Capital Programme Monitoring Update (*)

Approved Executive 1 paper

Cabinet approved this item on Wednesday 22 February 2017. Below is the council's own wording, with the papers it was decided on.

Item52

Resolved

RESOLVED – That (i) the proposals for four new start schemes over £1m to be added to the Council’s Capital Programme, as set out in paragraph 4.4 of the report, be approved; (ii) the capital expenditure to date in 2016/17 of £10.522m, as set out in paragraph 4.5 of the report, be noted; (iii) the revised Capital programme for 2016/17 of £17.912m, as discussed in paragraph 4.6 of the report, be approved; (iv) the position in relation to capital receipts, as discussed at section 5.4 of the report, be noted; (v) the proposed Prudential Indicators, as set out in paragraph 5.7 of the report and detailed at Appendix B, be approved; and (vi) the revised three-year Capital Programme of £44.427m, as outlined in paragraph 6.1.3 of the report, be approved. (Note:That in accordance with the provisions of Section 28(2) of the Localism Act 2011, and the Council’s Code of Conduct for Elected and Co-opted Members:- (a) Councillors A Moorhead, G J Morgan and [name removed] declared a Disclosable Pecuniary Interest in the above item but, having received a dispensation from the Monitoring Officer, remained in the meeting, took part in the discussion and voted thereon; and (b) Councillor Ms S O’Keeffe declared a Personal and Prejudicial Interest in the above item but, in accordance with the provisions of Section 8.6(f) of the Council’s Code of Conduct for Elected and Co-opted Members, remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting. Source: councillors.knowsley.gov.uk

Follow this further

Built from Knowsley's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1.1This report presents an update on the Council’s Capital Programme and the current level of expenditure against the planned delivery profile for 2016/17.

1.2The report also advises the Cabinet of the level of capital resources available and proposes a Capital Programme for the Council for 2017/18 and future years.

Recommendations

Members of the Cabinet are recommended to:-

(a) Approve the proposals for four new start schemes over £1m to be added to the Council’s Capital Programme as set out in paragraph 4.4 of this report;

(b) Note the capital expenditure to date in 2016/17 of £10.522m as set out in paragraph 4.5 of this report;

(c) Approve the revised Capital Programme for 2016/17 of £17.912m as discussed in paragraph 4.6 of this report;

(d) Note the position in relation to capital receipts as discussed at section 5.4 of this report;

(e) Agree the proposed Prudential Indicators as set out in paragraph 5.7 of this report and detailed at Appendix B; and, (f) Approve the revised three-year Capital Programme of £44.427m as outlined in paragraph 6.1.3 of this report.

Background

3.1There are a range of capital resources available to fund the Council’s Capital Programme. This report provides a summary of those resources and of the current programme of expenditure on capital schemes.

3.2The Capital Programme proposed in this report has been prepared in line with the Council’s Capital Strategy and Property and Asset Management Plans, which are designed to support the Authority’s priorities through a wider view of facilities and assets across the Borough. An update on the Capital Strategy is included in the Medium-Term Financial Strategy report elsewhere on this agenda.

4. 2016/17 CAPITAL PROGRAMME

4.1A number of adjustments to the Capital Programme have been made since the last monitoring report to the Cabinet on 21 September 2016. The resulting Programme is summarised at Appendix A for the Cabinet’s approval.

4.2Updates on expenditure against approved capital schemes were reported to the relevant Executive Directors in January 2017. As a result of this information, rephasing and adjustments under £1m to the 2016/17 element of the Programme totalling £1.548m have been approved by the relevant Executive Directors in consultation with the Executive Director (Resources).

4.3Since the last monitoring report to the Cabinet on 21 September 2016, the main additions to the Capital Programme have been the capital investments agreed by the Cabinet on 23 November 2016 (£0.813m in total) and the Kirkby Town Centre 3G Football Pitch scheme (£0.603m). The changes are summarised in Appendix A and full details of all amendments are available on request from the Executive Director (Resources).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Monitoring Update (*)Report 319 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Knowsley

Search all
  1. Capital Programme Monitoring Update (*)This decision
  2. Capital Programme: 2026/27 Monitoring (*)Approved
  3. Capital Programme: 2025/26 Final Outturn (*)Agreed
  4. Highways Capital Delivery Programme for 2027/28 and Highway Maintenance Revenue Programme for 2026/27Approved
  5. Capital Programme - 2025/26 and Future YearsApproved
  6. Capital Programme - 2025/26 and Future Years (*)Approved

More from Knowsley Cabinet

All decisions
MeetingDecisionOutcome
15 Jul 2026 Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App... Agreed Open
15 Jul 2026 2026/27 Revenue Budget - Quarter 1 Monitoring Update (*)RESOLVED – That:- (i) the key issues affecting 2026/27 budget monitoring as set out in this report be noted; and, (ii... Noted Open
15 Jul 2026 Capital Programme: 2026/27 Monitoring (*)RESOLVED – That the revised three-year Capital Programme of £118.011m in total as set out in section 4 and detailed i... Approved Open
15 Jul 2026 Local Government Association (Corporate Peer Challenge) - Progress Update on Delivery of Action PlanRESOLVED – That the draft Action Plan (attached at Appendix A) which sets out progress made to address the recommenda... Agreed Open
4 Jun 2026 2025/26 Revenue Budget Monitoring - Final Outturn Position (*)RESOLVED - That:- (i) the final 2025/26 budget monitoring position for the Council as set out in this report be noted... Noted Open