(1) U p to a total of £14,348,626 for housing investment in the period 2014 through 2018 provisionally released (subject to successful bids) from the housing regeneration allocation within the capital programme. (2) Senior Head of Community given delegated authority, in consultation with the lead Cabinet member, to undertake preparatory work to set up a council owned housing delivery company and report back to cabinet in the autumn. (3) Provision of £200,000 for a housing rescue emergency fund to help vulnerable people avoid the loss of their home by funding the purchase of properties originally built and provided by the council where strict criteria are met approved. (4) Provision of £500,000 to commence a second photo-voltaic (PV) programme approved. (5) Senior Head of Community given delegated authority, in consultation with the Chief Finance Officer and lead cabinet member for finance, to commence a second PV programme on the basis that market conditions (cost and FIT rate) result in systems being self-financing (including provision of a sinking fund to cover reduced warrantees).
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Report of: Ian Fitzpatrick, Senior Head of Community
Ward(s) All
Purpose This report provides an update on the Council’s Housing Investment plans and seeks approval for first stage development of a new Housing Delivery Company. It recommends further action to expand on this work and to extend the scope of the Solarbourne green energy initiative.
Decision Type: Key Decision
Recommendation: Cabinet is recommended to: • to provisionally release (subject to successful bids) from the Housing Regeneration allocation within the Capital programme up to a total of £14,348,626 for housing investment in the period 2014 through 2018. • Delegate authority to the Snr Head of Community in consultation with the Cabinet Portfolio Holder for Community to undertake preparatory work to set up a Council owned Housing Delivery Company and report back to Cabinet in the autumn. • Approve provision of £200,000 for a Housing Rescue Emergency Fund to help vulnerable people avoid the loss of their home by funding the purchase of properties originally built and provided by the Council where strict criteria are met. • Approve provision of £500,000 to commence second Photo- Voltaic programme. • Delegating authority to the Senior Head of Community in consultation with the Chief Finance Officer and Cabinet Portfolio holder for Finance to commence a second PV programme on the basis that market conditions (cost and FIT rate) result in systems being self-financing (including provision of a sinking fund to cover reduced warrantees).
Contact: Andy Thompson BA MSc – Strategic Housing Manager E-Mail address: [email protected] Telephone: 01323 415736
Paul Turton – HEDP Project Director E-mail address : [email removed] Telephone: [phone removed]
Page 1 of 10 1.0 Introduction
1.1The role of local authorities in shaping housing markets and meeting housing needs and aspirations has changed significantly over the past three years. Councils now have the ability to manage their landlord role independently within the financial constraints of a self financing Housing Revenue Account (HRA) while the Localism Act 2011 has given local authorities a general power of competence; unless otherwise prescribed by law.
1.2At the same time, there is a clear recognition that public sector financial subsidy from central government for new homes and economic development will in the future be limited. In addition, the ability of the Council to invest in new Council owned homes in the traditional way is constrained by the caps on borrowing that apply to the HRA.
1.3This means that for the Council to maintain its current progress on the housing and economic development fronts it will need to consider how to invest in ways that do not impact adversely on the HRA, find new ways to help subsidise affordable housing and also generate surpluses for investment in socially necessary projects.
2.0Phase 1 Delivery – Housing and Economic Development
2.1Delivery to date has focused on three areas:
1. Local Authority New Build: providing new housing on mainly Council owned land. The first phase of the LANB programme is underway to provide 35 new homes by December 2015. This is 12 more homes than originally envisaged. Sites include Coventry Court and Belmore Road and are being partly developed on a mixed tenure basis so that a limited amount of outright sales help financially support additional affordable homes and enable investment in local neighbourhood improvements.
2. Empty Homes Programme/SHEP: bringing empty properties back into use, including redundant retail units. Phase 1 of this programme comprises 20 affordable homes supported by £360k of grant secured from the Homes and Communities Agency and the refurbishment and commercial letting of 3 retail units.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.