- That: (i) Approval be given for the publication of the joint East Lancashire Highways and Transport Master Plan, set out at Appendix 'A' to the report, now presented, and the delivery of the studies that will allow the masterplan to be taken forward; (ii) Approval, as part of this work, be given to the more detailed work necessary to establish whether there is a business case for a bypass, including what could ultimately be done along the North Valley to increase capacity as well as detailed consideration of all possible routes for an A56 Colne to Foulridge bypass.
Word for word from the decision Lancashire & Rossendale published for this meeting.Source: council.lancashire.gov.uk
In order to determine its future transport planning and investment priorities, and provide a sound and defensible basis for decisions affecting development across Lancashire, the County Council has embarked on an ambitious programme to put in place highways and transport masterplans to cover the county.
The East Lancashire Highways and Transport Masterplan is presented here for approval. The masterplan has been developed jointly with Blackburn with Darwen Council which is also intending to approve and publish this masterplan.
A public consultation exercise for the Consultation draft East Lancashire Highways and Transport Masterplan ran for seven weeks, finishing on 13 December 2013. The response to the consultation exercise has, on the whole, endorsed the County Council's vision for East Lancashire's highways and transport networks and for the work needed to take the masterplan forward.
A number of concerns and suggestions were raised through the consultation and a number of changes have been made to the draft Masterplan as a result. The two most significant of these concerns were:
• Representation received from stakeholders about the A56 Colne to Foulridge Bypass. Almost without exception, there is total support for the 'Brown' route amongst businesses and our partners. However, amongst the public, responses are more mixed, with a far wider range of opinions as to the merit of any bypass. It is therefore proposed to progress the more detailed work necessary to take a business case for the bypass forward, including what could ultimately be done along the North Valley to increase capacity in the absence of a bypass as well as detailed consideration of all possible routes for an A56 Colne to Foulridge bypass. Once this work has been completed we will be able to consult on our final proposals. • There was a significant response calling for the East Lancashire Railway to be utilised as a commuter link and incorporated into the proposals within the draft East Lancashire Highways and Transport Masterplan. We have therefore moved consideration of a potential commuter link from the rail connectivity study to the M66 corridor gateway study to ensure that the corridor is treated holistically and that a long term solution to congestion in the corridor is found.
According to the Masterplan's delivery programme, a number of studies will be undertaken to establish how highways and transport can best support the development of East Lancashire; these studies will look at rail connectivity, highways connectivity in key corridors, accessibility to employment, town centres and to remote and/or rural areas and will establish a strategic East Lancashire Cycle Network.
The joint East Lancashire Highways and Transport Masterplan is set out at Appendix 'A'.
The Consultation Reports in respect of the Masterplan as a whole and an A56 Colne to Foulridge bypass are set out at Appendices 'B' and 'C' respectively.
The accompanying Environmental Report, containing an Equality Impact Assessment (EIA) is set out at Appendix 'D'.
Recommendation
Cabinet is asked to:
(i) Approve the publication of the joint East Lancashire Highways and Transport Master Plan, presented at Appendix 'A', and the delivery of the studies that will allow the masterplan to be taken forward; (ii) Approve, as part of this work, the more detailed work necessary to establish whether there is a business case for a bypass, including what could ultimately be done along the North Valley to increase capacity as well as detailed consideration of all possible routes for an A56 Colne to Foulridge bypass.
Background and Advice
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.