AI summaryLancaster City Council Cabinet noted its Q3 2025/26 performance report, covering April to December 2025. The forecasts were a £1.271M General Fund underspend, a (-£0.060M) Housing Revenue Account overspend and a +£5.255M capital programme variance. [D] [P4] [P6.1] [7.1] [8.1]
Written from the decision and the officer reportPDF Pro
OutcomeNotedThe report linked the Council plan with operational delivery. [D]
Money£1.271M General Fund underspend [P6.1]HRA overspend was (-£0.060M); capital variance was +£5.255M. [7.1] [8.1]
What happens nextFinancial monitoring continues [9.4] [12.3]HRA health and borrowing remain under review. [9.4] [12.3]
Who it affectsCouncil services and budgets [2.2]The report covers all service portfolios. [2.2] [6.2]
What was decided
Cabinet noted the Q3 2025/26 performance report. The report links the Council plan with operational delivery through regular updates. [D]
Why
Performance, project and resource monitoring links the Council plan with operational achievement by showing the effect of operational initiatives against strategic aims. [D]
All portfolios must examine revenue budgets and meet budget holders regularly. Reports go to Cabinet and the Budget & Performance Panel for review. [2.2] Report 2.2
The report updates financial performance for the first three quarters of 2025/26 and provides the related appendices. [P4] [1.1] [P14] Report P4, 1.1, P14
What happens next
Work to monitor HRA expenditure known to be under pressure will continue. [9.4] Report 9.4
Working capital cashflows and possible further borrowing will remain under close review. [12.3] Report 12.3
Slippage and accelerated capital expenditure are anticipated for inclusion in the 2026/27 budget process. [8.2] Report 8.2
The money
£1.271M Projected year end General Fund underspend against the approved original net revenue budget of £27.201M.
(-£0.060M) Projected year end Housing Revenue Account overspend against budget. Report 7.1
+£5.255M Projected year end capital variance against budget, comprising General Fund +£5.171M and HRA +£0.084M. Report 8.1
+£0.538M Expected salary underspend, including additional pay award, agency and consultancy costs. Report P24
£10.338M Projected General Fund unallocated balances, within forecast combined reserves of £30.234M. Report 9.1
£0.770M Projected Housing Revenue Account unallocated balances, with forecast combined usable reserves of £2.125M.
+£0.267M Forecast favourable in year Business Rates variance. Report 10.3
1,402,440 Total debt written off for Council Tax, Business Rates, Housing Benefit Overpayments and HRA Housing Rents. Report P115
Options considered
Chosen: Note the Q3 2025/26 performance report. The report provides regular updates linking the Council plan, operational initiatives and strategic aims.
Implications
Financial: The forecast is a £1.271M General Fund underspend and a (-£0.060M) Housing Revenue Account overspend. [P6.1] [7.1] Report 7.1
Financial: The capital programme has a forecast +£5.255M year end variance. Slippage and accelerated expenditure are anticipated for inclusion in the 2026/27 budget process. [8.1] [8.2] Report 8.1, 8.2
Financial: Combined General Fund reserves are forecast at £30.234M. Combined usable Housing Revenue Account reserves are forecast at £2.125M. [9.1] [9.3] Report 9.1
Climate: Burrow Beck Solar Farm has a forecast +£0.533M underspend. This relates to site clearance preparatory works and using the same contractor for related works. [P81] Report P81
Risk: The HRA depreciation adjustment of 35% is subject to external audit, and HRA financial health remains under close review. Further borrowing may be needed, but its amount is difficult to quantify. [7.4] [9.4] [12.3] Report 7.4, 9.4, 12.3
Staffing: Salary expenditure is expected to be underspent by +£0.538M. The full staff turnover provision has been removed from the forecast. [P24] Report P24
Legal: No legal implications directly arise from the decision. [P126] Report P126
Equalities: No direct equality or diversity impacts were identified because the report is high level. [P125] Report P125
Council Tax and Business Rates payers Report 10.2, 10.3
Local Council Tax Support claimants
Waste collection services Report P49
Commercial and leisure operations Report 5.1, P49, P55
Capital programme projects Report 8.1, 8.2
Timeline
February 2025: Council approved the 2025/26 Budget and Medium Term Financial Strategy, setting a balanced budget. [2.1] Report 2.1
July 2025: The National Employers' 3.2% pay offer was agreed for all NJC pay points. [3.2] Report 3.2
26th November 2025: The Chancellor announced the business rates multipliers for 2026/27. [P100] [P101] Report P100, P101
27th January 2026: The Government announced 15% business rates relief for eligible pubs and live music venues. [P106] Report P106
31 January 2026: Q3 information was distributed to members of Cabinet and the Budget & Performance Panel. [2.2] Report 2.2
10 February 2026: The Q3 2025/26 report was dated 10 February 2026. [P2] Report P2
1 April 2026: The proposed business rates reset and several relief schemes begin. [10.4] [P104] Report 10.4, P104
Plain English for the jargon
Q3: Quarter 3, covering April to December 2025. [P4] [6.1]
HRA: Housing Revenue Account. [P68]
MTFS: Medium Term Financial Strategy, covering 2025 to 2030. [2.1]
Working budget: The approved budget after virements and in year adjustments. [2.4]
EUV-SH: Existing use value, social housing, used as a depreciation adjustment factor. [7.4]
BRRR: Business Rates Retention Reserve, which will fully fund the forecast year end deficit. [10.3]
MRR: Major Repairs Reserve, used to fund the HRA self financing payment. [9.4]
RHL: Relief for retail, hospitality and leisure properties, replaced from 2026/27. [P98]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item103
Resolved
(1) That the report be noted. Reasons for making the decision: Performance, project and resource monitoring provides a link between the Council plan and operational achievement by providing regular updates on the impact of operational initiatives against strategic aims.
