Resolved
RESOLVED that the report be noted.
Performance Scrutiny Committee noted this item on Thursday 24 May 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
RESOLVED that the report be noted.
1.1To provide members with a progress report on the strategic projects, against their milestones for the final quarter of 2017/18.
2. Programme Summary
2.1There are currently 16 strategic projects being monitored.
2.214 projects are currently on track in terms of their physical and financial milestones and risk profiles.
Of these 2 projects have been completed and are currently awaiting a Post Implementation Review to be submitted and signed off.
2.3There are no projects off track in terms of all three of the areas of monitoring: physical progress, financial position or risk analysis.
2.4It has been concluded that there are no projects of sufficient concern to bring to members attention.
3. New Projects Approved
3.13 new projects were reviewed and recommended to the Executive for approval in the final quarter.
Noise Reduction Equipment
This project is to purchase two complete noise kits for measuring and recording noise in complainant’s homes and for the investigation of noise complaints.
Broadgate Lift Refurbishment
This project is for a full refurbishment to both lifts at Broadgate Car Park and the works will include lift car upgrade and upgrades to both the mechanical and electrical equipment. Tree Memorial
This project is to purchase a new memorial for the crematorium grounds that will aim to offer an affordable memorial option for the friends and families of the deceased.
4. Completed Projects and those awaiting PIR’s
4.1Where it is felt appropriate and beneficial for continuous improvement at the conclusion of a project a completion report and post implementation review (PIR) will be produced. Once they are received and reviewed a project is considered to be complete.
4.2Strategic Projects awaiting completion of a PIR
There are two projects which have completed their defined actions and just now await the completion of a PIR
New Surface Car Parks – Purchase of two new surface car parks in the city
The following project has submitted an initial PIR, but additional data was requested, so they will be finalised when the data is made available.
Bereavement Services improvements to facilities
4.3There were six projects signed off as completed during the final quarter.
Broadgate Car Park improvements – This project delivered structural concrete improvements, major improvements to the deck surfacing on certain floors and general improvement works in order to modernise the car park. The car park now meets modern safety requirements following the works.
Birchwood Bungalows – This project delivered 20 new build affordable units on 5 individual sites previously occupied by council owned garages. The bungalows all had level floor access and are energy efficient properties which in-turn will benefit the tenants by reducing energy costs. This project also assisted towards increasing the supply of affordable housing within the City.
City Hall Phase 2 Improvements – The second phase of improvements delivered a number of desired objectives including the remodelling of the whole of the fourth floor as new offices for prospective tenants, the creation of a medical assessment centre on the ground floor and the installation of LED lighting and CCTV to public areas.
Implementation of Servitor (Repair Ordering and Billing System) – This project delivered a new computer system to replace the outdated and unsupported billing system (DepotMaster) for the Housing Repair Service. The new system interacts in real time with tradesmen allowing on-line live information exchange which in-turn negates the need for extensive paperwork. The system, which utilises mobile technology, also interfaces with other Housing management software systems most notably Universal Housing, the main service programme, and DRS the repair job scheduling system.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Strategic Plan Progress: Outturn 2017-18Report | 85 KB | DownloadRead as text |
Follow Performance Scrutiny Committee at Lincoln and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Aug 2026 | Confirmation of Minutes - 9 July 2026RESOLVED that the minutes of the meeting held on 9 July 2026 be confirmed subject to the following amendment: - Counc... | Decided | Open |
| 13 Aug 2026 | To Receive the Minutes of Housing Scrutiny Sub-Committee - 4 June 2026RESOLVED that the minutes of the Housing Scrutiny Sub-Committee meeting held on 4 June 2026 be received. | Decided | Open |
| 13 Aug 2026 | Financial Performance - Quarterly MonitoringRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Treasury Management & Prudential Code – Quarterly UpdateRESOLVED that this item be deferred to the next meeting of the Performance Scrutiny Committee. | Deferred | Open |
| 13 Aug 2026 | Income and Arrears MonitoringRESOLVED that the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.