The Cabinet: 1.1 Approved the principle of funding a new, purpose-built leisure centre at Stychbrook Park, in Lichfield based on £10m of funding provided by the Council. 1.2 Cabinet recommends to Council to approve the Capital Financing Requirement (Borrowing Need) of £5m being initially funded by Internal Borrowing. 1.3 Recommends to Council an update to the Medium-Term Financial Strategy based on the financial implications section of this report. In the event increases in Approved Budgets become necessary then the changes will be subject to further approval by Council prior to contracts being completed in line with Contract and Financial Procedure Rules. 1.4 Delegated authority to the Leader and Chief Executive in consultation with the Monitoring Officer and the Section 151 Officer to complete all contracts and funding agreements necessary to successfully deliver the new leisure centre subject to the financial implications being within Approved Budgets.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
New Leisure Facility – Stychbrook Park Cabinet Member for leisure and Parks Date: 14th February 2023 Agenda Item: 9 Contact Officer: Simon Fletcher, Chief Executive, Anthony Thomas, Assistant Director Finance & Commissioning and S151 Officer, John Smith, Performance & Programmes Manager Tel Number: Email: [email protected] Cabinet [email protected][email protected] Key Decision? Yes Local Ward Curborough Ward Members
1. Executive Summary 1.1 This report proposes a second significant investment this financial year by the council, in line with its recently reviewed reserves policy and in its role as place-shaper for our district, following the December 2022 decision to support investment in a new cinema.
1.2It seeks Cabinet support to fund a new, purpose-built leisure centre at Stychbrook Park, in Lichfield. The new centre will replace the current facility at the Friary Grange. This investment, alongside a proposed investment in additional sport and leisure activities (see CIL paper on this agenda), will help encourage more people in the district to live healthy and active lives.
2. Recommendations 2.1 Cabinet approves the principle of funding a new, purpose-built leisure centre at Stychbrook Park, in Lichfield based on £10m of funding provided by the Council. 2.2 Cabinet recommends to Council to approve the Capital Financing Requirement (Borrowing Need) of £5m being initially funded by Internal Borrowing. 2.3 Cabinet recommends to Council an update to the Medium-Term Financial Strategy based on the financial implications section of this report. In the event increases in Approved Budgets become necessary then the changes will be subject to further approval by Council prior to contracts being completed in line with Contract and Financial Procedure Rules. 2.4 Cabinet delegates authority to the Leader and Chief Executive in consultation with the Monitoring Officer and the Section 151 Officer to complete all contracts and funding agreements necessary to successfully deliver the new leisure centre subject to the financial implications being within Approved Budgets.
3. Background 3.1 In October 2019 and following several meetings and consultations regarding Friary Grange Leisure Centre, Full Council decided a replacement facility would be built and to maintain and keep the Friary centre open until then. 3.2 A condition survey identified £2.38m of works needed to keep the building safe, watertight, and weatherproof and keep mechanical and electrical functions working, with a minimum of £503,000 investment needed to make the building safe, watertight, weatherproof, and operational alone. £694,658.62 was assigned with £560,930.17 being used to date, leaving a remaining budget of £130,243.75. Despite this remedial investment, the Friary Centre is still nearing end of useful life with significant further investment required to maintain it in its current poor condition and so a decision on its replacement is now imperative.
3.3Since October 2019, in addition to ensuring the current site remains open, the council’s Major Programmes Team has developed a project to investigate the location, mix and funding of a replacement centre.
Why Stychbrook Park
3.4A review of suitably sized, undeveloped sites in and around Lichfield City identified eight potential sites for the proposed new Lichfield Leisure Centre. They were:
Stychbrook Park Stowe Fields Shortbutts Park Saddlers Wood Leamonsley Park Birmingham Road Site Darnford Park Beacon Park
3.5Of the eight sites, Stychbrook Park was identified as the preferred site for the new leisure centre. The selection of Stychbrook Park as the preferred site was approved by the Leisure Centre Task Group at its meeting on 14 September 2020 and by the Leisure, Parks, and Waste Management (Overview and Scrutiny) Committee at their meeting 23 September 2020, who supported the proposal based on:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.