Budget and Performance Panel, Wednesday 11 February 2026

Delivering Our Priorities 2025/26 Q3

Noted Finance 2 papers

AI summaryLancaster City Council's Budget and Performance Panel noted the third quarter financial update for 2025/26. [D] The projections are a £1.271M General Fund underspend, a (-£0.060M) Housing Revenue Account overspend and +£5.255M capital underspend. [6.1] [7.1] [8.1]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCovered April to December 2025. [P4]
MoneyGeneral Fund underspend £1.271M [6.1]Housing account overspend (-£0.060M); capital variance +£5.255M. [7.1] [8.1]
What happens nextContinue close financial monitoring [9.4] [12.3]Reprofiled property and capital works enter 2026/27. [5.3] [8.2]
Who it affectsNot stated

What was decided

The panel noted the Delivering Our Priorities Q3 2025/26 report. Report P2

The chair thanked the cabinet member for attending and presenting reports to the panel.

Why

The report gave members an update on financial performance for the first three quarters of 2025/26, covering April to December 2025. Report P4

Forecasts use the working budget because it includes approved virements and in year adjustments and gives an up to date forecast. Report 2.4

Brackets show adverse movements and plus signs show favourable movements, to make variances easier to understand. Report 2.3

What happens next

The implementation of savings and budget proposals worth £0.025M is underway. Report 4.1

The reprofiled property works are included in draft estimates for the 2026/27 budget process. Report 5.3

Capital slippage and accelerated expenditure are anticipated for inclusion in the 2026/27 budget process. Report 8.2

The money

  • £1.271M Projected General Fund year end underspend Report 6.1
  • (-£0.060M) Projected Housing Revenue Account year end overspend Report 7.1
  • +£5.255M Projected capital projects year end variance Report 8.1
  • +£0.538M Expected overall salary underspend Report P24
  • £0.025M Approved savings target for 2025/26 Report 4.1
  • £10.338M Projected General Fund unallocated balances Report 9.1
  • £30.234M Forecast combined reserves Report 9.1
  • £0.770M Projected Housing Revenue Account unallocated balances

Options considered

  • Chosen: Note the financial performance report. The panel noted the report.

Implications

  • Financial: A year end General Fund underspend of £1.271M is projected. Report 6.1
  • Financial: A year end Housing Revenue Account overspend of (-£0.060M) is projected. Report 7.1
  • Financial: The capital programme is forecast to underspend by +£5.255M. Slippage and accelerated expenditure will enter the 2026/27 budget process. Report 8.1, 8.2
  • Staffing: The overall salary position, including pay award, agency and consultancy costs, is expected to underspend by +£0.538M. Report P24
  • Legal: No direct legal implications arise. The 35% social housing adjustment to market value is subject to external audit. Report P126, 7.4
  • Risk: Housing Revenue Account financial health remains under close review. Unallocated balances are projected at £0.770M and usable reserves at £2.125M. Report 9.4
  • Financial: Business Rates monitoring forecasts a +£0.267M in year variance. A (-£0.693M) deficit will be funded from the Business Rates Retention Reserve. Report 10.3
  • Equalities: No direct equality or diversity impacts were identified because the report is high level. Report P125

Who and where

  • General Fund service areas Report P44
  • Housing Revenue Account services Report P69
  • Council employees Report 3.1
  • Housing tenants Report 7.2, P69
  • Business ratepayers Report P98, P104
  • Eligible pubs and live music venues Report P106
  • Commercial property leaseholders Report P51
  • Residents affected by food waste collection changes Report P49

Timeline

  • February 2025: Council approved the 2025/26 Budget and Medium Term Financial Strategy. Report 2.1
  • July 2025: The 3.2% National Employers pay offer was agreed. Report 3.2
  • 31 July 2025: Cabinet considered the Provisional Outturn report. Report 9.2
  • April to December 2025: Q3 monitoring covered the first three quarters. Report P4, 6.1
  • 31 January 2026: Q3 information was distributed to both committees. Report 2.2
  • 10 February 2026: The report presented the Q3 update. Report P2
  • 31 March 2026: Projected reserve balances were reported. Report P85, P86
  • 1st April 2026: The business rates reset and relief changes begin. Report 10.4, P104

Plain English for the jargon

  • Q3: April to December 2025 financial monitoring period. [P4] [6.1]
  • HRA: Housing Revenue Account. [7.0]
  • General Fund: The revenue fund covering the Council's services. [6.0] [P44]
  • working budget: Approved virements and in year adjustments used for forecasts. [2.4]
  • favourable variance: A positive movement from the budgeted position. [2.3]
  • adverse variance: A negative movement from the budgeted position. [2.3]
  • Corporate Property Reserve: Receives consolidated underspend from reprofiled property works. [P30]
  • Business Rates Retention Reserve: Reserve used to fund the forecast year end deficit. [10.3]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item51

Resolved

- That the report be noted. At this point, on behalf of the Panel, the Chair thanked Councillor Hamilton-Cox for his attendance at the meeting and presentation of reports to the Panel.
Word for word from the decision Lancaster published for this meeting. Source: committeeadmin.lancaster.gov.uk

Follow this further

Built from Lancaster's papers

What the report saysPro

Report to Budget and Performance Panel, 13 pages

CABINET

Delivering Our Priorities: Q3 2025/26 10 February 2026

Report of Chief Executive & s151 Officer PURPOSE OF REPORT

To provide members with an update on financial performance during the first three quarters of 2025/26 (April – December 2025).

