Highway Maintenance Capital Programme – Recycled Materials from Samlesbury Enterprise Zone

Approved Executive 2 papers

Cabinet approved this item on Thursday 8 June 2023. Below is the council's own wording, with the papers it was decided on.

Item7

Resolved

That The revised approach set out in the report be approved, and it be noted that this may mean changes to the programme previously agreed; The Executive Director for Growth, Environment and Transport be authorised, in consultation with the Cabinet Member for Highways and Transport, to agree which schemes will go forward in the overall programme; and Any residual material be incorporated into the road base for the M55 to Heyhouses Link Road, where it was cost effective to do so.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Recommendation

Cabinet is asked to:

(i) Approve the revised approach set out in the report, and note that this may mean changes to the programme previously agreed.

(ii) Authorise the Executive Director for Growth, Environment and Transport, in consultation with the Cabinet Member for Highways and Transport, to agree which schemes will go forward in the overall programme.

(iii) Approve that any residual material can be incorporated into the road base for the M55 to Heyhouses Link Road where it is cost effective to do so. Detail

In March 2023, Cabinet approved the 2023/24 Highway Block of the Capital Programme including resurfacing schemes with a value of £1.865 million to be funded via the redevelopment of the Samlesbury Enterprise Zone.

These additional schemes were based on an opportunity to utilise the recycled material from the Samlesbury Enterprise Zone to allow additional highway maintenance carriageway schemes to be delivered, as well as preventing material being sent to landfill. The Enterprise Zone redevelopment is now drawing to a close and the site is being cleared by October 2023, giving a limited window of opportunity to the county council.

In May Cabinet approved a further scheme to utilise this material. However, further investigation has identified that some of the initial schemes identified have been found to be not suitable as recipient sites. In the main, this is due to the nature of the existing carriageway construction and issue relating to the disposal of the material to be removed from those roads.

There are also operational difficulties at present in identifying further suitable recipient schemes that meet the requirements within the timeframe for obtaining the necessary approval.

Taken together, these issues mean that there is a need for the council to develop a flexible approach that can react quickly and flexibly to ensure the most efficient and effective use of this recycled material.

It is therefore proposed that the original schemes approved in March 2023 are revised to establish this new flexible approach.

It is proposed that any further proposed schemes to utilise material from the Samlesbury Enterprise Zone be in line with the Transport Asset Management Plan prioritisation process agreed by the Executive Director for Growth, Environment and Transport, in consultation with the Cabinet Member for Highways and Transport.

There may be some residual material that cannot be used for highway maintenance schemes. It is proposed that this material be incorporated into the road base for the M55 to Heyhouses Link Road. This would allow for utilisation of the recycled material as opposed to sending it to landfill, providing cost efficiency on both projects.

This does not affect the proposed work to the A682 Rawtenstall Spur: Haslingden Road to A56 Lancashire Boundary, which will proceed as a scheme already approved.

Consultations

N/A

Implications:

This item has the following implications, as indicated: Financial management

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Maintenance Capital Programme: Recycled Materials from Samlesbury Enterprise ZoneReport 160 KB DownloadRead as text
PDF
View item 7. as DOC 113 KBReport 3 pages Download

At this meeting

Whole meeting

Who was there

12 of 17 attended
CP
CC P Williamson Leader of the County CouncilChair, present
CA
CC A Vincent Cabinet Member for Resources, HR and Property (Deputy Leader)Deputy Chair, apologies
CP
CC P Buckley Cabinet Member for Community and Cultural ServicesCommittee Member, present
CG
CC G Gooch Cabinet Member for Adult Social CareCommittee Member, present
CM
CC M Green Cabinet Member for Health and WellbeingCommittee Member, present
CJ
CC J Rear Cabinet Member for Education and SkillsCommittee Member, present
CA
CC A Riggott Cabinet Member for Economic Development and GrowthCommittee Member, present
CR
CC R Swarbrick Cabinet Member for Highways and TransportCommittee Member, present
CC
CC C Towneley Cabinet Member for Children and FamiliesCommittee Member, present
CS
CC S Turner Cabinet Member for Environment and Climate ChangeCommittee Member, present
CC
County Councillor Scott SmithCounty Councillor In Attendance, in attendance
CC
County Councillor Mrs Sue WhittamCounty Councillor In Attendance, in attendance

All 17 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. Highway Maintenance Capital Programme – Recycled Materials from Samlesbury Enterprise ZoneThis decision
  2. Additional Highway Maintenance Capital Allocations for 2024/25Approved
  3. Additional Budget 2023 Highways Maintenance and Pothole Repair Funding, 2023 to 2024Approved
  4. Additional Budget 2023 Highways Maintenance and Pothole Repair Funding, 2023 to 2024Approved
  5. Proposed 2022/23 Highway Maintenance New Start Capital Programme - Additional ResourcesApproved
  6. Proposed 2021/22 Highway Maintenance and Transport New Starts Capital ProgrammesApproved

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies