Resolved
That the continued development of Maxy Lane site as the preferred site for the provision of a new four form entry (600 place) secondary school in Preston, be approved.
Cabinet approved this item on Thursday 6 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the continued development of Maxy Lane site as the preferred site for the provision of a new four form entry (600 place) secondary school in Preston, be approved.
In October 2024, Cabinet considered options for the creation of a new four form of entry (600 place) Secondary school in north Preston. Cabinet requested that work commenced on the design and planning for both the former Tulketh High School, and a site at Maxy Lane, subject to certain conditions. This report provides an update on the position.
This is deemed to be a Key Decision and the requirements of the council's Cabinet procedure rules (Standing Order C18, Consideration of Key Decisions) have been complied with.
Cabinet is asked to approve the continued development of Maxy Lane site as the preferred site for the provision of a new four form entry (600 place) secondary school in Preston.
1. In October 2024, Cabinet considered the options for the creation of a new four form of entry (600 place) Secondary school in Preston. Cabinet approved:
"iii. The commencement of work to design and obtain planning permission for a new secondary school at the Tulketh High School site in Preston; iv. In addition to Recommendation (iii), pursue the design and planning for a new secondary school on the land to be released North of Maxy Lane assuming that the notice from the developer is issued within three months of today's date; v. To authorise the Director of Finance and Commerce, in consultation with the Cabinet Member for HR, Resources and Property and the Cabinet Member for Education and Skills, to consider both sites and progress with the design and planning permission for the site that will provide the required places within the time constrained development schedule"
2. Officers have commenced work to conduct feasibility studies on both sites in order to inform the next steps.
Former Tulketh High School site
3. In April 2023, Cabinet approved the 'demolition of the former Tulketh High School buildings, and to move and make safe utility services to the site, including a gas main which also serves the adjoining former caretakers house'. The main school buildings have now been demolished. However, the sports hall remains, and is still operational, having been leased in 2005 to a leisure company delivering sports facilities.
4. The Tulketh site was identified as a potential option to provide a new school, with the benefits of the site including it being in the county council's ownership, services are identified and there is an established entryway to the school. However, questions regarding the location of the site were raised, along with concerns around transport, accessibility and suitability. To begin to consider these issues, an initial desktop feasibility has been conducted.
5. The desktop feasibility study has identified that, although there are noted benefits to the site, risks have also been identified that may delay the scheme. These include having some retained sports facilities on site subject to a tenancy, a telecom tower on site requiring easements, and the site containing a habitat wildlife corridor which could impact the biodiversity and net gain. In order to progress feasibility, the site requires further studies such as a UK Habitat Survey including biodiversity and net gain data. In addition, the site requires planning approvals.
Maxy Lane Site
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
School Place Planning Delivery Programme Update: New School Places in PrestonReport | 138 KB | DownloadRead as text |
PDF |
View item 11. as DOC 150 KBReport | 4 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.