(Key decision): (1) To delegate authority to the Director of Regeneration & Planning in consultation with the Portfolio holder for Housing and the Chief Finance Officer to make an allocation in the Housing Revenue Account (HRA) for £29m for the construction programme at Bedfordwell Road. (2) To note the financial and legal advice provided within this report. (3) To agree to delegate authority to the Director of Regeneration and Planning in consultation with the Portfolio Holder for Housing to: (a) appropriate all or part of the land at Bedfordwell Road, in accordance with further financial and legal advice to be taken, from the General Fund to the HRA (b) appropriate all or part of land at further sites as identified in paragraph 6.3 of the report, in accordance with further financial and legal advice to be taken, from the General Fund to the HRA.
Word for word from the decision Lewes published for this meeting.Source: democracy.lewes-eastbourne.gov.uk
Title: Housing Revenue Account Capital Budget Allocation – Bedfordwell Road and appropriation of other development sites from the General Fund to the Housing Revenue Account
Report of: Ian Fitzpatrick, Deputy Chief Executive, Director of Regeneration & Planning
Cabinet member: Councillor Alan Shuttleworth, Cabinet member for direct assistance services
Ward(s): Upperton
Purpose of report: This report sets out the budget for the residential, commercial and community development of Bedfordwell Road. It also requests additional land which could be developed for housing is appropriated to the HRA to enable delivery.
Decision type: Key Decision
Officer (1) To delegate authority to the Director of Regeneration recommendation(s): & Planning in consultation with the Portfolio holder for Housing and the Chief Finance Officer to make an allocation in the Housing Revenue Account (HRA) for £29m for the construction programme at Bedfordwell Road.
(2) To note the financial and legal advice provided within this report.
(3) To agree to delegate authority to the Director of Regeneration and Planning in consultation with the Portfolio Holder for Housing to:
(a) appropriate all or part of the land at Bedfordwell Road, in accordance with further financial and legal advice to be taken, from the General Fund to the HRA (b) appropriate all or part of land at further sites as identified in paragraph 6.3 of this report, in accordance with further financial and legal advice to be taken, from the General Fund to the HRA Reasons for To finalise the budget available for the delivery of recommendations: Bedfordwell Road within the Housing Revenue Account Business Plan and also enable the pipeline of delivery of new homes through appropriation of land from the General Fund to HRA
Contact Officer(s): Name:Jessica Haines Post title: Head of Commercial Business E-mail: [email protected] Telephone number: 01323410000
1 Introduction
1.1A paper presented to Cabinet in September 2019 outlined the options available to the Council for development of the council owned site at Bedfordwell Road, Eastbourne which is set to deliver new homes, commercial and community premises for the town.
1.2The recommendations of that report were agreed and the the Bedfordwell scheme has since progressed in terms of a developed outline design and consideration of the best procurement route. Officers have been working with specialist consultants and architects to ensure the scheme continues to deliver community benefit and cost effective new homes. In addition extensive work has been undertaken to consider the most appropriate way of the Council financing the project and the legal implications of the Council considering different vehicles or Council owned companies for the development.
1.3This report seeks to confirm the procurement, financing and delivery arrangements and request the budget for development of the Bedfordwell scheme. The Council are now at the point of needing to negotiate the contractual terms between themselves and the proposed developer. The report seeks agreement of a capital allocation in the Councils Housing Revenue Account (HRA) of £29m where it is proposed the development is cashflowed and the social housing held on completion.
Additionally the report sets out the appropriation of a number of housing delivery 1.4 sites. This will allow further new homes sites to progress utilising the borrowing capacity of the HRA and supporting housing need.
2 Procurement – Bedfordwell Road Scheme
2.1The overall scope of the Bedfordwell Road project has not changed since the Cabinet report in September 2019 with the deliverables remaining 96 new build homes, 13 refurbished homes plus additional commercial and community space in the Pump House.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.