Lancashire County Council / Rossendale Borough Council
Cabinet, Thursday 1 February 2018 at 2.00pm

Bacup Townscape Heritage Initiative

Agreed Executive 3 papers

Cabinet agreed this item on Thursday 1 February 2018. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

That: i. the County Council enter into a S278 agreement under which it will accept staged payments totalling £320,000 from Rossendale Borough Council together with any other additional financial resources for the project that may be agreed, on the condition that payments are received and added to the Highways block of the 2015/16 capital programme in advance of any application for payment from the appointed contractor; and that the final wording of the Agreement be agreed under the present delegations for S278 Agreements. ii. the introduction of a three Zebra crossing arrangement and markings as set out in the report be approved.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Executive summary

This report seeks approval of a public realm improvement scheme and related funding arrangements proposed within Bacup Town Centre. The scheme relies on both County Council and Heritage Lottery funding (HLF).

As part of the public realm works, it is proposed to create three Zebra crossings, located on Market Street, St James Square and Yorkshire Street.

A Section 278 Agreement is being drafted that will be used to safeguard the County Council's financial position.

This is deemed to be a Key Decision and the provisions of Standing Order No. 25 have been complied with.

Recommendation

The Cabinet is recommended to:

(i) Approve that the County Council will enter into a S278 agreement under which it will accept staged payments totalling £320,000 from Rossendale Borough Council together with any other additional financial resources for the project that may be agreed, on the condition that payments are received and added to the Highways block of the 2015/16 capital programme in advance of any application for payment from the appointed contractor. The final wording of the Agreement will be agreed under the present delegations for S278 Agreements. (ii) Approve the introduction of a three Zebra crossing arrangement and markings as advertised and set out on the drawings attached at Appendix 'A'.

Background and Advice

The Bacup Townscape Heritage Initiative (THI), promoted by Rossendale Borough Council (RBC), who are the accountable body for the HLF, is a public realm improvement scheme proposed on St James Square and associated adjacent side roads of Bacup Town Centre. The scheme relies on both County Council and HLF funding.

The County Council has provided an estimating and design service to RBC in connection with the development of these proposals in so far as they relate to highway improvements. The design has gone through numerous iterations that have been steered by the THI Board representatives consisting of local business owners, Borough and County Councillors and public consultation.

The proposed improvements are on land which is predominately dedicated as public highway, with a small proportion of RBC owned land. RBC has agreed in principle to enter into a S278 Agreement with the County Council, to enable the County Council to procure the works through an external tender arrangement and subject to the tender price being in line with the available budget, supervise the construction stage.

The County Council has previously approved an allocation of £422,000 from the highways block of the 2015/16 capital programme. The staged payments totalling £320,000 from RBC will allow for a total project budget of £758,500 including the credit of £16,500 for previous design iterations. The County Council and HLF will pay for two separate pieces of work and both of these must be within the respective financial requirements for the scheme to be affordable and contract award made.

As stated above, the County Council and RBC have agreed, in principle, to enter into a Section 278 Agreement with terms to be agreed prior to progressing to the construction stage. RBC will undertake a due diligence review of the S278 Agreement process and once satisfied with the conditions the construction phase will proceed on this basis.

Cabinet is also requested to approve the introduction of three Zebra crossings, located on Market Street, St James Square and Yorkshire Street.

Consultations

RBC have arranged public consultation of the scheme and responses received have informed the final design, in addition specific statutory consultation has been undertaken in relation to the zebra crossings.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
(Location Plan)Appendix A 830 KB Download
PDF
Bacup Townscape Heritage InitiativeReport 99 KB DownloadRead as text
PDF
View item 8. as DOC 154 KBReport 3 pages Download

At this meeting

Whole meeting
3Minutes of the Meeting held on 18 January 2018Agreed 4Department for Transport Consultation: Shaping the Future of England's Strategic RoadsApproved 5Proposed 40mph Speed Limit at Briars Lane, Lowry Hill Lane and Course Lane, NewburghApproved 6Lancashire County Council (Various Roads, Chorley, Fylde, Pendle, Preston, Rossendale, South Ribble, West Lancashire and Wyre Boroughs) (Revocation, 30mph, 40mph, 50mph and De-Restricted Road (August No1) Speed Limits) Order 201*Approved 7McKenzie Street and Station Road, Bamber Bridge, South Ribble Borough Revocation, prohibition of Waiting and Restriction of Waiting Traffic Regulation OrderApproved
8Bacup Townscape Heritage InitiativeThis decision
9Highways and Transport Capital ProgrammeApproved 10Highway Pothole Repair PolicyApproved 25Capital Strategy for Schools – Condition Led Capital Investment Programme, 2017/18 and part 2018/19Approved 11Determination of Relevant Area for Consultation on Admission Arrangements for Lancashire Maintained Schools and Academies for 2020/21, 2021/22 and 2022/23Decided 12Determination of Admission Arrangements for Lancashire Community and Voluntary Controlled Schools 2019/20Approved 13Co-ordinated Admissions Scheme 2019/20 - Determination of the Qualifying SchemeApproved 14Joint Commissioning Arrangements for Children and Young People's Special Education Needs or Disabilities Provision - North LancashireAgreed 15Implementation of the Care Act 2014 - Approval of Revised Adult Social Care Policies and Procedures incorporating Information & Advice and Prisons and Approved PremisesApproved 22Preliminary Review of the County Council Policy on Fire Suppression Measures in Schools ahead of Government DirectionApproved 19Exclusion of Press and PublicDecided 20Asset ManagementPrivate 21Preston Western Distributor, East West Link Road and Cottam Link Road and Realignment of Footpath Network - Making (Signing and Sealing) and advertising of the Lancashire County Council (Preston Western Distributor, East West Link and CottaPrivate 23Clitheroe Ribblesdale High School -Proposed Capital Project to Facilitate School ExpansionPrivate

Who was there

8 of 8 attended
CG
CC G DriverChair, present
CA
CC A AtkinsonDeputy Chair, present
CM
CC M GreenCommittee Member, present
CS
CC S CharlesCommittee Member, present
CK
CC K IddonCommittee Member, present
CP
CC P BuckleyCommittee Member, present
CG
CC G GoochCommittee Member, present
CS
CC S TurnerCommittee Member, present

On this subject at Lancashire & Rossendale

Search all
  1. Bacup Townscape Heritage InitiativeThis decision
  2. Bacup Townscape Heritage Initiative - Experimental Traffic Regulation OrderDecided

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies