(1) Progress on main Devonshire Park project and related project for the replacement of the Congress Theatre Façade noted. (2) Variation to capital programme of £1.1million for the additional works to the Congress Theatre approved, bringing the total budget to £1.95m. (3) Up to £250,000 from the capital programme reserve to be utilised for the scheme costs to achieve RIBA Stage 2 to develop a concept plan for the Devonshire Park Complex approved, bringing the total budget to £950,000.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
1.1Since the last Cabinet reports the project has been progressing and is on track to deliver to programme. On the main project the consultants have completed the first stage of the procurement process for the Design Team and Quantity Surveyor (QS). The procurement process has been run in accordance with OJEU procurement regulations with shortlists drawn from a pre-qualification questionnaire process including financial checks. The tender briefs have been issued and tenders for both the Conservation architect led Design Team and QS are due back in July with appointments to be made in
Page 1 of 5 August. In addition to this the Conservation Management Plan was tendered and is underway and due for completion at the end of July 2014.
1.2The replacement of the Congress Theatre façade has had the full design team in place for some time. The full specification of works has been completed in consultation with English Heritage and the tenders have been returned and analysed. The listed building application for the works has also been submitted.
1.3Previously in December 2012, Cabinet approved, amongst other things, to earmark up to £700,000 to progress the Devonshire Park project to RIBA Stage C (this is the Concept stage to determine general approach to layout, design and construction – now referred to as Stage 2) and in May 2013, to release £850,000 to enable the repair of the Congress Theatre façade.
1.4The predicted costs of the Devonshire Park project to stage C and the Congress Theatre works were based on estimates from the consultants employed at the time.
1.5In the intervening time, external Project Managers have been appointed for each of these projects and have carried out detailed analysis of the work. This analysis has shown that further works and consultancy services are needed. The impact of this is the subject of this report.
2.0Congress Theatre Façade Restoration
2.1The full design team is now in place and have been working on the detailed design of the works. The original estimate of £850,000 for the works was based on two estimates prepared in 2012 for a like for like replacement of the façade by consultants at the time. The works were limited to only the south façade and excluded the ground floor. Now we have undertaken detailed analysis on the works and included English Heritage in the detailed discussions the extent of the works has expanded. The works now involve extra areas of expenditure which are:-
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.