Lancashire County Council / Rossendale Borough Council
Cabinet, Thursday 2 July 2026 at 2.00pm

The County Council's Financial Position - 2025/26 Outturn

Noted Executive 10 papers

AI summaryLancashire County Council Cabinet noted a £2.992m revenue overspend for 2025/26, approved drawing it from the transitional reserve, and noted a £9.195m schools delegated budget overspend. Capital spend reached £193.229m against a £306.005m in-year programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue, capital and schools outturn noted; £2.992m transfer from transitional reserve approved
Money£2.992m revenue overspendPlus £193.229m capital spend and £79m DSG overspend
What happens next2026/27 £74m savings deliveryRevised savings programme plus SEND reform plan submission to DfE
Who it affectsCouncil services and school budgetsIncluding SEND, adult care, home to school transport, schools and capital projects

What was decided

Cabinet noted the council's final revenue and capital outturn position for 2025/26, with revenue showing a £2.992m overspend (0.24% of net revenue budget) and capital spend at £193.229m against a £306.005m in-year programme. Report P2, P5, P9

Cabinet approved the transfer of £2.992m from the transitional reserve to cover the 2025/26 revenue overspend, drawing on reserves that remain robust. Report P4, P10

Cabinet noted the schools budget outturn for 2025/26, which includes a £9.195m overspend on delegated budgets, a £79m Dedicated Schools Grant overspend, and a cumulative DSG deficit of £102m at March 2026. Report P6, P11, P34, P35

Why

The £2.992m revenue overspend reflects continued improvement from a £27.863m forecast at Quarter 1, achieved through in-year mitigations, savings delivery and strong service-level controls during a year of rising demand and cost pressures. Report P2, P3, P16

The largest directorate pressures were Education and Children's Services (£8.568m overspend, including £5.2m on home to school transport and £4.0m on children's social care) and Adult Care and Provider Services (£8.032m overspend), partly offset by underspends in Place, Resources and Corporate Budgets. Report P15, P18, P19, P20, P22, P23

The Dedicated Schools Grant overspend and rising cumulative deficit reflect continued Special Educational Needs pressures, which the report says is a national picture across upper tier authorities with insufficient central government grant to meet increasing need. Report P6, P38

What happens next

A revised and adjusted savings delivery programme of £74m has been agreed as part of the 2026/27 budget, with additional governance in place to support delivery. Report P37

The council is preparing a SEND reform plan for submission to the Department for Education; if approved, the government has announced a High Needs Stability Grant that would cover 90% of the DSG deficit at March 2026. Report P38

The council's Efficiency Review Phase 2 will continue to develop further savings opportunities for consideration in the 2027/28 budget-setting process. Report P39

The money

  • £2.992m Revenue budget overspend for 2025/26 (0.24% of net revenue budget) Report P2, P10, P14
  • £27.863m Quarter 1 forecast overspend (2.24%) Report P2, P16
  • £10.354m Quarter 2 forecast overspend (0.83%) Report P2
  • £6.117m Quarter 3 forecast overspend (0.49%) Report P2, P15
  • £306.005m In-year capital delivery programme after approved additions and re-profiling Report P5, P30
  • £193.229m Capital outturn spend for 2025/26 Report P5, P30
  • -£112.776m Capital variance (-36.9%) Report P5, P30
  • £79m Dedicated Schools Grant overspend in 2025/26 Report P6, P35
  • £102m Cumulative DSG deficit at March 2026 Report P6, P35
  • £9.195m Schools delegated budget overspend for 2025/26 Report P6, P34
  • £57.73m School balances after 2025/26 Report P6, P34
  • £59.690m Agreed savings target for 2025/26 Report P27
  • £58.718m Savings delivered in 2025/26 (98%) Report P26, P28
  • £74m Revised savings programme for 2026/27 Report P37
  • £76m Forecast 2026/27 overspend on the High Needs Block Report P38

Options considered

  • Chosen: Note the council's final revenue and capital outturn position for 2025/26. Recommended in the Cabinet report Report P9
  • Chosen: Approve a £2.992m transfer from the transitional reserve to cover the 2025/26 revenue overspend. Reserve position remains robust and provides resilience for in-year fluctuations Report P4, P10
  • Chosen: Note the schools budget outturn position for 2025/26. Recommended in the Cabinet report Report P11