Word for word from the decision Lancaster published for this meeting.Source: committeeadmin.lancaster.gov.uk
Delivering Our Priorities: Q3 2025/26 10 February 2026
Report of Chief Executive & s151 Officer PURPOSE OF REPORT
To provide members with an update on financial performance during the first three quarters of 2025/26 (April – December 2025).
Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public
RECOMMENDATIONS OF COUNCILLOR HAMILTON-COX
That Cabinet (1) Consider the update on financial performance for Quarter 3 2025/26.
1.0INTRODUCTION
1.1The primary purpose of this report is to present information relating to the Council’s financial performance for the period April-December 2025, which can be found within the appendices.
2.0FINANCIAL MONITORING
2.1The 2025/26 Budget and Medium-Term Financial Strategy (MTFS) 2025-2030 approved by Council in February 2025 set a balanced budget for the year based on the assumptions made at that time.
2.2All portfolios are required to examine their revenue budgets and meet with their budget holders regularly and reports are submitted to Cabinet and Budget & Performance Panel for review. To enable Portfolio Holders to meet this requirement, Financial Services continually reviews and refreshes how it presents the Council’s corporate monitoring information, with the Quarter 3 information distributed members of both committees on 31 January 2026.
2.3In an attempt to aid understanding Members should note that where projected variances values are presented with brackets ( ) this reflects a negative, or adverse movement from the budgeted position. Conversely, projected variances accompanied with a + sign represents a positive, or favourable movement from the budgeted position. The following financial appendices accompany the financial monitoring section of this report.
Appendix A: General Fund Service Analysis Appendix B: General Fund Subjective Analysis Appendix C: HRA Service Analysis Appendix D: General Fund Capital Projects Appendix E: HRA Capital Projects Appendix F: Reserves Projected Outturn Appendix G: Approved Savings Monitoring Appendix H: Service Analysis Appendix I: Aged Debt Summary By Service Appendix J: Treasury Management Quarterly Update
2.4It should also be noted that projected outturn figures are monitored against the working budget and not the original budget within this report. The working budget includes approved virements and in-year budget adjustments. This reduces a number of variances in respect of items such as ‘grossing-up’ of grant income/expenditure and the movement of employees to different costs centres which is especially needed during times of service restructuring. It provides a more accurate up-to date forecast and eliminates the need for duplicate reporting at service and subjective levels.
3.0SALARY PROJECTIONS
3.1Salary expenditure is one of the largest areas of expenditure in the Council and the latest budgeted pay bill for direct employee expenses is £33.572M (£26.772M General Fund, £6.800M HRA).
3.2As part of the 2025/26 budget setting process, an inflationary uplift of 2.5% was included to salaries across all services of the Council. The National Employers latest offer of an increase of 3.2% on all NJC pay points was agreed in July 2025.
For the purposes of the projected outturn calculations used within this report, the agreed offer of 3.2% has been included. For information, additional annual costs in the region of £0.228M (£0.182M General Fund, £0.046M HRA) have been forecasted.
3.3The latest salary position is detailed in the table below.
Exclusion of the Press and PublicResolved unanimously: That in accordance with Section 100 A( 4) of the Local Government Act 1972, the press and publi...
Reports from Overview and Scrutiny(8 Members (Councillors Bannon, Bottoms, Hart, Caroline Jackson, Peter Jackson, Riches, Stubbins & Tyldesley) voted i...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.