CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
London Borough of Lambeth
Audit and Risk Committee, Monday 22 June 2026 at 5.30pm

Key Risk Summary (Q4 2025/26)

Decided Finance 2 papers

AI summaryLambeth Audit and Risk Committee is asked to consider the council's top risks at Q4 2025/26 and give feedback on assurance information in Appendix A. Top risks cover finance, cyber security, regulations, reputation, emergency planning and workforce.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedFeedback requested on Appendix A assurance information
MoneyNoneNo specific capital or revenue financial implications
What happens nextRisk appetite review in Q2 2026/27Survey, consultation session and feedback report planned
Who it affectsCouncil staff and membersRequired to make risk management a proactive tool

What was decided

The committee is to consider the key risks and assurance received at Q4 2025/26. Report P1

Members are asked to provide feedback on the additional assurance information included in Appendix A. Report P1

Why

The top risks at Appendix A relate to finance, cyber security, regulations, reputation, emergency planning and workforce, and are the council's most significant risks in terms of scope and potential impact on ambitions and financial stability. Report P19

The top risks are underpinned by approximately 60 Directorate level risks which may be escalated to corporate level if their likelihood or impact increase. Report P19

Assurance is built using the three lines of defence model: risk and control owners, risk management and compliance functions, and Internal Audit. Report 2.11

What happens next

The risk appetite statement and tolerance levels will be reviewed and updated in Q2 2026/27, involving a survey, consultation session and feedback report to Senior Leadership Team and Cabinet Members. Report 2.9

Corporate Directors will present their most significant Directorate risks to the committee on a cyclical basis, at least once a year, replacing the previous Risk Spotlight agenda items. Report P20

Future risk reports will provide an update on the revised risk appetite levels and process. Report 2.9

Options considered

  • Chosen: Treat: put further plans in place to bring the risk within appetite Report P22
  • Chosen: Tolerate: accept the risk at its current level Report P22
  • Chosen: Transfer: pass impacts to an insurance policy Report P22
  • Chosen: Terminate: stop the activity giving rise to the risk Report P22

Implications

  • Legal: Regulation 4 of the Accounts and Audit Regulations 2015 requires the council to have a sound system of internal control including arrangements for the management of risk.
  • Legal: Risk management supports the council's duties under the Civil Contingencies Act 2004 to manage risks affecting community safety. Report 8.0
  • Equalities: Departments should include identified EIA risks and control measures in their risk registers, and risk owners should be aware of equality implications when delivering controls. Report 7.3, 7.4
  • Financial: Improved risk management should lead to financial savings or cost avoidance by reducing incidents from unmanaged risks and identifying opportunities in line with the financial strategy. Report 3.2
  • Staffing: There are no staffing or accommodation implications arising from this report. Report 10.3
  • Climate: There are no environmental implications arising from this report. Report 10.1

Who and where

  • Council staff and members Report P28
  • Lambeth residents and community Report 8.0, P7

Timeline

  • Q4 2025/26: Period covered by the key risk summary in Appendix A Report P1, P19
  • Q2 2026/27: Risk appetite statement and tolerance levels to be reviewed and updated Report 2.9
  • 11/06/26: Report deadline and date final report sent Report P47

Plain English for the jargon

  • JCAD: The council's corporate risk management system used to hold and live-monitor corporate, strategic and operational risks
  • Three lines of defence: An assurance model: risk and control owners (first line), risk management and compliance (second line), Internal Audit (third line)
  • EIA: Equality Impact Assessment, used to identify differential impacts on different community groups
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the Committee Consider the key risks and assurance received at Quarter 4 2025/26. Provide feedback on the additional assurance information included in Appendix A
Word for word from the decision Lambeth published for this meeting. Source: moderngov.lambeth.gov.uk

Follow this further

Built from Lambeth's papers

What the report saysPro

Report to Audit and Risk Committee

Recommendation

1. To consider the key risks and assurance received at quarter 4 2025/26 2. To provide feedback on the additional assurance information included in Appendix A 1. CONTEXT

