Resolved that – (i) the Measure 19 Delivery Plans be approved and submitted to the Government Office for the North West and North West Development Agency. (ii) approval be given for the inclusion in the City Council’s capital programme for 2003/4 of £10,074,000 of ERDF grant and £9,786,000 of NWDA grant and a further £668,750 of ERDF grant in the revenue budget on condition that GoNW and NWDA give their formal approvals to the SIA Delivery Plans. Details of individual projects will be reported to Members for consideration and approval .; (iii) the City Council will continue to act as the Accountable Body for the expenditure of ERDF and NWDA grant during the financial year 2003/04 in respect of the SIA Programme and the individual projects referred to in the Measure 19 Delivery Plans; (iv) the Assistant Executive Director (Financial Management) be authorised to amend the budget and create new cost centres for revenue schemes which have received Board Approval, where the GONW and NWDA has approved general resources that can be allocated to specific schemes by the respective Partnership Boards; and (v) the Executive Director (Regeneration) be authorised to submit the necessary applications for funding for projects included in the Delivery Plans, and to act as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. to present to the Executive Members for Regeneration and Resources the Measure 19 Year 3 Delivery Plans for Atlantic Gateway, Approach 580, Speke/Halewood, and Eastern Approaches SIA’s; 2. to outline the requirement for public sector funding from Liverpool City Council, ERDF, and NWDA for 2003/4 in respect of those projects; and 3. to seek authority for those funding requirements to be included in the LCC 2003/04 Capital Programme.
SIA’s are the single largest measure in the Merseyside Objective 1 programme, with a total of £140 million ERDF notionally available under measure 19. The SIA’s need to perform in order that the programme as a whole is delivered effectively. Importantly, SIA’s must perform well to avoid the prospect of programme level de-commitment, whereby unused funds could, potentially, be clawed back by the European Union. The deadline for review is December 2003 (the mid term point of the programme).
In order to avoid de-commitment and inject realism into the SIA programmes, a Peer Review exercise was undertaken during November 2002. The outcome of this was reported to the Merseyside Chief Executives in January 2003. The resultant Delivery Plans, are framed to reflect the conclusions of this Peer Review and the urgency to commit funds by December 2003. Details of the SIA funding requirements are outlined in the attached report, along with SIA programme synopses.
Measure 19 projects, as defined in the Merseyside Objective 1 Strategy, are Priority 3 schemes which relate to developing locations through Strategic Spatial Development.
The responsibility for the delivery of the programmes rests with individual programme delivery teams, with transport schemes delivered by LCC, and development projects delivered by Liverpool Land Development Company. The detail of all development projects within the SIA’s for this and future years, is contained within the LLDC Business Plan which will be reported to Members separately.
The Strategic Investment Areas programmes are now in the third year of delivery. The programmes have until December 2008 to fully deliver the approved programmes and projects. Each of the Delivery Plans has now been endorsed by their respective Partnership Boards as the basis for investment over the forthcoming year . The figures in the Year 3 plans reflect the financial requirement for 2003/4, and Members will be informed of progress throughout 2003/4, and any variations to these figures will be reported.
Executive Director recommendation (Charlie Parker)
That the Board -
1. Approve the Measure 19 Delivery Plans and authorise their submission to the Government Office for the North West and North West Development Agency.
2. Approve the inclusion in the City Council’s capital programme for 2003/4 of £10,074,000 of ERDF grant and £9,786,000 of NWDA grant and a further £668,750 of ERDF grant in the revenue budget on condition that GoNW and NWDA give their formal approvals to the SIA Delivery Plans. Details of individual projects will be reported to Members for consideration and approval.
3. Approve that the City Council will continue to act as the Accountable Body for the expenditure of ERDF and NWDA grant during the financial year 2003/04 in respect of the SIA Programme and the individual projects referred to in the Measure 19 Delivery Plans.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.