Resolved
That Outline Planning Permission be granted, subject to the signing of a Section 106 Agreement covering: 1. 20% provision of affordable housing, all of which is to be available for social renting. 2. Not to occupy more than 20% of the dwellings until 10,000 sq m of B1/B2 buildings are constructed (including the installation of windows and roofs). 3. Public transport contribution of £597,000 for sustainable transport measures. 4. Contribution of £12,707 for Air Quality Monitoring Equipment prior to the occupation of the first unit. And subject to the following planning conditions, as set out in the case officer’s report: 1. Outline planning permission – all reserved matters required (except access). 2. Phasing plan required, including triggers for provision of open space, the neighbourhood centre, affordable housing and the construction of the industrial/commercial uses. 3. At least Code level 3. 4. At least 10% on site renewable energy production. 5. Adoptable highway details required. 6. Protection of visibility splays. 7. Provision of car parking and garages. 8. Servicing and turning areas – details required. 9. Wheel cleaning facilities during construction. 10. Provision of permeable pedestrian and cycle links between the site and adjacent commercial and residential areas. 11. Travel Plan – details required. 12. Affordable housing scheme – detail required (including numbers, types and location, arrangements for maintaining their affordability in perpetuity, and occupancy criteria). 13. Protected species – bats. 14. Programme of archaeological work and recording prior to any work occurring on site. 15. Notwithstanding the plans details of surfacing materials required. 16. Means of enclosure of the site and plot boundaries – details required. 17. Landscaping scheme required. 18. Retention of trees and hedgerows. 19. Tree protection measures. 20. Layout and future maintenance of public open space – details required. 21. Provision of equipped children’s play facilities on site – provided before first occupation of any dwelling. 22. Finished floor levels – details required. 23. Separate drainage system. 24. Provision of interceptor – car parks. 25. Use of SUDS – surface water discharge from the site should be attenuated to existing site levels or less. 26. Construction hours – 0800 to 1800 Mondays to Saturdays. 27. Scheme for dust control. 28. Noise assessment. 29. Standard contaminated land condition. 30. Contaminated land – importation of soil, materials and hardcore. 31. Contaminated land – prevention of new contamination. 32. Bunding of tanks. 33. Pile driving. And to the following additional condition (suitably worded): 34. Request updated ecological surveys at the reserved ... view the full minutes text for item 41.