The Cabinet: 1.1. Noted the Cabinet report and issues raised within and that Leadership Team with Cabinet Members will continue to closely monitor and manage the Medium Term Financial Strategy. 1.2. Accepted the funding from the Rough Sleeper Accommodation Programme of £165,898 (capital £140,000 and revenue £25,898) and approved an update to the Medium Term Financial Strategy to reflect the grant funding income and matching expenditure. 1.3. Approved the further allocations of funding from the Risk and Recovery Budget detailed at paragraph 3.9 and 3.10 of the Cabinet report totalling £52,600.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Money Matters: 2021/22 Review of Financial Performance against the Financial Strategy Cabinet Member for Finance, Procurement & Revenues and Benefits Date: 7 December 2021 Agenda Item: 3 Contact Officer: Anthony Thomas Tel Number: 01543 308012 Email: [email protected] Cabinet Key Decision? YES Local Ward Full Council Members
1. Executive Summary 1.1 The report covers the financial performance from April to September (Quarter Two) for 2021/22 including updated projections of the financial impact of COVID-19. 1.2 The Medium Term Financial Strategy projected general reserves at 31 March 2022 would be £6,985,824. At this stage, general reserves are forecast to be £6,913,291, a reduction of (£72,533) related to: A higher than budgeted contribution in 2020/21 of £139,117 Approved updates in 2021/22 summarised in para 3.14 decreasing the contribution by (£211,650) A projected decreased contribution contained in this report for 2021/22 of (£261,000) The favourable impact of COVID-19 in 2021/22 of £261,000 1.3 The Capital Programme is projected to be (£873,000) lower than the Approved budget due mainly to a re- profiling of the Coach Park and IT projects. 1.4 Capital Receipts are projected to be (£286,000) which is (£258,000) higher than the Approved Budget due to a projected increase in Housing Right to Buy monies. 1.5 In terms of Council Tax, Business Rates, Sundry Debtors and Supplier Performance: Council Tax collection in year performance was 57.20% (56.70% in 2020/21) and total arrears were £3,447,721 and the Council’s share is £448,204 (£2,759,204 and £358,697 in 2020/21). The Council Tax Collection Fund is projected to be in deficit, as budgeted, with the Council’s c13% share being £42,810 compared to the Approved Budget of £126,720. This additional income of (£83,910) will be included in the 2022/23 budget. Sundry Debt for income to be collected in 2021/22 has reduced by (£13,440) or 1% compared to 2020/21 and the value outstanding at 30 September 2021 has reduced by (£1,074,630) or 36%. Retained Business Rate Income is projected to be (£3,122,000) in line with the Approved Budget. The Business Rates Collection Fund is projected to be in deficit, as budgeted, with the Council’s 40% share being £2,884,000 compared to the Approved Budget of £908,000. This reduction in income of £1,976,000 is largely due to additional COVID-19 reliefs up to the end of June 2021. This sum will be included in the 2022/23 budget and will be offset by Section 31 grant. There will be a timing difference due to statutory arrangements between receipt of grant in 2021/22 and the period when the deficit is charged to the Revenue Budget. Therefore the Business Rates volatility earmarked reserve will be utilised to ‘smooth’ the financial impact. Business Rates collection in year performance was 55.20% (57.20% in 2020/21) and total arrears were £707,961 and the Council’s share is £283,184 (£992,192 and £396,877 in 2020/21). The payment of suppliers within 30 days was 86.85% and remains below our 90% target. 1.6 The Council’s investments achieved a risk status of A+ that was more secure than the aim of A- and yield exceeded all four of the industry standard London Interbank (LIBID) yield benchmarks. 2. Recommendations 2.1. To note the report and issues raised within and that Leadership Team with Cabinet Members will continue to closely monitor and manage the Medium Term Financial Strategy. 2.2. To accept the funding from the Rough Sleeper Accommodation Programme of £165,898 (capital £140,000 and revenue £25,898) and to approve an update to the Medium Term Financial Strategy to reflect the grant funding income and matching expenditure. 2.3. To approve the further allocations of funding from the Risk and Recovery Budget detailed at paras 3.9 and 3.10 totalling £52,600.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.