The Cabinet: 1.1. Approved the award of a 2-year contract for road sweeping services with provision for two 2-year contract extensions (2+2+2) with completion subject to the additional cost of the contract being identified from existing Approved Budgets. 1.2. Delegated the approval to utilise the option to extend the contract to the Head of Operational Services in consultation with the Cabinet Member for Economic Development, Leisure & Local Plan. 1.3. Determined whether the additional cost of the adopted highway sweeping be kept within approved budgets by either: meeting the cost from within the road cleansing budget by reducing the coverage of trunk road cleansing, or instructing officers to identify alternative savings from within the wider Operational Services approved budget.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
3.1Road Sweeping of the adopted highway is currently undertaken by Burntwood Group. To ensure compliance with Contract Procedure Rules this contract was re-tendered, with a new contract to start in April 2022. This work is separate to the cleansing of the district’s trunk roads: A51, A38 and A461.
3.2Lichfield District Council has a statutory duty to ensure that the district’s adopted highways are kept clean. Road Sweeping is a vital part of the Street Cleansing operations.
3.3The Road Sweeping provision has been carried out by an external supplier since 2008 following a compliant tender process. Prior to this date the service was carried out in-house. The current contract provides approximately 50 hours per week of Road Sweeping inclusive of vehicle, driver, fuel, consumables and traveling costs.
3.4A procurement process has been undertaken in line with the Council’s Contract Procedure Rules and the Public Contract Regulations 2015. The proposed contract term will be 2 years with the option to extend for a further two periods of 2 years.
3.5A number of compliant bids were returned and evaluated in line with the criteria of Price 70% and Quality 30%; the latter included questions on social and added value. The cost from the preferred supplier (the lowest-cost compliant submission) represents a 47% increase compared to the previous contract. This cost is however considered to represent market value; the market for road sweeping is geographically limited as the contractor is required to travel to / from Lichfield on a daily basis.
3.6Several factors are considered to have led to this increase:
Increased driver costs / HGV driver scarcity Increased fuel costs Legislative changes in 2021 prevent road sweepers from using rebated (red) diesel The previous cost was tendered six years ago
3.7The increased cost of the contract remains within the allocated budget for road cleansing. However this increased cost will require the other road cleansing services to be reviewed – reactive sweeping and trunk road cleansing. It is not recommended that the amount of cleansing of the adopted highway be reduced from the procured 50 hours per week. This is the considered the minimum required to maintain the current good standard of service.
3.8Bringing the road-sweeping service back in-house was considered. A number of factors – vehicle provision, storage and maintenance, driver availability and training and business resilience – meant that in-house provision was not advantageous at this time.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.