital Programme as set out in paragraph 6.1.2 of the report be approved; and (vii) the revised three-year Capital Programme of £50.047m , of which £20.429m is programmed for completion in 2012/13 as noted in paragraphs 6.1.4 and 6.1.5 and detailed at Appendix A of the report, be approved. (Note: That in accordance with Section 31 of the Localism Act 2011:- (a) all Members present declared a Disclosable Pecuniary Interest in the above item but, having received a dispensation from the Monitoring Officer, remained in the meeting, took part in the discussion and voted thereon; and (b) Councillors E Connor and [name removed] declared a Personal and Prejudicial Interest in the above item but, in accordance with the provisions of section 8.6 (f) of the Council’s Code of Conduct for Elected Members, remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report presents an update on the Council’s Capital Programme and the current level of expenditure against the planned delivery profile for 2012/13.

1.2The report also advises the Cabinet of the level of capital resources available and proposes a revised Capital Programme for the Council for 2013/14 and future years.

Recommendations

Members of the Cabinet are recommended to:-

(a) Approve the revised Capital Programme for 2012/13 of £20.429m as discussed in section 4.1 of this report;

(b) Note the capital expenditure in 2012/13 to date of £10.073m and the expected impact on the delivery of the approved capital programme as set out in paragraph 4.1.4 of this report;

(c) Note the position on capital receipts as discussed at section 5.4 of this report;

(d) Approve the allocation of available capital receipts as discussed in section 5.4; (e) Endorse the proposals from Portfolio Holders for new start schemes under £1m in 2013/14 and future years totalling £5.336m as discussed in paragraph 6.1.1 of this report;

(f) Approve the proposals for new start schemes over £1m totalling £1.648m in 2013/14 and £2.654m in 2014/15 to be added to the Council’s Capital Programme as set out in paragraph 6.1.2 of this report; and,

(g) Approve the revised three-year Capital Programme of £50.047m, of which £20.429m is programmed for completion in 2012/13 as noted in paragraphs 6.1.4 and 6.1.5 of this report and detailed at Appendix A.

Background

3.1There are a range of capital resources available to fund the Council’s Capital Programme. This report provides a summary of the resources available to fund capital expenditure, and of the programme of capital schemes.

3.2The proposed Capital Programme has been prepared in line with the Council’s Capital Strategy (which is available on request from the Director of Finance and Information Technology), which is designed to ensure that the Council’s strategic priorities can be delivered. The Strategy outlines the process for the approval of capital projects and demonstrates a robust and transparent approach. In this respect, it requires the use of a Capital Investment Outline document, which sets out the details, impact and alignment to priorities of any given capital scheme.

3.3As well as being an integral part of the planning process aimed at delivering high quality services and value for money, the Capital Strategy is also intrinsically linked with the Council’s Property and Asset Management Plans, and is designed to support the priorities emerging from this wider view of facilities and assets across the Borough.

4. 2012/13 CAPITAL PROGRAMME

4.1Rephasings and Adjustments to the 2012/13 Capital Programme

4.1.1 The approved Capital Programme reflects adjustments arising from the 2012/13 monitoring position as last reported to the Cabinet on 7 November 2012. Any adjustments to the Programme since that time are explained within the body of this report and also summarised at Appendix A. 4.1.2 Expenditure against approved schemes was last reported to Portfolio Holders in January 2013. Those reports to individual Portfolio Holders confirmed that capital expenditure planned for 2012/13 in a number of Portfolio areas would not be fully achieved by 31 March 2013. In view of this, rephasings and adjustments totalling £8.714m were proposed to the 2012/13 element of the Programme, bringing the revised Programme for the year to £20.429m. Of these, £2.624m have already been approved by Portfolio Holders and there are three remaining adjustments (totalling £6.090m) which individually exceed £1m and are therefore presented for approval by the Cabinet as outlined below.

4.1.3 Requests for Rephasing of Schemes over £1m

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: 2012/13 Monitoring Update and Future Years (*)Report 130 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Capital Programme - 2012/13 Monitoring Update and Future Years (*)This decision
  2. Capital Programme: 2026/27 Monitoring (*)Approved
  3. Capital Programme: 2025/26 Final Outturn (*)Agreed
  4. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Approved
  5. Capital Programme - 2025/26 and Future YearsApproved
  6. Capital Programme - 2025/26 and Future Years (*)Approved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies