Resolved
Resolved that authority be granted for the award of a contract in respect of Postal Services to Secured Mail. L/24
Cabinet 2010/21 decided this item on Friday 4 March 2011. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that authority be granted for the award of a contract in respect of Postal Services to Secured Mail. L/24
Contract Standing Order 9.9 requires that for all contracts where the tender price, together with all associated fees and other relevant costs have an estimated value of over £500,000, the acceptance of the tender must be carried out by the Cabinet upon a report by the Head of Business Unit/Assistant Director in consultation with the Director and Head of Procurement.
Purpose of Report To seek Cabinet approval to award a contract for the provision of Postal Services.
Background The Cabinet approved the recommendation to undertake a competitive procurement exercise for the provision of Postal Services at its meeting on 26th November 2010. Following this approval a mini-competition was undertaken between suppliers on the OGC Buying Solutions framework agreement for Postal and Courier Services (service contract reference RM782). 6 organisations were invited to tender, of which 4 returned completed proposals. These organisations were Royal Mail, TNT, Secured Mail and UK Mail. The bids were evaluated against the following criteria. • Proposed approach to service delivery 40% • Whole life costs 60%
Scores Royal Mail 62.50% TNT 77% Secured Mail 94.50% UK Mail 23%
The officer recommendation is to award the contract for Postal Services to Secured Mail, based on this evaluation.
Cabinet Member recommendation: That authority be granted for the award of a contract in respect of Postal Services to Secured Mail
Corporate Aim(s): To reduce the cost of services.
Key Decision: Yes.
Forward Plan: No. it was not possible to include in Forward Plan due to the timescales involved in the process.
Implementation effective from: 11 March 2011
Timescale for action The contract will be awarded to Secured Mail immediately following the expiry of the call in period following the Cabinet meeting on 04/03/2011
Reason(s) for Recommendation: Secured Mail secured a score of 94.50% in the evaluation process. Although not significantly better than Royal Mail and TNT in respect of the quality of their proposal for delivering services, they were significantly lower in cost than these bidders.
Alternative options were outlined in the pre-procurement approval papers presented to Cabinet on 26/11/2010. Consultation including consultation with Ward Councillors and outcome: n/a
Financial implications (Efficiency Savings): Where approval is sought to award a contract: The anticipated contract value was £700,000 p.a. based on previous actual expenditure figures. It has been estimated that as a result of undertaking this procurement exercise cashable savings of £60,000 p.a will be achieved.
Legal implications: In the procurement of good, services and works the Council is required to comply with the Public Contracts Regulations 2006 (‘the Regulations’) where relevant and the Council’s Contract Standing Orders. The Regulations apply when the relevant financial thresholds are exceeded - goods and services the threshold is £156,442 and for works the financial threshold is £3,927,260 The Regulations divide services into so called Part A (or priority services) and Part B (or residual services). Only Part A services are fully caught by the Regulations. Part B services are caught by a lesser regime.
Failure to comply with the Regulations can lead to formal legal challenge under the Regulations, the remedies available to the Court in the event of an illegal award is the cancellation of the contract awarded (so compensation to the contractor it had wrongly contracted with) , impose a civil fine and the aggrieved bidders awarded damages.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Approval to Award a Contract for Postal Services (R&T/31)Report | 4 pages | DownloadRead as text |
Follow Cabinet 2010/21 at Liverpool and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 5 Jun 2020 | Minutes of Last MeetingResolved that the minutes of the Virtual Cabinet held on 22 May 2020 be approved. | Approved | Open |
| 5 Jun 2020 | Adult Social Care Infection Control Fund (SCH/1)On the 13 May the Government announced a £600m Infection Control Fund for adult social care homes. Further guidance a... | Decided | Open |
| 5 Jun 2020 | Better Roads - Highways Investment Programme & Temporary Cycle Lanes (RH/1)This report provides an update and seeks further approvals to progress with the Better Roads programme, particularly ... | Approved | Open |
| 5 Jun 2020 | Capital Programme 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
| 5 Jun 2020 | Revenue Budget 2019/20 - Final Outturn PositionDuring the course of each financial year, monitoring reports are submitted on a monthly basis to Cabinet advising of ... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.