The Cabinet: 1.1 Approved the signing of the Planning Memorandum to become a ‘Qualifying Authority’ for the purpose of the High Speed Rail (West Midlands - Crewe) Bill (the Bill). 1.2 Requested that Council amend the Constitution to include the determination of all planning matters submitted under Schedule 17 (the Planning Conditions Schedule) of the Bill, in line with the current provisions that already exist for Phase 1 of HS2 matters under Schedule 17 of the High Speed Rail (London – West Midlands) Act 2017 as set out in the Appendix of the Cabinet report.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
HS2 Draft Planning Memorandum – Decision on Qualifying Authority Status Cabinet Member: Councillor A Lax and Councillor I Eadie Date: 9th July 2019 Agenda Item: 5 Contact Officer: Jeff Upton Tel Number: 01543 308199 Email: [email protected] CABINET Key Decision? YES Local Ward All Wards within Phase 2a of HS2 – Alrewas and Fradley, and Members Armitage with Handsacre, Colton and The Ridwares
1. Executive Summary 1.1 The purpose of this report is to seek authority to sign the HS2 Planning Memorandum, the effect of which is that Lichfield District Council will become a ‘Qualifying Authority’ for the purposes of the High Speed Rail (West Midlands - Crewe) Bill (the Bill). Those authorities choosing qualifying status are given greater control over the detailed design and external appearance of buildings and structures along the route. In agreeing to these controls, qualifying authorities are required to handle requests for approval in an expeditious manner, and to ensure appropriate delegated authority and Committee procedures are in place.
2. Recommendations 2.1 That the Cabinet approves the signing of the Planning Memorandum to become a ‘Qualifying Authority’ for the purpose of the High Speed Rail (West Midlands - Crewe) Bill (the Bill). 2.2 That Council be requested to amend the Constitution to include the determination of all planning matters submitted under Schedule 17 (the Planning Conditions Schedule) of the Bill, in line with the current provisions that already exist for Phase 1 of HS2 matters under Schedule 17 of the High Speed Rail (London – West Midlands) Act 2017 as set out in the attached Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.