Resolved
(i) The Committee requested that a revised submission be brought to the next TfL meeting. (ii) The Chair thanked [name removed] for his reports and presentations to the Committee.
LEP - Transport for Lancashire Committee decided this item on Monday 13 April 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
(i) The Committee requested that a revised submission be brought to the next TfL meeting. (ii) The Chair thanked [name removed] for his reports and presentations to the Committee.
East Lancashire Strategic Cycleway Network Strategic Outline Business Case - Independent Review Lancashire County Council April 2015 East Lancashire Strategic Cycleway Network Strategic Outline Business Case - Independent Review
Notice This document and its contents have been prepared and are intended solely for Lancashire County Council’s information and use in relation to the Independent Review of the Strategic Outline Business Case of the East Lancashire Strategic Cycleway Network.
Atkins assumes no responsibility to any other party in respect of or arising out of or in connection with this document and/or its contents.
This document has 19 pages including the cover.
Document history Job number: 5138421 Document ref: Revision Purpose description Originated Checked Reviewed Authorised Date Rev 1.0 Report KB GR GR NM 01/04/15
Atkins Independent Review | Version 1.0 | April 2015 | 5138421 East Lancashire Strategic Cycleway Network Strategic Outline Business Case - Independent Review
Table of contents Chapter Pages 1. Introduction 4
1.1Overview 4 1.2. Methodology 4 1.3. Structure of Report 7 2. Scheme Review 8
2.1Scheme Description 8 2.2. Strategic Case 8 2.3. Economic Case 8 2.4. Financial Case 8 2.5. Commercial Case 9 2.6. Management Case 9 2.7. Review Summary 10
Appendices 11 Appendix A. Assessment Scores 12
A.1. Summary 12 A.2. Strategic Case 14 A.3. Economic Case 15 A.4. Financial Case 16 A.5. Commercial Case 17 A.6. Management Case 18
Tables Table 1-1 Ranking mechanism of the scrutiny framework 4 Table 1-2 Aspects of the scrutiny framework 5 Table 2-1 Review summary table 10
Atkins Independent Review | Version 1.0 | April 2015 | 5138421 East Lancashire Strategic Cycleway Network Strategic Outline Business Case - Independent Review
1. Introduction 1.1. Overview Atkins has been commissioned by Lancashire County Council to undertake an independent review of their business case submissions which will be put forward to the Lancashire Enterprise Partnership (LEP) to seek and obtain funding via the Local Growth Deal.
We have created a scrutiny framework to review the business case submissions which has been developed based on the Department for Transport business case guidance. The guidance details how each case model is expected to address certain aspects of the scheme in the submission. Each case model within the business case has been assessed against those aspects and judged on how well they are addressed.
In line with the LEP’s Accountability Framework, it is recognised that a proportionate approach to the development of the business cases under review has been applied in the submitted business case documents. For schemes where the total costs are less than £5m, only a strategic outline business case has been developed, however, it is acknowledged that as these schemes are still seeking funding in full, some elements of outline and full business case submissions are required.
This document presents our review of the East Lancashire Strategic Cycleway Network Strategic Outline Business Case.
1.2Methodology The developed scrutiny framework has been based on a colour coded system that provides a transparent mechanism in assessing each case. Each individual aspect of the case model is given a colour of green, amber or red depending on:
How well it has been addressed in the submission; How relevant it is in relation to the scheme; and How well it meets the acceptability criteria set out in the DfT guidance and LEP Accountability Framework.
Table 1-1 Ranking mechanism of the scrutiny framework
Element under scrutiny Colour/ Description Score
No issues of note with the submission. Project to progress as Requirements fully met 1 scheduled.
Requirements substantially Minor issues exist with the submission. Project to progress 2 met and issues to be resolved.
Requirements partially met Medium issues exist with the submission. Project to progress 3 and issues to be resolved urgently.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
East Lancashire Strategic Cycle Network Scheme Funding Approval ApplicationReport | 830 KB | DownloadRead as text |
Follow LEP - Transport for Lancashire Committee at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Jan 2020 | South East Blackburn Funding ApplicationThat the Lancashire Enterprise Partnership Board be recommended to grant the scheme a maximum of £9.05m Growth Deal f... | Decided | Open |
| 5 Jun 2019 | Matters ArisingThat the update be noted . | Noted | Open |
| 5 Jun 2019 | Preston Western Distributor Funding ApplicationThat the Lancashire Enterprise Partnership be recommended to grant the scheme a maximum £58m Growth Deal funding, sub... | Approved | Open |
| 5 Jun 2019 | Preston Rail Station HS2 Hub - Assessment of Wider Economic benefitsThat the contents of the report be noted. | Noted | Open |
| 5 Jun 2019 | Exclusion of Press and Public- That the press and members of the public be excluded from the meeting during consideration of the following item of... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.