Resolved that – (i) the Executive Director (Regeneration) be authorised to accept NWDA grant totalling up to £968,000 (limited to 12 months from the date of signing the contract) and, in doing so, permit the City Council to accept the role of accountable body; (ii) the Planning Manager be appointed as the nominated officer for the purposes of monitoring compliance with the terms and conditions of the grant. The duties of the nominated officer will include maintaining a constant review of the risk of grant being clawed back under grant rules and regulations and making budgetary provision to cover any requirement to repay grant in the financial year that the liability is likely to arise; (iii) the Capital Programme be amended for the financial years 2003/04 (£755,000) and 2004/05 (£323,000) to reflect expenditure of £1,078,000 on the Buildings at Risk programme funded by £968,000 from the NWDA and £110,000 of City Council general capital resources; (iv) the commitment of the expenditure of £1,078,000 for the Buildings at Risk programme be authorised; and (v) the capital programme be amended to show the THI planned expenditure of £2,250,000 in the financial years 2003/04 to 2005/06.
Word for word from the decision Liverpool published for this meeting.Source: councillors.liverpool.gov.uk
1. The purpose of this report is to seek approval to accept a North West Development Agency grant and amend the Capital Programme for the Buildings at Risk Project accordingly.
Background
2. The Buildings at Risk (BAR) project commenced in 2001 as a joint- initiative with English Heritage. It addresses the exceptional problems of the city’s dilapidated historic buildings – the issue highlighted in the “Stop the Rot” local media campaign.
3. The awareness of Liverpool’s stock of buildings at risk, and the recognition that the improvement of these buildings is a strategic issue, has allowed the City Council to include £200,000 p.a. for each year (including the previous financial year) up to 2005/06 from general resources in the Capital Programme. During 2002/03, only £90,000 of the available allocation was spent, thus allowing £110,000 to be carried forward into 2003/04. In total therefore, the Council has £310,000 of it’s own resources available for the buildings at risk initiative in 2003/04.
4. The BAR project is an important part of the Council’s regeneration strategy, especially within the city centre. Key aims of the project are to: • resolve the problem of potentially dangerous buildings and buildings that blight an area and discourage investment and development; • re-use vacant and under-used buildings; • assist the supply of properties for residential and commercial use, and; • improve the city’s image. 5. In association with English Heritage and Liverpool Vision, officers have been pursuing a dialogue with the North West Development Agency (NWDA) and English Partnerships (EP), as outlined in the background report EDR/88/02.
6. The North West Development Agency have now determined an application for funding, and have offered up to £968,000 from June 2003, which is to be spent by July 2004. This funding will be used to deliver the following: • 65 Building Owners Contacted • 50 Initial Building Surveys Completed • 30 Detailed Building Surveys Completed • 14 Urgent Works Notices Served • 2 Repairs Notices Served • 6 Building Owners Assisted to Prepare Refurbishment Schemes
7. The framework introduced above will deliver a significant impact on the stock of historic buildings at risk throughout the City of Liverpool, delivering the improvement of the worst of these buildings, and allowing further works to be undertaken in future years.
8. The Buildings at Risk Project has two parts, an NWDA funded programme for action and a THI (Townscape Heritage Initiative), a grant scheme that will assist those owners in the City Centre that wish to improve their properties, but find that this is still not viable. Both schemes are complimentary, but have distinct roles which will assist in the regeneration of Liverpool City Centre.
9. In addition to the City Council’s own capital resources of £310,000 the capital programme for 2003/04 also contains an anticipated level of further expenditure on the Buildings at Risk scheme to be funded by £50,000 of English Heritage grant and £2,000,000 of Heritage Lottery Grant. It is anticipated that this funding profile may change in the light of revised bids for grant funding which are currently being prepared for/considered by grant funding agencies. However, it is requested that the executive members agree to the revised presentation of the capital programme to reflect the two elements of the Buildings at Risk programme so that it shows :
a) A buildings at risk (NWDA) scheme – expenditure of £968,000 funded by grant and complemented by £110,000 of the Councils own capital resources. b) THI – to reflect currently anticipated expenditure of £2,250,000 funded by grant and general capital resources.
Summary
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.