The Cabinet: 1.1 Approved the installation of a new Skatepark facility at Burntwood Leisure Centre with operational management and responsibility for maintenance assigned to councils wholly owned company Lichfield West Midlands Trading Services (LWMTS). 1.2 Delegated to the Deputy Leader and Property Services and Estates Manager responsibility to agree all necessary agreements to facilitate the project subject to financial implications being within Approved Budgets. 1.3 Recommended to Council to include a project in the Capital Programme for the new Skateboard Facility of £106,000 with (£86,000) of funding provided by Section 106 and a contribution from Burntwood Town Council of (£20,000). Declarations of interest on this item were received from Simon Fletcher and Kerry Dove as directors of LWMTS.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Skateboard Facility at Burntwood Leisure Centre Deputy Leader and Cabinet Member leisure, Parks and Major projects Date: 9 April 2024 Agenda Item: 6 Contact Officer: Andrew Rowbotham Tel Number: [phone removed] Email: [email protected] Cabinet Key Decision? NO Local Ward Chasetown Ward- Councillor Darren Ennis and Members Councillor Laura Ennis
1. Executive Summary 1.1. The current skate park provision is located at Cherry Close in Burntwood at the rear of the Cherry Close Youth Centre. 1.2. Staffordshire County Council (SCC) are due to redevelop the site which includes the removal of the skate park and building on site. The current skate park is not suitable to be relocated and as such SCC will remove with no cost to the Council. 1.3. Council now proposes to install a skate park at Burntwood Leisure Centre to ensure the provision for local groups is still available 1.4. An initial costing exercise has taken place, this has indicated to put in a new provision will be possible for the budget. 1.5. Annex A provides an outline proposal. 1.6. Full plans will need to be drawn up along with applying for planning permission and permission from the Coalfield Industry Social Welfare Organisation (CISWO) who own the land that the Council lease for the Burntwood Leisure Centre.
2. Recommendations 2.1. Cabinet approves the installation of a new Skatepark facility at Burntwood Leisure Centre with operational management and responsibility for maintenance assigned to the District Council. 2.2. Cabinet delegate to the Deputy Leader and Property Services and Estates Manager responsibility to agree all necessary agreements to facilitate the project subject to financial implications being within Approved Budgets. 2.3. Cabinet recommends to Council to include a project in the Capital Programme for the new Skateboard Facility of £106,000 with (£86,000) of funding provided by Section 106 and a contribution from Burntwood Town Council of (£20,000).
3. Background 3.1. The current skate park provision is located at Cherry Close in Burntwood. 3.2. The Council held a lease with SCC for the skate park and this lease has now ended. 3.3. SCC are due to redevelop the site which includes the removal of the skate park and building on site. The current skate park is not suitable to be relocated and as such SCC will remove with no cost to the Council. 3.4. The Council are committed to preserving and developing leisure activities in the district as evidenced by the recent approval of leisure investment across the District including the new Leisure Centre at Stychbrook Park, and therefore working together with Burntwood Town Council a replacement facility is proposed. 3.5. This facility will ensure skaters of the district will continue to have a place to practice, meet, and enjoy the facilities in a safe and secure location.
Alternative options • To not replace the facility. • To advocate for replacement of the facility by Staffordshire County Council or another organisation. • The skate park is provided at a different park within the Burntwood locality. • More funding is identified, and a larger, managed facility is installed.
Consultation Consultation has been undertaken with Ward Members and any views provided will be shared with Cabinet.
Financial The projected capital cost of the new facility in 2024/25 is £106,000 and funding implications will be provided by Section 106 retained by the District Council of (£86,000) and a contribution of (£20,000) from Burntwood Town Council. The costs of operating and maintaining the new facility will be funded from existing Approved Revenue Budgets. Approved by Section 151 Yes Officer
Legal implications 1. Subject to approval from the Coalfield Industry Social Welfare Organisation (CISWO) given the Council lease the land. 2. Subject to approval from Planning Committee. 3. Annual Royal Society for the Prevention of Accidents (ROSPA) inspection required annually. Approved by Monitoring Yes Officer
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.