The Cabinet: 1.1 Agreed that Coleman & Company be awarded the contract to undertake the commission for the tendered sum of £599,991. 1.2 Approved the awarding of a contract to Healthmatic for the provision and maintenance of temporary toilet facilities for a 3 year period for the tendered sum of £90,000. 1.3 Delegated to the Cabinet Member for Investment, Economic Growth and Tourism in consultation with the Head of Economic Growth the authority to sign the contractual agreements and to authorise any minor variations in the contractual arrangements subject to the costs being within the agreed budget. 1.4 Recommended that Council approve and update the Medium Term Financial Strategy to increase the Project Budget for the Birmingham Road Site by £185,000 from £2,995,000 to £3,180,000 with funding of £182,000 provided by the Earmarked Reserve and £3,000 from the Revenue Budget.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Birmingham Road, Lichfield Enabling Works – Selection of Tender Report of the Cabinet Member for Investment, Environment & Tourism Development Services: Councillor I. Eadie Date: 10th September 2019 Agenda Item: 6 Contact Officer: Stephen Stray/ Craig Jordan Tel Number: 01543 308760/ 308202 Email: [email protected]/ CABINET [email protected] Key Decision? YES Local Ward ALL Members
1. Executive Summary 1.1 A tender exercise for enabling works including the redevelopment of the former police station site on Frog Lane and the associated re-modelling of the adjacent bus station off the Birmingham Road has been undertaken. Five bids were received to carry out the works. 1.2 The tenders were all appraised against defined criteria set out in the tender specification covering price and quality. The price has been carefully considered in respect of detailed costings for the various aspects of the works which the tenderers were asked to set out. The quality of the tenders has been considered in relation to five aspects: i) minimising impact on the bus station service, ii) a method statement as to how the contractor will liaise effectively with key stakeholders throughout the works, iii) the relevant skills and experience to deliver a project of this size and nature, iv) a method statement as to how the existing buildings will be safely demolished within a busy residential and commercial area and finally v) the relevant experience of those undertaking the demolition. 1.3 The contractor will deliver the works granted planning permission on the 29th July 2019. This includes the demolition of existing police station buildings and bus station kiosk/toilet buildings, a 5 year temporary consent for car parking on the police station site, and in addition the remodelling of the existing bus station to include additional coach parking, the erection of replacement bus shelters, temporary toilet facilities and associated landscaping works. 1.4 In the assessment process, Coleman & Company provided a good standard of response supported by comprehensive evidence to demonstrate they could meet the quality requirements with a reasoned justification for the price submitted.
2. Recommendations 2.1 That the Cabinet agrees to the recommendation that Coleman & Company be awarded the contract to undertake the commission for the tendered sum of £599,991. 2.2 That the Cabinet approve the awarding of a contract to Healthmatic for the provision and maintenance of temporary toilet facilities for a 3 year period for the tendered sum of £90,000. 2.3 That the Cabinet delegates to the Cabinet member for Investment, Economic Growth and Tourism in consultation with the Head of Economic Growth the authority to sign the contractual agreements and to authorise any minor variations in the contractual arrangements subject to the costs being within the agreed budget. 2.4 Cabinet recommend to Council to approve and update the Medium Term Financial Strategy to increase the Project Budget for the Birmingham Road Site by £185,000 from £2,995,000 to £3,180,000 with funding of £182,000 provided by the Earmarked Reserve and £3,000 from the Revenue Budget.
3. Background 3.1 Members will be aware of the decision of the District Council not to fund the Friarsgate scheme and the consequent demise of that project in 2018. Since then the Council has determined to bring forward alternative proposals for the Birmingham Road site.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.