Knowsley Metropolitan Borough Council
Cabinet, Wednesday 12 February 2014 at 2.00pm

Capital Programme - 2013/14 Monitoring Update and Future Years (*)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 12 February 2014. Below is the council's own wording, with the papers it was decided on.

Item70

Resolved

RESOLVED – That:- (i) the phasing of £4.402m in relation to elements of the Kirkby Town Centre Regeneration Programme to reflect the detailed timing of expenditure, as set out in paragraph 4.1.3 of the report, be approved; (ii) the proposed new start scheme for 2013/14 totalling £1.000m, as set out in paragraph 4.2.1 of the report, be approved; (iii) the capital expenditure to date in 2013/14 of £13.243m, as set out in paragraph 4.2.2 of the report, be noted; (iv) the revised Capital Programme for 2013/14 of £22.648m, as discussed in paragraph 4.2.4 of the report, be approved; (v) the position in relation to capital receipts, as discussed at section 5.4 of the report, be noted; (vi) the proposals for a new start scheme in 2015/16 totalling £1.206m to be added to the Council’s Capital programme, as set out in paragraph 6.1.2 of the report, be approved; and (vii) the revised three-year Capital Programme of £48.491m, as noted in paragraph 6.1.3 of the report and detailed at Appendix A, be approved. (Note:That in accordance with the provisions of Section 28(2) of the Localism Act 2011, and the Council’s Code of Conduct for Elected and Co-opted Members:- (a) Councillor G Morgan declared a Disclosable Pecuniary Interest in the above item but, having received a dispensation from the Monitoring Officer, remained in the meeting, took part in the discussion and voted thereon; and (b) Councillors E Connor, [name removed] and R Round declared a Personal and Prejudicial Interest in the above item but, in accordance with the provisions of Section 8.6(f) of the Council’s Code of Conduct for Elected Members, remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report presents an update on the Council’s Capital Programme and the current level of expenditure against the planned delivery profile for 2013/14.

1.2The report also advises the Cabinet of the level of capital resources available and proposes a Capital Programme for the Council for 2014/15 and future years.

Recommendations

Members of the Cabinet are recommended to:-

(a) Approve the phasing of £4.402m in relation to elements of the Kirkby Town Centre Regeneration Programme to reflect the detailed timing of expenditure as set out in paragraph 4.1.3 of this report;

(b) Approve the proposed new start scheme for 2013/14 totalling £1.000m as set out in paragraph 4.2.1 of this report;

(c) Note the capital expenditure to date in 2013/14 of £13.243m as set out in paragraph 4.2.2 of this report;

(d) Approve the revised Capital Programme for 2013/14 of £22.648m as discussed in paragraph 4.2.4 of this report; (e) Note the position in relation to capital receipts as discussed at section 5.4 of this report;

(f) Approve the proposals for a new start scheme in 2015/16 totalling £1.206m to be added to the Council’s Capital Programme as set out in paragraph 6.1.2 of this report; and,

(g) Approve the revised three-year Capital Programme of £48.491m as noted in paragraph 6.1.3 of this report and detailed at Appendix A.

Background

3.1There are a range of capital resources available to fund the Council’s Capital Programme. This report provides a summary of those resources and of the current programme of expenditure on capital schemes.

3.2The proposed Capital Programme set out in this report has been prepared in line with the Council’s Capital Strategy, which is designed to assist in delivering the Council’s strategic priorities. The Strategy outlines the process for the approval of capital projects and demonstrates a robust and transparent approach. In this respect, it requires the use of a Capital Investment Outline which sets out the details, impact and alignment with strategic priorities of any given capital scheme.

3.3As well as being an integral part of the planning process aimed at delivering high quality services and value for money, the Capital Strategy is also intrinsically linked with the Council’s Property and Asset Management Plans, and is designed to support the priorities emerging from this wider view of facilities and assets across the Borough.

4. 2013/14 CAPITAL PROGRAMME

4.1Rephasings and Adjustments to the 2013/14 Capital Programme

4.1.1 The approved Capital Programme currently reflects adjustments arising from the 2013/14 monitoring report to the Cabinet on 14 August 2013. A number of adjustments to the Programme have been considered by Portfolio Holders since then and are explained within the body of this report. The resultant Programme is summarised at Appendix A for the Cabinet’s formal approval. 4.1.2 Updates on expenditure against approved capital schemes were reported to the relevant Portfolio Holders in January 2014. Taken together, those reports to individual Portfolio Holders confirmed that the overall capital expenditure planned for 2013/14 would not be fully achieved by 31 March 2014. In view of this, rephasings and adjustments totalling £4.549m were approved by Portfolio Holders to the 2013/14 element of the Programme.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme: 2013/14 Monitoring Update and Future Years (*)Report 211 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Capital Programme - 2013/14 Monitoring Update and Future Years (*)This decision
  2. Capital Programme: 2026/27 Monitoring (*)Approved
  3. Capital Programme: 2025/26 Final Outturn (*)Agreed
  4. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Approved
  5. Capital Programme - 2025/26 and Future YearsApproved
  6. Capital Programme - 2025/26 and Future Years (*)Approved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies