AI summaryCabinet approves moving Lichfield's Local Plan to the new 30-month system, pushing adoption from 2027 to 2029 to allow fuller evidence work for the 746 homes per year target.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegation to serve notice of commencement and publish timetable
Money£240,000 earmarked reserve; £90,000 annual budgetReserve balance at 1 April 2026, current yearly budget
What happens nextNotice of commencement by 30 June 2026Triggers the 30-month preparation period
Who it affectsAll wards, residents, developers, infrastructure providersPlan covers district to 2043, targets 15,666 new homes
What was decided
Cabinet approved switching the Local Plan to the new 30-month system under the Town and Country Planning Regulations 2026. Report P4
Cabinet delegated authority to the Cabinet Member for Housing and Local Plan, with the Chief Executive, to serve the notice of commencement and publish the timetable. Report P4
Why
The April 2025 National Planning Policy Framework update raised the housing target by 158% to 746 homes per year, requiring a deeper evidence base than the legacy system allows. Report P3, P6
Officers warned that rushing the plan to meet the 31 December 2026 legacy submission deadline risked it being found unsound at examination, which would further delay adoption. Report P6, P10
The new 30-month system gives time to assess new settlement options, infrastructure capacity, transport, environmental impact and overall deliverability. Report P3, P6
What happens next
The Cabinet Member and Chief Executive will serve a notice of commencement and publish a new Local Plan timetable, with the preparation period starting at Gateway 1 in November 2026. Report 3.13, P8, P9
A scoping consultation is scheduled for September 2026 for 21 days, ending in October 2026 before the self-assessment is published. Report P8, P9
Planning applications will continue to be decided under the existing Local Plan and national policy until the new plan is adopted, now expected in 2029 rather than 2027. Report P6
The money
£588,000 Spent on the new Local Plan to date Report P6
£352,693 Government grant received for the Local Plan process Report P6
£466,000 Cost of the previous plan withdrawn from examination in 2023 Report P6
£240,000 Estimated balance of the Local Plan Earmarked Reserve at 1 April 2026 Report P12
£90,000 Current annual budget for the Local Plan Report P12
£227,963 Government grant received in 24-25 Report P14
£55,000 Government grant received in 25-26 Report P14
Options considered
Rejected: Continue the Local Plan 2043 under the legacy system and submit by 31 December 2026. Evidence base and draft plan are not complete; risk of missing the deadline and the plan being found unsound at examination Report P6, P10
Chosen: Switch to the new 30-month plan-making system under the 2026 Regulations. Allows a deeper evidence base, time to assess new settlement options, and reduces the risk of the plan being found unsound Report P3, P4, P6
Implications
Financial: Additional costs are expected for evidence base updates, including a new Housing and Economic Development Needs Assessment and a Green Belt Study Part 2, and for digital map-based plan making requirements. Report P12, P13
Legal: The Council must keep preparing a Local Plan under Section 15 of the Planning and Compulsory Purchase Act 2004 and Regulation 18 of the 2026 Regulations, and faces a risk of Secretary of State intervention under Section 27 if progress stalls. Report P14
Risk: Risks include MHCLG disagreement with the switch, loss of developer confidence, more speculative applications and appeals, and uncertainty from Local Government Reorganisation with a new unitary authority vesting in April 2028. Report P23
Other: Planning applications will continue to be assessed under the existing Local Plan and national policy during the extended preparation period, with weight given according to relevance and status. Report P6
Who and where
Residents, businesses and stakeholders across all wards of Lichfield district Report P2, P6
Landowners and developers promoting sites through the Local Plan Report P23
Infrastructure providers and neighbouring authorities Report P6, P23
Parish and Town Councils with Neighbourhood Plans Report P6
Timeline
12th May 2026: Cabinet decision to progress under the new plan making system Report P8
By 30th June 2026: Notice of commencement and publication of the Local Plan timetable, 4-month period begins Report P8
September 2026: Scoping consultation for 21 days Report P8
October 2026: End of scoping consultation Report P9
November 2026: Self-assessment published and Gateway 1; 30-month plan preparation period begins Report P9
31 December 2026: Deadline for legacy system plans to be submitted for examination Report P6
April 2028: New unitary authority expected to be vested under Local Government Reorganisation Report P23
2027 to 2029: Anticipated Local Plan adoption date pushed back from 2027 to 2029 Report P6
Plain English for the jargon
NPPF: National Planning Policy Framework, the government's planning policy document for England
LDS: Local Development Scheme, the timetable for producing Local Plan documents, now called the Local Plan timetable
SPD: Supplementary Planning Document, providing detail on policies in the Local Plan
MHCLG: Ministry of Housing, Communities and Local Government, the responsible government department
Section 27: Section 27 of the Planning and Compulsory Purchase Act 2004, which lets the Secretary of State intervene in plan preparation
CIL / Section 106: Community Infrastructure Levy and Section 106 legal agreements, used to collect developer contributions for infrastructure
Gateway 1: An early checkpoint in the new plan-making system where the Planning Inspectorate reviews the council's self-assessment
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item3
Resolved
The Cabinet: 2.1 Approved a move to a Local Plan submission under the new 30 month system in line with the Town and Country Planning Regulations 2026. 2.2 Delegated authority to the Cabinet Member for Housing and the Local Plan in conjunction with the Chief Executive, to serve the notice of commencement and publish the timetable for the new Local Plan.
Word for word from the decision Lichfield published for this meeting.Source: democracy.lichfielddc.gov.uk
Lichfield District Local Plan Councillor Alex Farrell, Cabinet Member for Housing & Local Plan Date: 12th May 2026 Agenda item: 3
Contact officer: Simon Fletcher/ Lucy Robinson Tel number: 01543 308001/ 01543 308710 CABINET Email: [email protected]/ [email protected] Key decision? YES Local ward All wards members
1. Executive summary 1.1 This paper provides Cabinet with an update on the progress the Council has made in developing its latest Local Plan. In doing so, it reflects on: • the impact the April 2025 update of the National Planning Policy Framework (NPPF) had on the housing target for Lichfield district, (increasing it to 746 houses per year - 15,666 over the plan period 2022-2043 - a 158% increase on the previous target of 289 houses per year), and • the opportunity to develop a deeper evidence base to support a preferred option for distributing growth across the district to achieve this revised housing number, provided through the new Town and Country Planning Regulations under the new condensed timeframe of 30 months for non ‘legacy system’ plans. 1.2 If the proposal to change to the new 30-month process is approved, it will allow time for the new plan to adequately address and include options for new settlements - new, planned communities in appropriate locations, alongside other approaches. This approach would better ensure that growth can be planned in the right locations and supported by the necessary infrastructure, while protecting landscapes, heritage and the character of the district. 1.3 While this would extend the overall timeline for adopting the Local Plan, it would strengthen the council’s ability to manage development in the long term and also presents an opportunity to produce a clearer, more user-friendly plan for the benefit of residents and businesses.
2. Recommendations 2.1 That Cabinet approve a move to a Local Plan submission under the new 30-month system in line with the Town and Country Planning Regulations 2026. 2.2 That Cabinet delegate authority to the Cabinet Member for Housing and the Local Plan in conjunction with the Chief Executive, to serve the notice of commencement and publish the timetable for the new Local Plan.
3. Background 3.1 A Local Plan sets out the long‑term spatial vision and planning framework for the area, guiding where development should take place, what form it should take, and how land will be used to meet the needs of current and future communities. It provides the basis for making decisions on planning applications and for coordinating investment in homes, jobs, infrastructure and the environment.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Procurement Matters Update 2025/26The Cabinet: 2.1. Reviewed the contents of this report and the progress against planned actions in the Action Plan fo...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.