Lancashire County Council / Rossendale Borough Council
Cabinet, Thursday 1 February 2018 at 2.00pm

Highways and Transport Capital Programme

Approved Executive 9 papers

Cabinet approved this item on Thursday 1 February 2018. Below is the council's own wording, with the papers it was decided on.

Item9

Resolved

That: i. the proposed amendments to the s be approved. ii. the proposed Additional 2017/18 Urban Unclassified Capital Programme be approved . iii. the proposed Road Safety Programme Assessment Criteria be approved. iv. the proposed Additional 2017/18 Road Safety Programme be approved
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Executive summary

As part of the normal process of service delivery the approved Highways and Transport Capital Programmes now require certain amendments in order to meet emerging priorities and to respond to some unanticipated service demands. The proposed amendments are set out at Appendix 'A'.

The report also seeks approval of the proposed Additional 2017/18 Urban Unclassified Capital Programme at Appendix 'B', the proposed Road Safety Programme Apportionment Criteria at Appendix 'C', and the proposed Additional 2017/18 Road Safety Programme at Appendix 'D'.

This is deemed to be a Key Decision and the provisions of Standing Order No. 25 have been complied with.

Recommendation

The Cabinet is recommended to:

(i) Approve the proposed amendments to the Highways and Transport Capital Programmes as outlined at Appendix 'A'. (ii) Approve the proposed Additional 2017/18 Urban Unclassified Capital Programme at Appendix 'B'. (iii) Approve the proposed Road Safety Programme Assessment Criteria at Appendix 'C'. (iv) Approve the proposed Additional 2017/18 Road Safety Programme at Appendix 'D'. Background and Advice

Proposed Changes to the Highways and Transport Capital Programmes

The following detailed highway and transport capital programmes of work have previously been approved by the Cabinet Member for Highways and Transport;

 2014/15 New Starts Programme - 27 January 2014  2015/16 New Starts Programme - 5 March 2015  2016/17 New Starts Programme - 18 April 2016  2017/18 New Starts programme - 13 March 2017

As part of the normal process of service delivery these detailed programmes of work now require certain amendments in order to meet the emerging priorities and to respond to some unanticipated service demands. The proposed amendments are set out at Appendix 'A'.

Proposed Additional 2017/18 Urban Unclassified Capital Programme

On 20 July 2017, Full Council approved revisions to the 2017/18 Budget that included additional capital and revenue funding for highway maintenance. On 10th August 2017, Cabinet approved the apportionment of the capital funding including an allocation of £3 million to improve the condition of the urban unclassified network, in line with highway condition data.

During November and December 2017 the Cabinet Member for Highways and Transport invited all county councillors to attend one of twelve district workshops to discuss the proposed programme. The workshops were an opportunity to explain to county councillors how the programme had been developed and for county councillors to be given the opportunity share their local knowledge of the condition of highways in their divisions. The feedback from the workshops has been taken into account in developing the proposed programme detailed at Appendix 'B'.

Proposed Additional 2017/18 Road Safety Programme

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 62 KB Download
PDF
Appendix BAppendix B 68 KB Download
PDF
Appendix CAppendix C 55 KB Download
PDF
Appendix DAppendix D 42 KB Download
PDF
Highways and Transport Capital ProgrammeReport 105 KB DownloadRead as text
PDF
View as DOCX (9./2) 28 KBAppendix 3 pages Download
PDF
View as DOCX (9./4) 15 KBAppendix 1 pages Download
PDF
View as DOCX (9./5) 14 KBAppendix 2 pages Download
PDF
View item 9. as DOC 158 KBReport 3 pages Download

At this meeting

Whole meeting
3Minutes of the Meeting held on 18 January 2018Agreed 4Department for Transport Consultation: Shaping the Future of England's Strategic RoadsApproved 5Proposed 40mph Speed Limit at Briars Lane, Lowry Hill Lane and Course Lane, NewburghApproved 6Lancashire County Council (Various Roads, Chorley, Fylde, Pendle, Preston, Rossendale, South Ribble, West Lancashire and Wyre Boroughs) (Revocation, 30mph, 40mph, 50mph and De-Restricted Road (August No1) Speed Limits) Order 201*Approved 7McKenzie Street and Station Road, Bamber Bridge, South Ribble Borough Revocation, prohibition of Waiting and Restriction of Waiting Traffic Regulation OrderApproved 8Bacup Townscape Heritage InitiativeAgreed
9Highways and Transport Capital ProgrammeThis decision
10Highway Pothole Repair PolicyApproved 25Capital Strategy for Schools – Condition Led Capital Investment Programme, 2017/18 and part 2018/19Approved 11Determination of Relevant Area for Consultation on Admission Arrangements for Lancashire Maintained Schools and Academies for 2020/21, 2021/22 and 2022/23Decided 12Determination of Admission Arrangements for Lancashire Community and Voluntary Controlled Schools 2019/20Approved 13Co-ordinated Admissions Scheme 2019/20 - Determination of the Qualifying SchemeApproved 14Joint Commissioning Arrangements for Children and Young People's Special Education Needs or Disabilities Provision - North LancashireAgreed 15Implementation of the Care Act 2014 - Approval of Revised Adult Social Care Policies and Procedures incorporating Information & Advice and Prisons and Approved PremisesApproved 22Preliminary Review of the County Council Policy on Fire Suppression Measures in Schools ahead of Government DirectionApproved 19Exclusion of Press and PublicDecided 20Asset ManagementPrivate 21Preston Western Distributor, East West Link Road and Cottam Link Road and Realignment of Footpath Network - Making (Signing and Sealing) and advertising of the Lancashire County Council (Preston Western Distributor, East West Link and CottaPrivate 23Clitheroe Ribblesdale High School -Proposed Capital Project to Facilitate School ExpansionPrivate

Who was there

8 of 8 attended
CG
CC G DriverChair, present
CA
CC A AtkinsonDeputy Chair, present
CM
CC M GreenCommittee Member, present
CS
CC S CharlesCommittee Member, present
CK
CC K IddonCommittee Member, present
CP
CC P BuckleyCommittee Member, present
CG
CC G GoochCommittee Member, present
CS
CC S TurnerCommittee Member, present

On this subject at Lancashire & Rossendale

Search all
  1. Highways and Transport Capital ProgrammeThis decision
  2. Lancashire County Council Highways and Transport Strategy 2023-25Approved
  3. Proposed Amendments to the Highways and Transport Capital ProgrammesApproved
  4. Proposed Amendments to the Highways and Transport Capital ProgrammesApproved
  5. Proposed Amendments to the Highways and Transport Capital ProgrammesApproved
  6. Proposed Changes to the Highways and Transport Capital ProgrammesApproved

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies