The Cabinet: 1.1 Noted the progress and submission of the final amended masterplan by consultants David Lock Associates; and, 1.2 Noted the requirement to test the viability and deliverability of the masterplan as presented and, 1.3 Noted the issues raised about the potential impacts of CV19 on centres across the country and the need to assess this in the context of Lichfield and the Lichfield City Centre Masterplan.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Lichfield City Centre Masterplan Cabinet Member for Major Projects & Economic Development
Date: 7th July 2020 Agenda Item: 5 Contact Officer: Helen Bielby Tel Number: 01543 308252 CABINET Email: [email protected] Local Ward All Members Members
1. Executive Summary 1.1 In Summer 2019, following a competitive tender, consultants David Lock Associates (DLA) were commissioned to produce a Masterplan for Lichfield City Centre. Following the production of an Analysis, Issues and Options report in October 2019, a draft Masterplan was produced. This was subject to public consultation during January/February 2020 and the document was amended as a result of the feedback. The final document was submitted to LDC in March 2020 and duly considered by EGED O&S Committee. 1.2 In response to issues raised by the EGED Committee, further work has been commissioned that will provide advice in regards to the impact of Covid-19 on city centres and on the implementation of the Masterplan.
2. Recommendations 2.1 That the Cabinet: i) Notes the progress and submission of the final amended masterplan by consultants David Lock Associates; and, ii) Notes the requirement to test the viability and deliverability of the masterplan as presented and, ii) Notes the issues raised about the potential impacts of CV19 on centres across the country and the need to assess this in the context of Lichfield and the Lichfield City Centre Masterplan.
3. Background 3.1 David Lock Associates were commissioned by the Council in July 2019 to undertake work and formulate a Masterplan in respect of the future Lichfield City Centre. Following engagement with officers and members and external stakeholders based upon a detailed baseline assessment and analysis, issues and options exercise, a draft Masterplan was duly prepared.
3.2The document envisages a 20 year implementation process and considers the Council’s role in implementing and funding the key projects. The Masterplan is aspirational, whilst continuing to support and facilitate the vitality and characteristics of the city centre that make it attractive and popular. As well as supporting emerging planning policy, the projects set out in the Masterplan will also be used to shape the future of the city centre by encouraging appropriate land uses and public realm improvements to ensure Lichfield continues to prosper in a sustainable way which is sensitive to the city’s character. 3.3 The Masterplan is a flexible framework rather than a rigid blueprint, setting out clear aspirations that the Council would like to achieve while being able to adapt to changes in the economy, required uses or other events that impact on city centres and development in general. This includes the impact of Covid 19. As with any masterplan it will be essential to keep it under review and ensure that the evidence base that supports it is still valid. In addition the implementation of any of the development schemes proposed within the Masterplan will be subject to rigorous viability and deliverability assessments and can be adapted and designed to meet the economic and community demands at that time. The plan is deliberately designed to evolve over the 20 years of its intended life as inevitably there will be significant socio- economic changes during this period.
3.4Public consultation on the draft Masterplan took place from the 6th January 2020 to 3rd February 2020. This included a drop-in session over two days at the St Mary’s Hub in the centre of Lichfield. A total of 141 responses were received from local residents and local interest groups and organisations via either online or via a paper questionnaire. In addition a number of organisations and individuals responded via letter or email.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.