Implications

  • Financial: Transitional reserve continues to provide resilience; further savings delivery of £74m in 2026/27 and Phase 2 of the Efficiency Review are central to ongoing sustainability. Report P4, P37, P39
  • Financial: High Needs Block pressure is forecast to continue, with a £76m in-year overspend projected for 2026/27 alongside the £102m cumulative DSG deficit. Report P38
  • Financial: Over half of the £112.776m capital variance (56%) relates to grant funded activity, much of which was received late in the year. Report P5
  • Financial: Treasury Management surpluses that have historically benefited the council are unlikely to continue at current interest rates; an existing reserve has sufficient funding to cover the shortfall for the life of the MTFS. Report P41
  • Financial: The reported position relies on income from the NHS and work continues to resolve the ongoing share of some costs between both organisations. Report P40
  • Legal: The report is governed by the best value duty under Section 3 of the Local Government Act 1999 and the balanced budget duty under the Local Government Finance Act 1992; Local Government Reorganisation will require future consideration of the distribution of assets, liabilities, reserves and financial planning responsibilities. Report P46, P47, P53
  • Equalities: The report states that, as a monitoring report with no specific service delivery decisions, there are no inherent equality and diversity issues. Report P57
  • Risk: The outturn is based on actual spend so has limited risk implications, although savings delivery and the SEND reform plan remain key financial risks. Report P37, P38, P55

Who and where

  • Lancashire County Council directorates, with overspends in Education and Children's Services and Adults Health and Wellbeing, and underspends in Place, Resources and Chief Executive Services, and Corporate Budgets Report P15
  • Schools in Lancashire, with delegated budget overspend of £9.195m and balances falling to £57.73m Report P34
  • Children and young people with Special Educational Needs, who drive the £79m DSG overspend and £102m cumulative deficit Report P6, P38
  • Children requiring home to school transport, where the £5.2m SEND transport overspend is a key pressure Report P19
  • Adult social care service users, within the £8.032m Adult Care and Provider Services overspend Report P20
  • NHS partners in Lancashire, given ongoing work to resolve the share of joint costs Report P40

Timeline

  • February 2025: Indicative Capital Delivery Programme of £299.635m set, later increased to £306.005m after additions and re-profiling Report P30
  • Quarter 1 2025/26: Forecast revenue overspend of £27.863m (2.24%) Report P2, P16
  • Quarter 2 2025/26: Forecast revenue overspend reduced to £10.354m (0.83%) Report P2
  • Quarter 3 2025/26: Forecast revenue overspend further reduced to £6.117m (0.49%) Report P2, P15
  • 2025/26 financial year: Final outturn: £2.992m revenue overspend, £193.229m capital spend, £9.195m schools delegated budget overspend, £79m DSG overspend Report P2, P5, P6, P30, P34, P35
  • March 2026: Cumulative DSG deficit at this date stood at £102m Report P6, P38
  • 2026/27: Revised £74m savings delivery programme in place; £76m forecast High Needs Block overspend Report P37, P38
  • 2027/28: Budget-setting process to consider further Efficiency Review Phase 2 opportunities Report P39

Plain English for the jargon

  • DSG (Dedicated Schools Grant): Central government funding provided to councils for schools and education, including the High Needs Block for SEND
  • SEND (Special Educational Needs and Disabilities): Support for children and young people with learning difficulties or disabilities, a major cost pressure for upper tier councils
  • MTFS (Medium Term Financial Strategy): The council's multi-year financial planning framework
  • BSIP (Bus Service Improvement Plan): Government-funded programme to improve local bus services
  • DFC (Devolved Formula Capital): Capital funding devolved directly to schools for smaller projects
  • Levelling Up Fund: Central government capital fund for local infrastructure projects, with East Lancs a major recipient in Lancashire
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

That The council's final revenue and capital outturn position for 2025/26, be noted; The transfer from the transitional reserve for the 2025/26 overspend of £2.992m, be approved; and The schools budget outturn position for 2025/26, be noted.
Word for word from the decision Lancashire & Rossendale published for this meeting. Source: council.lancashire.gov.uk

Follow this further

Built from Lancashire & Rossendale's papers

What the report saysPro

Report to Cabinet

Summary

Purpose of the report

This report summarises the 2025/26 outturn position across the Council’s Revenue, Capital and Schools Budgets. The financial position should be considered alongside delivery of the Council Plan and associated key performance indicators.

The final revenue outturn for 2025/26 is an overspend of £2.992m, representing 0.24% of the net revenue budget. This reflects a continued improvement throughout the year. A significant pressure of £27.863m (2.24%) was identified at Quarter 1, which reduced to £10.354m (0.83%) at Quarter 2 and £6.117m (0.49%) at Quarter 3.

Over the course of the financial year, the Council has maintained a clear focus on financial stability despite a challenging operating environment, characterised by rising demand and cost pressures. The implementation of efficiency measures and robust in-year mitigations, supported by strong service-level controls and corporate oversight, has culminated in the improved outturn position.

The Council’s reserve position remains robust, with the Transitional Reserve providing resilience. Reserve utilisation is closely monitored and ensures that resources are aligned to corporate priorities, underpinned by strong governance arrangements. Further details of major spending variations to budget and the resultant impact on reserves are shown in Appendix 'A'.

