Resolved that – (i) Bidder 2 as identified in the Evaluation Report annexed to the report submitted be appointed as the Preferred Bidder; (ii) the Interim City Solicitor and the Director of Regeneration and Employment be authorised to prepare all necessary legal documentation to award the contract; (iii) upon completion of the final development agreement and guarantees, the scheme detail for each Lot will be reported to Cabinet; and (iv) If satisfactory agreement with the Preferred Bidder cannot be entered into, authority be provided to the Director of Regeneration and Employment in consultation with legal and financial services to change all necessary legal documentation with the proposed reserved bidders.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
Appendices 1-4 to this report are EXEMPT and not for publication by virtue of section 100 A (4) of the Local Government Act 1972 as defined under paragraph 3 of Part 1 of Schedule 12a of the Act as amended.
WARD – Picton, Princess Park STATUS: Public HCS/13
Cabinet Member: Director: Councillor Ann O’Byrne - Housing and Nick Kavanagh, Director of Community Safety Regeneration and Employment
Councillor Paul Brant – Finance and Peter Timmins, Interim Director of Resources Finance & Resources
Date of submission: Subject: Contract Award Approval – 3rd February 2012 Refurbishment of Council owned properties.
Report No.: EDR/9/12 Contact Officers: Background papers: Julie Wickington, Jane Christopher L/26 Properties Acquired for Regeneration
Executive summary Cabinet is requested to approve the recommendation in the appended report, to award the contract NWCE-8H9AFY, Refurbishment of Council owned properties to the preferred bidder. The final details and guarantees will be reported to the Cabinet in a separate report. When the project is delivered it will bring back into use 180 Council owned properties in 3 neighbourhood areas in the inner core of the city.
Purpose of Report Contract Standing Order 9.9 requires that for all contracts where the tender price, together with all associated fees and other relevant costs have an estimated value of over £500,000, the acceptance of the tender must be carried out by the Cabinet upon a report by the Head of Business Unit/Assistant Executive Director in consultation with the Executive Director and Head of Procurement. Following the evaluation of the final tender, the Cabinet is asked to consider and approve the recommendation in the appended Evaluation Report.
The purpose of this report is therefore to seek Cabinet approval to award the refurbishment contract (NWCE-8H9AFY) to the preferred bidder (please see appended Evaluation Report).
Background Authority was granted by the Council’s Cabinet on 18th March 2011 to prepare a brief and invite tenders from interested organisations and investors for the refurbishment of 180 Council owned properties in the Webster Triangle East, Arnside Road and Granby 4 Streets areas. The properties are within 3 neighbourhoods of the city and the table below provides an overview of the Lots in the tender (NWCE-8H9AFY).
Lots Number of LCC owned properties Lot 1 133 Granby Triangle/ Four Streets Lot 2 25 Webster Triangle East Lot 3 22 Arnside Road
The Council’s major goal is to secure a balanced mix of property types and tenure to encourage mixed income and inclusive communities, the overall objective of this procurement exercise is to bring back into use 180 vacant Liverpool City Council (LCC) owned properties. In pursuing this scheme LCC sees the opportunity to attract investment and introduce financially viable refurbishment models.
The bidders were asked to demonstrate how they would work with the Council and key stakeholders to deliver innovative and exciting change to the housing market, provide affordable homes to own or rent, improve the residential environment and accommodate the needs and aspirations of existing residents. The Council acknowledged however, that it may not be economically viable to refurbish some of the properties and that selective demolition may be an option to consider. The brief requested a start on site by June 2012 and that the scheme be physically completed by 2015.
The Procurement Process The procurement was run in accordance with the EU Procurement Directive 2004/18/EC using the Competitive Dialogue Procedure.
An OJEU Contract Notice (107-175300) was published and completed pre- qualification questionnaires were submitted by 12 candidates.
Following the evaluation of the submissions 7 organisations were invited to participate in the first stage of the Competitive Dialogue and to submit Outline Solutions. During this stage, 4 organisations withdrew from the process. Outline Solutions were submitted by 3 organisations.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.