Completion of the Winter Garden redevelopment

Agreed Executive 1 paper

Eastbourne Borough Council Cabinet agreed this item on Monday 16 March 2020. Below is the council's own wording, with the papers it was decided on.

Item62

Resolved

(Budget and policy framework): (1) To support Option 2 of the two proposals for completion that are offered and recommend to Full Council that Option 2 be agreed. The business plan commissioned by David Clarke Associates (DCA) 2015 identified that for the full income potential to be realised for Devonshire Park, all of the complex needed to be transformed to the same standard. The Winter Garden remains outstanding. We are seeking authority to agree a programme of works for the Winter Garden (Key decision) (2) To delegate responsibility for all contractual land procurement related decisions to the Director of Tourism & Enterprise (up to £3m in total spend).
Word for word from the decision Lewes published for this meeting. Source: democracy.lewes-eastbourne.gov.uk

Follow this further

Built from Lewes's papers

What the report saysPro

Report to Eastbourne Borough Council Cabinet

Report to: Cabinet

Date: 16 March 2020

Title: Completion of the Winter Garden redevelopment

Report of: Phil Evans, Director of Tourism and Enterprise

Cabinet member: Councillor Margaret Bannister, Cabinet member for Tourism and Enterprise Ward(s): All

Purpose of report: To agree on proposals for the completion of the Winter Garden redevelopment to support the conferencing, entertainment and private hire functions of the premises

Decision type: Key

Officer (1) To support Option 2 of the two proposals for recommendation(s): completion that are offered. The business plan commissioned by David Clarke Associates (DCA) 2015 identified that for the full income potential to be realised for Devonshire Park, all of the complex needed to be transformed to the same standard. The Winter Garden remains outstanding. We are seeking authority to agree a programme of works for the Winter Garden

(2) To delegate responsibility for all contractural land procurement related decisions to the Director of Tourism & Enterprise (up to £3m in total spend)

Reasons for Opportunity to increase additional income and to meet recommendations: financial targets identified by DCA

Contact Officer(s): Name: Phil Evans Post title: Director of Tourism and Enterprise E-mail: [email protected] Telephone number: 01323 415410

Introduction

1.1From the commencement of the redevelopment of Devonshire Park it was always envisaged that the refurbishment of The Winter Garden would be the final phase of the project. Currently it remains as the one outstanding building that needs to be completed to complement the Devonshire Quarter business, cultural and sporting complex as was defined in the original business case for the redevelopment of Devonshire Park produced by DCA prior to the works commencing.

1.2The Devonshire Park Theatre underwent refurbishment in 2016; the sports facilities including the tennis irrigation schemes and Locker Room project were completed in 2017/18; the Congress Theatre refurbishment was completed in March 2019 and the new Welcome Building opened in June 2019. The external plaza and landscaping were also completed in 2019.

1.3The Winter Garden has been closed to the public since 2017. The former staff offices including non-structural partitions on the upper floor were removed and the Floral Hall and bar fittings stripped out after the building closed. The Gold Room has since been used as temporary office space for on-site contractors and the Floral Hall used for storage of equipment during the construction process.

2 Proposal

Complete the works still outstanding

The Winter Garden is a Grade II listed building and there are restrictions on works that can be implemented on the structure but it is of less significance than the Grade II* listed Congress Theatre and there is more flexibility allowed by Historic England on some aspects of its redevelopment. The building has undergone many uses since it was completed in 1875 ranging from a glasshouse displaying exotic trees and plants, to a roller skating rink to a dance hall and various additions and changes have been made to the fabric of the structure, including the introduction of glazed outer shell panelling that was constructed to the first floor foyer and front offices in the early 1960s. More recently the Winter Garden was used variously as a dining/function room, an exhibition space for conferences, as a theatre and music venue and as an auditorium for conferences and events.

In 2015, the last full year of operation, the Winter Garden generated a gross income of £486,755 and a net income (surplus) of £199,000. £135,000 of the gross was from 5 Christmas parties but at the time the premises were winding down prior to the redevelopment and there would be scope to do many more than 5 such events.

In order to generate private booking income of this kind it can only be achieved if the following are included within any refurbishments:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Completion of the Winter Garden redevelopmentReport 93 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 17 attended
DT
Councillor David TuttChair, present
AS
Councillor Alan ShuttleworthDeputy-Chair, present
MB
Councillor Margaret BannisterCommittee Member, present
JD
Councillor Jonathan DowCommittee Member, present
SH
Councillor Stephen HoltCommittee Member, present
CS
Councillor Colin SwansboroughCommittee Member, present
RW
Councillor Rebecca WhippyCommittee Member, apologies
RC
Robert CottrillOfficer, in attendance
HJ
Homira JavadiOfficer, in attendance
PE
Philip EvansOfficer, in attendance
IF
Ian FitzpatrickOfficer, in attendance
CK
Catherine KnightOfficer, in attendance

All 17 on the meeting page

On this subject at Lewes

Search all
  1. Completion of the Winter Garden redevelopmentThis decision
  2. Completion of Winter Garden RedevelopmentDecided

More from Lewes Eastbourne Borough Council Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes of the meeting held on 15 July 2026Resolved – That the minutes of the meeting held on 15 July 2026 be approved and the Chair authorised to sign them as ... Approved Open
16 Sep 2026 Housing Services Progress and Performance Report - 2026/27 - Quarter 1(Non-Key Decision): To note the Quarter 1 2026/27 housing services progress and performance position, including areas... Noted Open
16 Sep 2026 Portfolio Progress and Performance Report 2026/27 - Quarter 1(Non-Key Decision): 1) To note progress and performance for Quarter 1 2026/27. To enable Cabinet Members to consider ... Noted Open
16 Sep 2026 Revenue and Capital Financial Monitoring Report - Quarter 1 2026/27(Key Decision): 1) To note the Quarter 1 forecast financial position for 2026/27 and the associated risks. 2) To dele... Noted Open