Key Decision Non-Key Decision Referral from Cabinet N Member Date of notice of forthcoming N/A key decision This report is public

RECOMMENDATIONS OF COUNCILLOR HAMILTON-COX

That Cabinet (1) Consider the update on financial performance for Quarter 3 2025/26.

1.0INTRODUCTION

1.1The primary purpose of this report is to present information relating to the Council’s financial performance for the period April-December 2025, which can be found within the appendices.

2.0FINANCIAL MONITORING

2.1The 2025/26 Budget and Medium-Term Financial Strategy (MTFS) 2025-2030 approved by Council in February 2025 set a balanced budget for the year based on the assumptions made at that time.

2.2All portfolios are required to examine their revenue budgets and meet with their budget holders regularly and reports are submitted to Cabinet and Budget & Performance Panel for review. To enable Portfolio Holders to meet this requirement, Financial Services continually reviews and refreshes how it presents the Council’s corporate monitoring information, with the Quarter 3 information distributed members of both committees on 31 January 2026.

2.3In an attempt to aid understanding Members should note that where projected variances values are presented with brackets ( ) this reflects a negative, or adverse movement from the budgeted position. Conversely, projected variances accompanied with a + sign represents a positive, or favourable movement from the budgeted position. The following financial appendices accompany the financial monitoring section of this report.

Appendix A: General Fund Service Analysis Appendix B: General Fund Subjective Analysis Appendix C: HRA Service Analysis Appendix D: General Fund Capital Projects Appendix E: HRA Capital Projects Appendix F: Reserves Projected Outturn Appendix G: Approved Savings Monitoring Appendix H: Service Analysis Appendix I: Aged Debt Summary By Service Appendix J: Treasury Management Quarterly Update

2.4It should also be noted that projected outturn figures are monitored against the working budget and not the original budget within this report. The working budget includes approved virements and in-year budget adjustments. This reduces a number of variances in respect of items such as ‘grossing-up’ of grant income/expenditure and the movement of employees to different costs centres which is especially needed during times of service restructuring. It provides a more accurate up-to date forecast and eliminates the need for duplicate reporting at service and subjective levels.

3.0SALARY PROJECTIONS

3.1Salary expenditure is one of the largest areas of expenditure in the Council and the latest budgeted pay bill for direct employee expenses is £33.572M (£26.772M General Fund, £6.800M HRA).

3.2As part of the 2025/26 budget setting process, an inflationary uplift of 2.5% was included to salaries across all services of the Council. The National Employers latest offer of an increase of 3.2% on all NJC pay points was agreed in July 2025.

For the purposes of the projected outturn calculations used within this report, the agreed offer of 3.2% has been included. For information, additional annual costs in the region of £0.228M (£0.182M General Fund, £0.046M HRA) have been forecasted.

3.3The latest salary position is detailed in the table below.

Table 1 Quarter 3 Financial Monitoring – Salary Monitoring

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Delivering Our Priorities 2025/26 Q3Report 13 pages DownloadRead as text
PDF
DoP Appendix Pack Q3 25-26Appendix 22 pages Download

At this meeting

Whole meeting

On this subject at Lancaster

Search all
  1. Delivering Our Priorities 2025/26 Q3This decision
  2. Delivering our Priorities 2025/26 Q3Noted
  3. Delivering Our Priorities: Q2 2025/26Noted
  4. Delivering Our Priorities: Q2 2025/26Noted
  5. Delivering Our Priorities: Q1 2025/26Noted
  6. Delivering Our Priorities: Q1 2025/26Noted

More from Lancaster Budget and Performance Panel

All decisions
MeetingDecisionOutcome
11 Mar 2026 Projects and Performance Q3 2025-26That Councillor Hamilton-Cox and officers be thanked for their attendance, reporting and answering questions and that... Noted Open
11 Mar 2026 Strategic Risk ManagementThat the report be noted. At this point the press and public were re-admitted to the meeting. Noted Open
11 Mar 2026 Work Programme- That the report and updates be noted. Noted Open
11 Feb 2026 Capital Programme 2026/27 – 2035/36 & Capital Strategy (Investing in the Future)- That the report be noted. Noted Open