Resolved
That the commencement of the procurement exercise for the following be approved: ii. Primary Care Local Improvement Scheme Agreements
Cabinet approved this item on Thursday 6 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
That the commencement of the procurement exercise for the following be approved: ii. Primary Care Local Improvement Scheme Agreements
In line with the county council's procurement rules, this report sets out a recommendation to approve the commencement of the following procurement exercise:
i) Primary Care Local Improvement Scheme Agreements
At the conclusion of the procurement process, any award of contract will be made under Section 9.52 (51) of the county council's Scheme of Delegation to Officers.
This is deemed to be a Key Decision and the requirements of the council's Cabinet procedure rules (Standing Order C18, Consideration of Key Decisions) have been complied with.
Cabinet is asked to approve the commencement of the following procurement exercise:
i) Primary Care Local Improvement Scheme Agreements
1. Appendix 'A' sets out the detail of the procurement exercise and basis upon which it is proposed to carry out the process including:
• The description of the services. • The procurement route proposed. • The estimated contract value. • The proposed basis for the evaluation of the tender submissions.
Options and Proposals
2. The options concerning the procurement exercise are considered within Appendix 'A'.
Consultations
3. The relevant head of service and key operational staff have been consulted in drawing up the proposals contained within this report.
Context and Implications
Legal (including Human Rights)
4. Legal implications are considered within Appendix 'A'.
Financial
5. The maximum estimated value of the contract will be contained within the funding arrangements as set out in Appendix 'A'. If significant variations should result from this position, a further report to Cabinet will be required.
Equality and Diversity
6. Equality and Diversity implications are considered within Appendix 'A'.
7. Any procurement exercise inherently involves several risks. These include the risk of failing to identify a successful bidder, the risk of non-compliance with procurement legislation leading to procurement challenges, or the risk of selecting an unsuitable supplier.
8. To mitigate these risks effectively, robust procurement procedures and requirements have been established. This includes the development of precise specifications/contracts, the appointment of multiple suppliers, and a rigorous evaluation process to review suppliers comprehensively. These measures ensure a suitable degree of risk mitigation and contribute to a successful procurement outcome.
Appendix Title Appendix 'A' Procurement Exercise Detail List of Background Papers
Paper Date Contact/Tel None
Part II Reason
N/A
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Appendix AAppendix A | 63 KB | Download |
PDF |
Procurement ReportReport | 129 KB | DownloadRead as text |
PDF |
View as DOCX (5./2) 28 KBAppendix | 2 pages | Download |
PDF |
View item 5. as DOC 138 KBReport | 2 pages | Download |
Follow Cabinet at Lancashire & Rossendale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 3 Sep 2026 | Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. | Decided | Open |
| 3 Sep 2026 | Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... | Noted | Open |
| 3 Sep 2026 | 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... | Noted | Open |
| 3 Sep 2026 | Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... | Approved | Open |
| 3 Sep 2026 | SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.