Resolved that in relation to the progress of land reclamation on Merseyside – (i) the New Approaches Study be endorsed and that ‘in principle’ support for the next stages of the development and approval process be approved; (ii) Knowsley MBC’s offer to act as Accountable Body for the New Approaches Programme be supported (as approved by Knowsley’s Cabinet 22 January 03), to be confirmed in a letter of support; (iii) the list of 15 Priority Projects that has been drawn up and to the list of Phase 1 projects be approved and that the Executive Director (Regeneration) writes to Knowsley MBC confirming support; (iv) each Local Authority should contribute to the preparation of the Commencement Business Plan in providing pre-developing costs, by agreeing to assign officer time to support the Steering Group through to the commencement of the Phase 1 programme; (v) the existing New Approaches Steering Group should be chaired by Knowsley Council; and its membership broadened for the purposes of overseeing the preparation of the Commencement Business Plan and the development of NAP governance and management arrangements through the preparation of a Governance and Management Report; (vi) authority be given to the Assistant Executive Director (Regeneration, Policy & Programmes), as lead officer acting for and on behalf of Liverpool City Council; and (vii) further reports on progress be submitted to the Executive Board and before any commitment to individual projects within the overall programme is made.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1 In response to the NWDA’s commitment to increase its expenditure on land reclamation in the North West, focusing specifically on ‘soft-end’ uses (public open spaces, nature conservation etc), three programmes are currently being developed which will impact upon Liverpool and Merseyside:-
• Greater Merseyside Gateways and Corridors Programme – ‘New Approaches Programme (NAP)’ • City Centre Environmental Improvement Programme • Liverpool City Wide Land Reclamation Programme
2 The attached report (including details at Annex 1) focuses on and provides Members with details of the proposed New Approaches Programme (NAP) including:
• Progress to date. • Preparation of the Business Plan and pre-development work. • Governance and Management issues. • The next stages in the appraisal and approval process • and to gain “in principle” support for the next stages in the development of the New Approaches Programme (NAP).
3 A more detailed report setting out the above is attached at Annex One. However, a summary has been provided which draws on the issues that need to be considered by Members. Background
4 Members have previously been informed of the progress on the NWDA funded New Approaches (NAP) Study. The appointed Consultants, TEP, have now completed the final report. From a list of over 300 sites, 80 priority sites, suitable for reclamation for soft end use, have been identified and organised into 15 project proposals based on a thematic and spatial framework around key gateways and corridors (see Annex 1). The total cost of the 15 project proposals is estimated to be approximately £41 m. This list has been approved by the Merseyside Co-ordinating Committee.
5 It has identified some of the key gateways and corridors into the City and complements existing schemes, particularly the SIAs and the City Centre Movement Strategy. The bulk of work in the preparation of the NAP study was carried out in consultation with the SIAs, City Council Officers etc, including workshops. All comments were taken on board.
6 Due to the scale and complexity of the NAP it is proposed to adopt a phased approach over the period of the 6 year programme (2003-09). A list of Phase 1 schemes has been identified on the basis of the schemes’ early implementation. Phase 1 schemes need to be agreed by the Merseyside Districts as soon as possible. The indicative cost of Phase 1 is in the region of £15 - £20m which will take up around 40% of the available funding. The indicative Phase 1 schemes are:
• A580 North City approaches transport corridor; • St Helens approaches transport corridor; • Wirral Maritime and Bidston Parkway transport corridor • A5036 Dunningsbridge transport corridor • Gateway Art • City Limits Gateways
7 Details of the entire programme, its phasing, incorporating future phases, is not yet clear. Districts need some clarification from the NWDA of when the commencement of future phases is anticipated to ensure that it dovetails with other work that is underway. This will ensure synergy between the work of our SIAs and with that of Liverpool Vision, encouraging maximum impact for all the SIA programmes and maximising opportunities to secure Objective 1 funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.