RESOLVED – That (i) the addition to the Capital Programme of planned expenditure on the Huyton Town Centre Regeneration Shop Frontages of £1.750m, as set out in paragraph 4.5 of the report, be approved; (ii) the revised Capital Programme for 2018/19 of £21.039m, as discussed in paragraph 4.6 of the report, be approved; and (iii) as a result of the above recommendations, the revised three-year Capital Programme of £87.804m, as outlined in paragraph 7.1 of the report, be approved. (Note: That in accordance with the provisions of Section 28(2) of the Localism Act 2011, and the Council’s Code of Conduct for Elected and Co-opted Members, Councillors G Morgan and [name removed] declared a Disclosable Pecuniary Interest in the above item but, having received a dispensation from the Monitoring Officer, remained in the meeting, took part in the discussion and voted thereon.)
Word for word from the decision Knowsley published for this meeting.Source: councillors.knowsley.gov.uk
1.1This report presents an update on the Council’s Capital Programme for 2018/19 and future years. As at 31 December 2018, 70% of the 2018/19 Capital Programme had been spent. While scheme managers have each confirmed that they plan to achieve their elements of the programme, there has historically been an element of unplanned rephasing at the end of each year. In light of this experience, the Capital Programme now reflects an assumption that over the coming months managers will identify the need to rephase up to 30% of the overall programme into future years. For 2019/20, the Executive Director (Resources) will establish processes to reflect the need for rephasings at an earlier stage in the monitoring and reporting process.
1.2Subject to consideration of an accompanying report on the Cabinet agenda, the revised Capital Programme will include the Shakespeare North Rail Interchange Prescot Transport scheme. The report also identifies one new scheme in excess of £1m to be approved by the Cabinet for addition to the Capital Programme; this is to reflect the commencement of expenditure on the Huyton Town Centre Regeneration Shop Frontages scheme (£1.750m), which involves the renovation of Council-owned and other properties to facilitate the regeneration of Huyton Town Centre.
1.3Based on current forecasts, there are no further unallocated receipts expected to be available in 2018/19 or in 2019/20. All receipts from Phase 2 and Phase 3 of the Housing Land Disposal Programme have been fully allocated to investments previously agreed by the Cabinet, the main such investment being the Shakespeare North Playhouse. 2. RECOMMENDATIONS
Members of the Cabinet are recommended to:-
(a) Approve the addition to the Capital Programme of planned expenditure on the Huyton Town Centre Regeneration Shop Frontages of £1.750m, as set out in paragraph 4.5 of this report;
(b) Approve the revised Capital Programme for 2018/19 of £21.039m as discussed in paragraph 4.6 of this report; and,
(c) As a result of the above recommendations, approve the revised three-year Capital Programme of £87.804m as outlined in paragraph 7.1 of this report.
Background
3.1There are a range of capital resources available to fund the Council’s Capital Programme. This report provides a summary of those resources and of the current programme of expenditure on capital schemes.
3.2The Capital Programme proposed in this report has been prepared in line with the Council’s Capital Strategy and Property and Asset Management Plans, which are designed to support the Authority’s priorities through a wider view of facilities and assets across the Borough.
3.3The Government has introduced a new requirement for the Council to approve a Capital Strategy which is aimed at explaining how the Council’s capital expenditure, capital financing, and treasury management activity contribute to the provision of local public services.
3.4The overall Capital Strategy is therefore comprised of this report, accompanied by the Council’s Treasury Management Strategy (reported to the Governance and Audit Committee on 4 February 2019), and the Capital and Investment Strategy report elsewhere on this agenda. Subject to consideration of those reports, the overall Capital Strategy will be considered by the Council at its meeting on 6 March 2019.
4. 2018/19 CAPITAL PROGRAMME
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Kirkby Town Centre Investment (*)RESOLVED – That:- (i) the grant of a new lease in Kirkby Town Centre on the headline commercial terms detailed at App...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.