Cabinet, Tuesday 10 September 2024

Projects and Performance Monitoring

Noted Executive 3 papers

Cabinet noted this item on Tuesday 10 September 2024. Below is the council's own wording, with the papers it was decided on.

Item29

Resolved

Resolved unanimously: That the report be noted. Reasons for making the decision: Monitoring of strategic projects and key performance indicators provides a link between the Council Plan 24-27 by providing progress updates.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Cabinet

CABINET

Projects and Performance: Q1 2024-25 10th September 2024

Report of Chief Executive PURPOSE OF REPORT

To provide members with an update on performance and projects during quarter one of 2024 - 25 (April - June 2024).

Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public

RECOMMENDATIONS OF COUNCILLOR HAMILTON-COX

That Cabinet (1) Consider the update on Projects and Performance for Quarter 1 2024/25.

1.0INTRODUCTION

1.1The primary purpose of this report is to present information relating to the council’s strategic projects and key performance indicators for the period April – June 2024, which can be found within the appendices.

2.0PERFORMANCE REPORTING

2.1The highlight report at Appendix A provides a broadly consistent set of information across the last five quarters.

2.2The direction of travel indicators are included against each performance measure to show if the KPI has improved, is broadly the same or has worsened. The typical definition of ‘broadly the same’ is within 3% variation on the comparative quarter. Most indicators compare to the previous quarter, those marked with an asterisk compare to the like quarter from the previous year.

2.3The ‘measure’ column no shows ‘Low is good’ or ‘High is good’ in addition to the measure to help with the readability of the report.

2.4The direction of travel indicators shows that four KPIs have improved, eleven are broadly the same, three have worsened and two have no comparative data. The comments in the appendix provide explanation on the direction of travel.

3.0PROJECT REPORTING

3.1The highlight report at Appendix B shows a short narrative and “Red – Amber – Green” status updates for three elements of the project, these being Plan, Cost and Scope.

3.2Of the 17 projects where full update reports have been received:  Four are reporting ‘amber’ (minor) delays with their project plans (progress)  One is reporting ‘red’ (major) delays with their project plans (progress)  Seven are reporting ‘amber’ (minor) deviations to the cost of the project  Two are reporting ‘amber’ (minor) concerns with the scope, meaning it is anticipated that one or more benefits of each project may not be realised.

3.3The highlight report shows the majority of the council’s Strategic Projects are progressing as planned at the end of Quarter 1 2024-25, some with minor delays.

3.4No projects have completed or closed during this quarter.

RELATIONSHIP TO POLICY FRAMEWORK

Monitoring of strategic projects and key performance indicators provides a link between the Council Plan 24-27 by providing progress updates.

CONCLUSION OF IMPACT ASSESSMENT (including Health & Safety, Equality & Diversity, Human Rights, Community Safety, HR, Sustainability and Rural Proofing) None directly identifiable, due to the high-level nature of this report.

LEGAL IMPLICATIONS There are no legal implications directly arising.

FINANCIAL IMPLICATIONS There are no financial implications directly arising.

OTHER RESOURCE IMPLICATIONS Human Resources / Information Services / Property / Open Spaces: There are no further implications directly arising.

SECTION 151 OFFICER’S COMMENTS The Section 151 officer has been consulted and has no further comments

MONITORING OFFICER’S COMMENTS The Monitoring Officer has been consulted and has no further comments

BACKGROUND PAPERS Contact Officers: Claire Dubelbeis, Projects and Performance Manager None. Telephone: 01524 582505 E-mail: [email protected] Ref:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Projects and Performance MonitoringReport 230 KB DownloadRead as text
PDF
Q1 Performance Report 2024-25: IntranetReport 537 KB Download
PDF
Q1 Projects Report 2024-25: IntranetReport 455 KB Download

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Projects and Performance MonitoringThis decision
  2. Projects and Performance: Q4 2025-26Noted
  3. Projects and Performance Q3 2025-26Noted
  4. Projects and Performance Quarter 3 2025-26Noted
  5. Projects and Performance: Q2 2025-26Noted
  6. Projects and Performance: Q2 2025-26Noted

More from Lancaster Cabinet

All decisions
MeetingDecisionOutcome
28 Jul 2026 Provisional Revenue, Capital and Treasury Management Outturn 2025/26Resolved unanimously: (1) That the provisional outturn for 2025/26 be endorsed, including the transfers to and from R... Approved Open
28 Jul 2026 Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi... Decided Open
7 Jul 2026 Exclusion of press and publicResolved unanimously: (1) That, in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and ... Decided Open
9 Jun 2026 Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i... Approved Open
9 Jun 2026 Appointments ReportResolved unanimously: That the appointments to outside bodes and partnerships as appended to the report be confirmed ... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies