Luneside Engineering Workshop, Mill Lane, Halton

Agreed Planning 1 paper

Planning Regulatory Committee agreed this item on Monday 26 July 2010. Below is the council's own wording, with the papers it was decided on.

Item42

Resolved

That, subject to the signing of a Unilateral Agreement, Planning Permission be granted, subject to the following conditions, as set out in the case officer’s report, and amendment to conditions 19 and 20: 1. Standard time limit. 2. Development to be carried out in accordance with the approved plans. 3. Development to be carried out in accordance with the amended plans (7 th June 2010) 4. External material sample panel for the new dwellings to be provided. 5. Precise details of the windows, doors, balconies and rooflights to be provided and agreed in respect of the new housing. 6. Precise details of the roof (eaves, verge, ridge) to be submitted and agreed in respect of the new housing. 7. Details of the new windows, doors, viewing platform and roofing systems (including samples) to the boathouse and Mill Building to be agreed. 8. Tree Protection condition. 9. Landscaping and maintenance conditions. 10. Submission of an Arboricultural Method Statement. 11. Bat mitigation to be implemented in full. 12. Submission of a Habitat Creation/Enhancement Management Plan. 13. Submission of a Woodland Habitat Management Plan. 14. A method statement for the removal of/or long-term management/eradication of Japanese Knotweed and Himalayan Balsam to be submitted. 15. Archaeological Recording Condition. 16. Use of the Mill Building – no subdivision. 17. Use of the Boathouse – as applied for and ancillary to the cohousing scheme (no overnight accommodation). 18. Use of residential units (except units 30-35) to be used in association with the cohousing scheme. 19. Scheme for odour control (the premises shall not be used for ... view the full minutes text for item 42.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Planning Regulatory Committee

Agenda Item Committee Date Application Number

A10 26 July 2010 10/00319/FUL

Application Site Proposal

Luneside Engineering Workshop 1) Development of ecological cohousing scheme including 28 houses, 6 flats, ancillary residential Mill Lane buildings and associated landscaping (including provision of a new riverside footpath) Halton 2) Development of 6 terraced houses on former Lancaster Lower Halton Mill (Managers House) site;

3) Change of use of existing Mill Building from B2 general industrial with ancillary B1 office and B8 storage to mixed use B1/B2/B8 managed workspace, with refurbishment to include replacement roof and doors/windows, flue for biomass boiler and solar panels;

4) Change of use of the Boathouse to provide ancillary use for cohousing residents, changing facilities and training space for canoe clubs, and a space to host educational day visitors to the site; with refurbishment to include reroofing in reclaimed slate, replacement doors / windows and installation of a viewing platform.

Name of Applicant Name of Agent

[name removed] Target Date Reason For Delay

1 July 2010 Increasing application numbers

Case Officer [name removed] None

Approval, subject to the submission and agreement of Summary of Recommendation a signed Unilateral Undertaking.

1.0The Site and its Surroundings

1.1The proposal relates to a 2.5 hectare linear site located between Mill Lane and the River Lune in Halton, approximately 3 miles east of the centre of Lancaster. The site lies on the right bank between Forge Bank Weir and Lower Halton Weir, bound by farmland to the east; ‘The Forge’ and ‘Out of the Woods’ commercial buildings to the north with farmland beyond; the River Lune to the south; and a mixture of recently developed residential dwellings to the west, mainly three-story, plus two commercial buildings now completed and occupied to the north west of the site.

1.2At present there are five existing buildings on the site, including the existing stone Mill Building which dates back to the early 20th century, together with large areas of hardstanding, an unmade track which provides access to Forge Bank Weir, and important groups of trees, including a locally important woodland at the eastern end of the site which is protected by a Tree Preservation Order (TPO). The south banks of the site are generally covered with overgrown self-seeded vegetation, although there are some areas where stone outcrops are exposed.

1.3The site topography changes quite dramatically from the western end of the site where it is relatively flat to the eastern side of the site when the levels rise approximately 8.5m between the southern and northern boundaries. As a consequence of the site contours there are a number of large retaining walls plus two public rights of way passing through this part of the Halton Mills development site; one running along the higher northern part of the site and one running along the southern boundary adjacent to the River Lune.

1.4Halton Mills, as the area is now known, is accessed off Low Road adjacent to Town End Farm, which has recently been converted, opposite the village playing fields and allotments. It is approximately 1km up a 30m hill to the village amenities and services on High Road but closer to the community centre on Low Road. Access to the site itself is via the internal road system, which has now, in part, been constructed to adoptable standards. The remaining parts of the Halton Mills site linger in a state of flux, with the site subdivided into a number of plots with various land owners. Some parts of the site have been developed but regretfully most of the site has been left undeveloped or incomplete for some considerable time.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Luneside Engineering Workshop, Mill Lane, HaltonReport 191 KB DownloadRead as text

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Luneside Engineering Workshop, Mill Lane, HaltonThis decision
  2. Luneside Engineering Workshop, Mill Lane, HaltonAgreed

More from Lancaster Planning Regulatory Committee

All decisions
MeetingDecisionOutcome
1 Sep 2026 Bus Station Central Drive MorecambeResolved : That prior approval for demolition is required and is granted. Approved Open
1 Sep 2026 Car Park Nelson Street LancasterResolved : That the application be approved subject to the following conditions: 1. Development in accordance with Ap... Approved Open
1 Sep 2026 Auction Mart Car Park Thurnham Street LancasterResolved : That the application be approved subject to an additional condition regarding additional ground investigat... Approved Open
1 Sep 2026 Delegated ListThat the report be noted. Noted Open
27 Jul 2026 Land at Ashton Road LancasterResolved : That the application be approved subject to the following conditions: · the satisfactory completion of a L... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies