Multi-Storey Car Park Refurbishment Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 12 March 2019. Below is the council's own wording, with the papers it was decided on.

Item4

Resolved

The Cabinet: 1.1 Approved the procurement of works to undertake a refurbishment of the Multi Storey car park. 1.2 Delegated to the Cabinet Member for Economic Growth, Environment and Development Services, in consultation with the Head of Economic Growth, the authority to appoint contractors following a procurement exercise and subject to the costs being within agreed budgets. 1.3 Recommended to Full Council : · The inclusion of a new project in the Capital Programme with a total cost of up to £300,000 (including £50,000 of contingency) funded by the restricted earmarked reserve entitled ‘Birmingham Road Car Park Repairs and Renewals’. · A change to the revenue budget to reflect the savings identified in the revenue implications section of this report
Word for word from the decision Lichfield published for this meeting. Source: democracy.lichfielddc.gov.uk

Follow this further

Built from Lichfield's papers

What the report saysPro

Report to Cabinet

Multi Storey Car Park, Refurbishment Project Report of the Cabinet Member for Economic Growth, Environment & Development Services : Councillor Ian Pritchard

Date 12 March 2019 Agenda Item 4 Contact Officers Craig Jordan/John Roobottom Tel Numbers 308202/687546 Email [email protected] [email protected] Cabinet Key Decision? YES Local Ward Although situated in the town centre, the car park is a Members major asset of this Council and therefore an issue affecting all Wards.

1. Executive Summary 1.1 Due to the previously planned demolition in connection with the Friarsgate project, maintenance work on the Birmingham Road, Multi Storey car park has been limited to essential items only for some years.

1.2This has led to a backlog of tasks which will now need to be completed in order to ensure the continued structural integrity of the car park and also to make sure that the facility can provide a reasonably pleasant and inviting offer for our customers.

1.3The intention of this project is to provide for a minimum five year life extension to the structure with no further major works expected in that period.

1.4If redevelopment intentions for the area were to change making retention of the facility for the longer term desirable, additional structural works would be required, but none of the works proposed in this report would prejudice this course of action.

1.5It is likely that the works would be split into two areas with one tender for structural and decorative works and a second for lighting improvements. However, if advice from our new purchasing providers at Wolverhampton City Council was to the contrary, the two operations could be combined into one tender.

2. Recommendations 2.1 That Cabinet approves the procurement of works to undertake a refurbishment of the Multi Storey car park. 2.2 That Cabinet delegates to the Cabinet Member for Economic Growth, Environment and Development Services, in consultation with the Head of Economic Growth, the authority to appoint contractors following a procurement exercise and subject to the costs being within agreed budgets. That Cabinet agree to recommend to full Council :  The inclusion of a new project in the Capital Programme with a total cost of up to £300,000 (including £50,000 of contingency) funded by the restricted earmarked reserve entitled ‘Birmingham Road Car Park Repairs and Renewals’.  A change to the revenue budget to reflect the savings identified in the revenue implications section of this report

3. Background 3.1 The structure has been regularly inspected by consultant engineers and their recommendations form the core of the works proposed for the structural tender. These will include : replacing the failing upper deck covering, repairs to various areas of damaged concrete, anti-corrosion treatment to structural steelwork, replacement of the damaged Birmingham Road height limiters, replacement of fire doors and frames, a deep clean of the entire building and localised improvements to paintwork and lining. Based on the engineers advice and experience of similar works it is expected that these works will cost in the region of £150,000.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Item 4: Multi Storey Car Park Refurbishment: Final: 4.3.19Report 112 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 12 attended
MW
Councillor Mike WilcoxChairman, present
IP
Councillor Ian PritchardVice-Chair, present
EL
Councillor Elizabeth LittleCommittee Member, present
DL
Councillor David LeythamCommittee Member, present
AY
Councillor Ashley YeatesCommittee Member, present
CS
Councillor Christopher SpruceCommittee Member, present
RK
Richard KingOfficer, expected
BW
Billy WebsterOfficer, expected
BN
Bal NahalOfficer, expected
DT
Diane TilleyOfficer, expected
NT
Neil TurnerOfficer, expected
MH
Mark HooperClerk, expected

On this subject at Lichfield

Search all
  1. Multi-Storey Car Park Refurbishment ProjectThis decision
  2. Multi-Storey Car Park RefurbishmentNoted

More from Lichfield Cabinet

All decisions
MeetingDecisionOutcome
13 Jul 2026 Year-End Performance and Delivery Report 2025/26The Cabinet: 2.1 Discussed and approved the Q4 Year 2 Delivery Plan outturn of the Lichfield District 2050 Strategy a... Approved Open
13 Jul 2026 Confirmation of Scheme of Delegation for New Local PlanThe Cabinet: Delegated authority to the Cabinet Member for Housing and Local Plan in conjunction with the Chief Execu... Decided Open
13 Jul 2026 Community infrastructure Levy (CIL) Allocations 2026The Cabinet: 2.1 Approved the following CIL allocations: · £100,000 to Wigginton and Hopwas Parish council towards th... Approved Open
13 Jul 2026 Money Matters: 2025/26 Financial MonitoringThe Cabinet: 2.1. Reviewed the report including the level of general and earmarked reserves and issues raised within ... Approved Open
13 Jul 2026 Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies