Eastbourne Borough Council Cabinet, Monday 16 March 2020 at 6.00pm

Seafront Lighting Reinstatement

Agreed Executive 2 papers

Eastbourne Borough Council Cabinet agreed this item on Monday 16 March 2020. Below is the council's own wording, with the papers it was decided on.

Item61

Resolved

(Key decision): (1) To agree that funds up to the level already earmarked for the project within the Council’s capital programme be released to support seafront lighting reinstatement works (2) To agree a waiver of the Council’s Contract Procedure Rules for necessary works in connection with reinstatement of the lighting and award the contract for works to the Council’s term electrical contractor, GM Monk; (3) To authorise the Accountable Officer to sign a waiver of the Council’s Contract Procedure Rules to GM Monk in connection with these works.
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Cabinet

Report to: Cabinet

Date: 16 March 2020

Title: Seafront Lighting Reinstatement

Report of: Ian Fitzpatrick, Deputy Chief Executive and Director of Regeneration and Planning

Cabinet member: Councillor Jonathan Dow, Cabinet member for climate change

Ward(s): Meads and Devonshire

Purpose of report: For Cabinet to note costs for the reinstatement of the seafront lighting and agree that funds up to the level already earmarked for the project within the Council’s capital programme be released to support reinstatement works.

Decision type: Key Decision

Officer (1) To agree that funds up to the level already earmarked recommendation(s): for the project within the Council’s capital programme be released to support seafront lighting reinstatement works;

(2) To agree a waiver of the Council’s Contract Procedure Rules for necessary works in connection with reinstatement of the lighting and award the contract for works to the Council’s term electrical contractor, GM Monk;

(3) To approve the Accountable Officer to sign a waiver of the Council’s Contract Procedure Rules to GM Monk in connection with these works.

Reasons for Works are required in order to restore the seafront lighting recommendations: and reduce future maintenance costs.

Contact Officer(s): Name: Mark Langridge-Kemp Post title: Head of Property, Delivery and Compliance E-mail: [email protected] Telephone number: 01323 415876 1 Introduction

1.1Eastbourne’s seafront lighting consists of lamp columns and festoon lighting; it plays an important part in the promenade’s charm as well as supporting seafront safety during the night. The Council is responsible for the majority of the lighting between Western Lawns and Fisherman’s Green, stretching 1.5 miles. ESCC is responsible for lighting and columns adjacent to the roadway, EBC is responsible for the festoon lighting between these columns. There are a mixture of styles of light columns along the seafront with most being cast iron decorative columns with the lighting being fed from underground cables via a number of junction boxes and feeder pillars.

1.2Considerable parts of the lighting have been impacted by underground faults, rendering large sections of festoon lighting and a good proportion of the lamp columns for which the Council is responsible inoperative. Due to the nature of the fault, a temporary solution bringing additional cabling and lighting to the existing structures has been required in order to restore lighting to the area. However, a permanent solution now needs to be put in place to fully restore the lighting and ensure its future integrity.

2 Proposal

2.1The temporary solution currently in place has not been able to bring back into use the existing lamp columns and does not address the problems long-term. It is proposed that a scheme of repair works is undertaken, Phase 1 would look at replacing all the underground cabling between the Pier and the Wish Tower; the columns along the Middle Parade will be repaired or replaced with new columns to the same casting as the existing. Phase 2 would look at works between the pier and Fisherman’s Green.

2.2It is proposed that all new lighting in the initial phase will be delivered by energy efficient LED fittings to replace the existing halogen and sodium fittings. This has the advantage of lower energy consumption, smaller cable size and longer lamp life which will reduce running, installation and maintenance costs.

2.3The lighting design of columns and globes interlaced with festoon lighting is likely to be retained, using new lamp heads and festoons and refurbished globes. Control gear and protective devices will be upgraded as part of the project which will ensure the electrical installation is brought into compliance with electrical safety regulations.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Seafront Lighting Reinstatement: Appendix 1Appendix 67 KB Download
PDF
Seafront Lighting ReinstatementReport 81 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
DT
Councillor David TuttChair, present
AS
Councillor Alan ShuttleworthDeputy-Chair, present
MB
Councillor Margaret BannisterCommittee Member, present
JD
Councillor Jonathan DowCommittee Member, present
SH
Councillor Stephen HoltCommittee Member, present
CS
Councillor Colin SwansboroughCommittee Member, present
RW
Councillor Rebecca WhippyCommittee Member, apologies
RC
Robert CottrillOfficer, in attendance
HJ
Homira JavadiOfficer, in attendance
PE
Philip EvansOfficer, in attendance
IF
Ian FitzpatrickOfficer, in attendance
CK
Catherine KnightOfficer, in attendance

All 17 on the meeting page

More from Lewes Eastbourne Borough Council Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting held on 15 July 2026Resolved – That the minutes of the meeting held on 15 July 2026 be approved and the Chair authorised to sign them as ... Approved Open
16 Sep 2026 Housing Services Progress and Performance Report - 2026/27 - Quarter 1(Non-Key Decision): To note the Quarter 1 2026/27 housing services progress and performance position, including areas... Noted Open
16 Sep 2026 Portfolio Progress and Performance Report 2026/27 - Quarter 1(Non-Key Decision): 1) To note progress and performance for Quarter 1 2026/27. To enable Cabinet Members to consider ... Noted Open
16 Sep 2026 Revenue and Capital Financial Monitoring Report - Quarter 1 2026/27(Key Decision): 1) To note the Quarter 1 forecast financial position for 2026/27 and the associated risks. 2) To dele... Noted Open
16 Sep 2026 Eastbourne Local Plan (Proposed Submission Version Plan) Regulation 19(Key Decision): Cabinet is asked to Recommend to Full Council that it: 1) Agrees the Proposed Submission Local Plan (... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies