Resolved that – (i) Liverpool City Council acts as Accountable Body for Objective 1 funding in respect of projects at 101 Old Hall Street; Fleet St/ Holmes Building; St Peters Church; Sentinel/ Richmond House ; (ii) on the receipt of offer letters from the Government Office North West - · authority be granted for the Assistant Executive Director (Regeneration, Policy and Programmes ) to accept capital grant of £7,424,832.00 phased over the financial years 2003/04 2006/07 to contribute towards the costs of delivering the four schemes; 101 Old Hall Street: Fleet Street/Holmes Building: St Peters Church; Sentinel/ Richmond House; and · the Divisional Manager (Regeneration Programmes ) be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises; (iii) the City Council’s capital programme be adjusted, to reflect expenditure on these projects for a sum up to £7,424,832 phased over the financial years 2003/4 (£2,421,474), 2004/5 (£2,032,248) 2005/6 (£2,803,508) and 2006/7 (£167,602); (iv) expenditure be committed to each of the projects namely 101 Old Hall Street; Fleet St/ Holmes Building; St Peters Church; Sentinel/Richmond House , after the confirmation of funding from all the relevant organisations / bodies upon which this project relies and the finalisation of all other relevant documents; and (v) further reports to be submitted to Members as and when appropriate to update on progress.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. Liverpool City Council as a key partner in the regeneration of the City Centre, and as Accountable Body for Liverpool Vision, the City Centre Urban Regeneration Company, must act as the Accountable Body for Objective 1 ERDF to allow the funding to be accessed and then used towards the delivery of a number of City Centre capital works schemes. The schemes requiring agreement to act as Accountable Body at this stage are: • 101 Old Hall Street; • Fleet St/ Holmes Building; • St Peters Church; • Sentinel/ Richmond House
2. Each project will be delivered in partnership, primarily by the private sector, supported by Liverpool Vision and the City Council as Accountable Body for the Objective 1 grant. All projects sit within the Liverpool Vision Strategic Regeneration Framework complementary to the City Council's Corporate Objectives and those of Liverpool First the City’s Community Strategy. Liverpool First is committed with Liverpool Vision to create a competitive, sustainable and inclusive City Centre of major international significance.
3. Appendix 1 describes briefly each project, its funding package, timescale for delivery and anticipated outcomes. In all the four projects comprise four separate bids for Objective 1 funding but also separate bids for NWDA funding made directly to the Agency by the private sector. This report seeks authority from LCC to act as Accountable Body for Objective 1 funding, effectively applying for and accepting grant, and then facilitating the processing of Objective 1 grant claims and the payment of the grant to the private companies involved.
There is no requirement to fund these projects from LCC budgets simply to act as a conduit for Objective 1 grant. Executive Member/Director recommendation. Councillors Peter Millea and Chris Curry/ Charlie Parker
That -
(i) Liverpool City Council acts as Accountable Body for Objective 1 funding in respect of projects at 101 Old Hall Street; Fleet St/ Holmes Building; St Peters Church; Sentinel/ Richmond House;
(ii) on the receipt of offer letters from the Government Office North West -
• authority to be given to the Assistant Executive Director Regeneration, Policy & Programmes, to accept capital grant of £7,424,832.00 phased over the financial years 2003/4 to 2006/7 to contribute towards the cost of delivering the four schemes; 101 Old Hall Street; Fleet St/ Holmes Building; St Peters Church; Sentinel/ Richmond House; and
• The Divisional Manager for Regeneration Programmes be appointed as the nominated officer for monitoring compliance with the terms and conditions of the grant. This includes maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year in which the liability arises;
(iii) the City Council’s capital programme be adjusted, to reflect expenditure on these projects for a sum up to £7,424,832 phased over the financial years 2003/4 (£2,421,474), 2004/5 (£2,032,248) 2005/6 (£2,803,508) and 2006/7 (£167,602);
(iv) expenditure be committed to each of the projects namely 101 Old Hall Street; Fleet St/ Holmes Building; St Peters Church; Sentinel/ Richmond House, after the confirmation of funding from all the relevant organisations/bodies upon which this project relies and the finalisation of all other relevant documents; and
(v) further reports to be submitted to Members as and when appropriate to update on progress.
Key Decision: Yes Forward Plan:
No- Appropriate notices have been published in accordance with the constitution
Implementation effective from:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.