1.1The Council’s ongoing risk management aims are:

a. To give Members and Senior Officers an understanding of the key risks facing the Council and its community, and how these risks are being responded to. b. Ensure that risk management effectively supports the corporate governance of the Council. c. Ensure the process for identifying, evaluating, controlling, reviewing, reporting and communicating risks is in line with best practice, consistently applied and understood. d. To provide a strategic lead and champion risk management, increasing our capacity for risk, whilst maintaining our statutory responsibilities; and, e. To take a lead on developing and replicating best practice in risk management, providing value for money and enabling better outcomes

1.2The risk management framework – the below table summarises the key components of the Council’s risk management framework:

Risk Management Policy •Statement of intent on how the council will Statement approach risk management. It also includes a risk appetite statement.

Risk Managment strategy •Defines the activities and responsibilities for managing risk and reporting arrangements

•Register which records the key hazards and Community risk register risks that have potential to cause distruption to the local area •Register which records the most significant Corporate risk register corporate & strategic risks and who is responsible for managing them

•Register which records key directorate level Directorate risk registers (corporate/strategic) risks and who is responsible for managing them

•Register which records all divisional/team risks Divisional/team risk registers and who is responsible for managing them

Programme/Project risk •Register which records all programme/project Registers risks

2. PROPOSAL AND REASONS

2.1As displayed in the risk management framework table above, the Council’s risk register holds a variety of risks relating to several key areas. Risks are prioritised for reporting in accordance with the scoring methodology highlighted within the Risk Management Strategy 2023-26 - Lambeth’s risk scoring matrix is shown in Figure 1 below. Risk Scoring and Risk Appetite

2.2Figure 1: Lambeth’s risk scoring matrix:

very likely 4 8 16 32

likely 3 6 12 24 likelihood unlikely 2 4 8 16

very 1 2 4 8 unlikely minor significant serious major Impact

Risk identification and reporting processes 2.3 Risks are identified and assessed on an ongoing basis across all Divisions and Directorates. The Council’s corporate risk management system - JC Applications “JCAD” holds the corporate, strategic and operational risks identified across the Council. JCAD enables live monitoring and reporting of all categories of risk. The risk management team manage and develop the system and responsible officers (risk and control owners) access the risk system to review and update risks directly or provide risk updates to the risk team for importing into JCAD.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
updated key risk summary Q4 25-26Appendix A 461 KB Download
PDF
Key Risk Summary (Q4 2025/26)Report 570 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

5 of 6 attended
DA
Councillor David AmosChair, present
MW
Councillor Matt WilcockCommittee Member, present
JB
Councillor Jacqueline BondCommittee Member, apologies
JC
Councillor Judith CavanaghCommittee Member, present
MB
Councillor Matthew BryantCommittee Member, present
PM
Paula MillsCo-Optee, present

On this subject at Lambeth

Search all
  1. Key Risk Summary (Q4 2025/26)This decision
  2. Assurance on key Council risks held by the Growth and Environment DirectorateDecided
  3. Updated Key Risk Summary (Q3 2025/26)Agreed
  4. Key Risk Report Quarter 1Decided
  5. Key Risk Report Q3 2023/24Agreed
  6. Key Risk Report Q2 2023/24Agreed

More from Lambeth Audit and Risk Committee

All decisions
MeetingDecisionOutcome
23 Jul 2026 MinutesThe from the Audit and Risk Committee meeting held on the 22 June 2026, were agreed unanimously as an accurate record... Agreed Open
23 Jul 2026 Work Programme and Action Monitoring Log 2026-2027That the Committee Consider and agree the Audit and Risk Committees’ work programme for 2026 (Appendix A). Consider a... Agreed Open
23 Jul 2026 Counter Fraud Annual Report 2025/26That the Committee Consider outcomes of Counter Fraud annual report for 2025/26. Decided Open
23 Jul 2026 Annual Governance Statement 2025/26That the Committee Consider the findings of the review of the internal control system, and Approve the Annual Governa... Approved Open
23 Jul 2026 Report on Regulation of Investigatory Powers Act 2000That the Committee Note the contents of the report. Approve the Policy appended to this report covering: (a) Directed... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies