AI summaryLichfield District Council Cabinet approves a Heritage Shopfront Design Code and a £900,000 grant scheme for Lichfield City Centre shop owners, and backs a Heritage Lottery Fund bid.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDesign code, grant scheme and HLF bid
Money£900,000 capital budgetFor grant programme 2026/27 and 2027/28
What happens nextDesign Code adoption deadlineStatutory deadline 30 June 2026
Who it affectsLichfield City Centre businessesFreeholders, leaseholders and SMEs in conservation area
What was decided
Cabinet approved development of a Heritage Shop Front Design Code for Lichfield City Centre. Report P5
Cabinet approved a grant scheme to support the Lichfield City Centre Heritage Shop Frontage Scheme. Report P5
Cabinet delegated authority to the Cabinet Member to approve the finalised grant scheme, including scoring criteria, triage pathways, grant agreements, monitoring, and payment structure. It also approved development of a Heritage Lottery Fund grant application to seek external funding. Report P5
Why
The scheme aims to deliver regeneration of Lichfield City Centre by recovering, renovating or replacing selected shop fronts, guided by a detailed design code to sustain heritage character. Report 1.3, P2
It will provide financial support to incentivise participation and reduce the cost burden on small businesses carrying out heritage work. Report 1.3, P5
The adopted code will give stronger planning grounds to act against unauthorised or poor quality alterations in the conservation area. Report 1.4
What happens next
The Design Code will go through Cabinet and Council for formal adoption by the statutory deadline of 30 June 2026, with a four-week statutory consultation to follow. Report P11
A Heritage Lottery Fund bid will be developed to seek additional external funding, with a communications plan to support business uptake and public confidence. Report P118
Final scheme details, including scoring criteria, triage pathways, grant agreements, monitoring requirements, and payment structure, will be approved by the Cabinet Member. Report P5
The money
£900,000 Capital budget for grant programme in 2026/27 and 2027/28, approved by Council on 24 February 2026 Report P12
£20,000 Allocated to date for the design code Report P12
£4,000 Allocated to date for the Heritage Lottery Fund bid Report P12
£940k Indicative total across around 60 shopfronts at the recommended grant tier mix Report P71, P72
£600k Indicative cost of 20 full reinstatements at £30k each Report P71
£240k Indicative cost of 20 partial restorations at £12k each Report P71
£100k Indicative cost of 20 minor enhancements at £5k each Report P71
Options considered
Chosen: Option B: Tiered by Heritage Sensitivity (75% up to £30,000 for full reinstatement, 50% up to £15,000 partial, 30% up to £7,500 minor). Best option for achieving strong design code alignment while allowing the biggest transformational projects and distributing funding fairly. Report P69, P58, P59, P60, P61
Rejected: Option A: Tiered by Business Size (70% micro, 50% small, 30% medium) Report P52, P53, P54, P55, P56
Rejected: Option C: Tiered by Location Priority (up to 75% and £35,000 in Priority Zone A). Not preferred as the primary model. Report P64, P65, P66, P67
Rejected: Do Nothing. Shop owners would face the full cost of meeting the design code without grant support. Report P9
Rejected: Restart the process with a different grant scheme. Unlikely to produce new options and risks further decline of the city centre. Report P9
Rejected: Proceed without an enhanced Design Code. Improvements would be less coherent and less impactful across shopfronts. Report P9
Chosen: Delivery Option 2: Business Led Delivery. Allows businesses to retain autonomy over procurement and delivery, with the council providing framework, guidance, and funding without taking on warranties or operational burden. Report P108, P113
Rejected: Delivery Option 1: Council Led Delivery. Higher resource demand and longer lead times for the council. Report P113
Rejected: Delivery Option 3: Outsourcing Delivery. Higher cost and less direct council control. Report P109, P110, P111, P113
Implications
Financial: £900,000 capital budget is earmarked over 2026/27 and 2027/28, with further funding to be sought through a Heritage Lottery Fund bid. Report P12
Legal: Legal advice will be required to administer the grant scheme lawfully, including agreements, contracts, governance, and Subsidy Control compliance. Report P13, P81, P28
Equalities: The scheme can support heritage-sensitive accessibility improvements such as DDA compliant entrance thresholds, clearer navigation, and improved lighting. Report 1.4, P18
Climate: The scheme prioritises retaining and repairing existing historic fabric over replacement, and may specify sustainable construction methods and low impact materials. Report P16, P22