The in-year Capital Delivery Programme was £306.005m (after approved additions and re-profiling). The outturn position for 2025/26 is spend of £193.229m, a variance of -£112.776m (-36.9%). The variance is primarily the product of delayed delivery on some schemes, arising notably from resource, procurement and contract issues and delayed decisions. This has been mitigated where possible through earlier than originally planned delivery on other schemes within the multi-year programme. It should be noted that over half of the variation (56%) relates to grant funded activity (for example Levelling Up Fund and Department for Education projects) and the majority of the former wasn't received until late in the year. Further details are provided in Appendix 'B'.

The Dedicated Schools Grant (DSG) has overspent in this year by £79m, with the cumulative DSG deficit at March 2026 now £102m. This is due to continuing pressures in Special Educational Needs, which reflects a national picture across upper tier authorities, with insufficient central Government grant resources to meet increasing need. Schools outturn position of schools delegated budget for 2025/26 is an overspend of £9.195m. This has resulted in the level of school balances falling to £57.73m. Further details are provided in Appendix 'C'.

The Council’s Efficiency Review continues to play a central role in supporting financial sustainability and organisational improvement. Phase 1 of the review informed the 2026/27 budget and Medium-Term Financial Strategy, with identified savings incorporated into the Council’s approved financial and transformation plans. The review is designed as an ongoing programme, with Phase 2 building on this work to further embed efficiency into business as usual, identify and deliver further opportunities. An update on progress to date is provided in Appendix ‘D’.

Recommendation

Cabinet is asked to:

(i) Note the council's final revenue and capital outturn position for 2025/26.

(ii) Approve the transfer from the transitional reserve for the 2025/26 overspend of £2.992m.

(iii) Note the schools budget outturn position for 2025/26. Background

2025/26 Revenue Outturn

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix AAppendix A 451 KB Download
PDF
Appendix BAppendix B 309 KB Download
PDF
Appendix CAppendix C 293 KB Download
PDF
Appendix DAppendix D 1.8 MB Download
PDF
The County Council's Financial Position: 2025/26 OutturnReport 223 KB DownloadRead as text
PDF
View as DOCX (9./2) 433 KBAppendix 17 pages Download
PDF
View as DOCX (9./3) 166 KBAppendix 8 pages Download
PDF
View as DOCX (9./4) 197 KBAppendix 3 pages Download
PDF
View as DOCX (9./5) 775 KBAppendix 12 pages Download
PDF
View item 9. as DOCX 106 KBReport 6 pages Download

At this meeting

Whole meeting

Who was there

10 of 18 attended
CS
CC S Atkinson Leader of the County CouncilChair, present
CS
CC S Evans Deputy Leader & Cabinet Member for Children and FamiliesDeputy Chair, present
CD
CC D Dwyer Cabinet Member for Resources, Property and EfficiencyCommittee Member, present
CW
CC W Goldsworthy Cabinet Member for Highways and TransportCommittee Member, present
CD
CC D Matchett Cabinet Member for Health and WellbeingCommittee Member, present
CB
CC B Moore Cabinet Member for Economic Development and GrowthCommittee Member, present
CT
CC T Pickup Cabinet Member for Adult Social CareCommittee Member, present
CJ
CC J Roberts Cabinet Member for Rural Affairs, Environment and CommunitiesCommittee Member, present
CM
CC M Salter Cabinet Member for Education and SkillsCommittee Member, present
CE
CC E Worthington Cabinet Member for Civic PrideCommittee Member, present
CA
CC A AliCounty Councillor In Attendance, in attendance
CG
CC G DowdingCounty Councillor In Attendance, in attendance

All 18 on the meeting page

On this subject at Lancashire & Rossendale

Search all
  1. The County Council's Financial Position - 2025/26 OutturnThis decision
  2. The County Council's Financial Position - 2025/26 OutturnNoted
  3. The County Council's Financial Position - 2024/25 OutturnNoted
  4. The County Council's Financial Position - 2023/24 OutturnDecided
  5. The County Council's Financial Position - 2023/24 OutturnNoted
  6. The County Council's Financial Position - 2022/23 OutturnNoted

More from Lancashire & Rossendale Cabinet

All decisions
MeetingDecisionOutcome
3 Sep 2026 Minutes of the Meeting held on 2 July 2026That the minutes of the meeting held on 2 July 2026 be confirmed as a correct record and signed by the Chair. Decided Open
3 Sep 2026 Quarter 1 2026/27 Corporate Performance ReportThat, following consideration of the performance of the Council in Quarter 1 of 2026/27 against the ambitions set out... Noted Open
3 Sep 2026 2026/27 Quarter 1 Financial Monitoring ReportThat i. The current forecast Revenue Budget overspend at Quarter 1 of £15.655m (1.18%), as detailed in Appendix 'A' o... Noted Open
3 Sep 2026 Ofsted Inspection of Lancashire Children's ServicesThat, following consideration of the outcome of the inspection, which confirmed that Lancashire's Children's Services... Approved Open
3 Sep 2026 SEND Capital ProjectThat i. Following consideration of the positive consultation responses, the prior approval of those projects through ... Approved Open