Risk: Eleven risks are tracked (A to K), covering low participation, design code adoption, HLF bid success, funding, capacity, inappropriate applications, vocal opposition, poor value perception, maintenance, subsidy control, and the 30 June 2026 SPD deadline. Report P24, P25, P26, P27, P28
Staffing: The Major Projects Team will manage the scheme to mobilisation and delivery, with a later review on whether to transfer it to another team as business as usual. Report P85
Other: Crime and safety may improve through clearer sightlines, brighter frontages, more activity, and increased passive surveillance. Report P21
Who and where
Freehold property owners within the Lichfield City Conservation Area Report P33
Leaseholders with written freeholder permission Report P33
Independent small and medium sized enterprises and sole traders occupying ground floor commercial premises Report P33
Social enterprises and community run businesses with public facing shopfronts Report P33
National multiples and large chains (generally excluded, except in exceptional heritage cases) Report 1.2
Owners or landlords involved in an enforcement case for breaching conservation area terms Report 1.2
Lichfield City Centre residents and visitors Report P15, P136, P137
Local suppliers, contractors, and craftspeople in the Lichfield District Report P15
Timeline
24 February 2026: Council approved the £900,000 capital budget for the grant programme Report P12
7th April 2026: Cabinet decision to approve the design code, grant scheme, delegated authority, and Heritage Lottery Fund bid Report P1
30 June 2026: Statutory deadline for adopting the updated Design Code as a Supplementary Planning Document
Within 6 months of approval: Approved work must commence Report P74
Within 12 months of approval: Work must be completed unless formally extended Report P74
At least 5 years after completion: Businesses must maintain the shopfront, with a sliding scale repayment if they leave early Report P76
Plain English for the jargon
SPD: Supplementary Planning Document, a type of planning guidance that must follow a statutory process.
HLF: Heritage Lottery Fund, a potential external funder for heritage projects.
DDA: Disability Discrimination Act, the legal framework for accessibility standards.
EOI: Expression of Interest, an initial application step used in the grant process.
SME: Small and Medium sized Enterprise, a business scale category used in eligibility rules.
RYG: Red, Yellow, Green, the colour coded risk scoring system used in the risk register.
BAU: Business as Usual, referring to routine council operations after a project ends.
Section 151 Officer: The council officer with statutory responsibility for financial administration.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3
Resolved
The Cabinet: 2.1 Approves the development of a Heritage Shop Front Design Code for Lichfield City Centre. 2.2 Approves the introduction of a grant scheme to support the Lichfield City Centre Heritage Shop Frontage Scheme. 2.3 Cabinet delegates authority to the Cabinet Member to approve the finalised Shopfront Improvement Grant Scheme, including scoring criteria, triage pathways, grant agreements, monitoring requirements, and payment structure. 2.4 Approved development of a Heritage Lottery Fund grant application, seeking external funding to further support the implementation of the Shop Front Design Code across the city centre.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Heritage Shopfront Design Code & Grant Scheme Councillor Richard Holland Date: 7th April 2026 Agenda item: 3 Contact officer: John Smith Tel number: CABINET Email: [email protected] Key decision? Yes Local ward members
1. Executive summary 1.1 To deliver a high-quality regeneration scheme for Lichfield City Centre by recovering, renovating or replacing selected shop fronts. The city centre businesses will be guided by a detailed design code that aids owners create and sustain high quality, attractive frontages in line with the city’s traditional streetscape. 1.2 The Shop Frontage Heritage Grant Scheme will support the implementation of the emerging Design Code, ensuring consistency, quality, and character-led improvements across the area. Providing financial support to incentivise participation and reduce the cost burden on small businesses.
1.3The grant scheme will encourage property owners and tenants to restore shop frontages to their authentic early period heritage appearance enhancing the visual quality, historic character, and economic vitality of the town centre.
1.4This strengthened framework will align fully with the Council’s conservation approach and, while grant funding will not be used for enforcement, the adoption of a clear, city centre specific design code will better support planning enforcement activity where required to act against unauthorised or poor quality alterations helping to safeguard the long-term integrity of the conservation area.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.